WisDOT contract 20260113026 bid tabulation
Wisconsin Rapids - Plover; 26th Street North to CTH B (STH 054, Portage County Wisconsin Rapids - Plover). Let by Wisconsin DOT on January 13, 2026, Portage. 4 bids received; low bid $7,526,564 by Michels Road & Stone, Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 109
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Michels Road & Stone, Inc. | $7,526,564 | Low |
| 2 | Chippewa Concrete Services, Inc. | $7,620,029 | +1.0% |
| 3 | Zignego Company, Inc. | $8,147,429 | +8.0% |
| 4 | Vinton Construction Company | $8,480,911 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Michels Road & Stone, Inc. | 2. Chippewa Concrete Services, Inc. | 3. Zignego Company, Inc. | 4. Vinton Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Removing asphaltic surface (204.0110) | SY | 3,930 | $22.00 | $6.57 | $5.18 | $13.50 |
| 2 | Removing asphaltic surface butt joints (204.0115) | SY | 1,350 | $1.00 | $5.93 | $6.57 | $6.57 |
| 3 | Removing asphaltic surface milling (204.0120) | SY | 116,750 | $2.62 | $2.61 | $3.60 | $3.60 |
| 4 | Removing curb & gutter (204.0150) | LF | 3,785 | $11.00 | $18.10 | $5.18 | $21.03 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 1,190 | $11.00 | $22.24 | $7.18 | $20.90 |
| 6 | Removing (item description) 01. apron endwalls (204.9060.S) | EACH | 4 | $600.00 | $758.25 | $500.00 | $340.00 |
| 7 | Prepare foundation for asphaltic paving (project) 01. 1520-01-60 (211.0101) | EACH | 1 | $75,000 | $90,176 | $89,195 | $89,195 |
| 8 | Finishing roadway (project) 01. 1520-01-60 (213.0100) | EACH | 1 | $5,000.00 | $5,055.00 | $1,000.00 | $10,000 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 8,200 | $26.00 | $25.02 | $30.93 | $33.00 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,710 | $27.00 | $18.15 | $30.69 | $0.01 |
| 11 | Concrete pavement 9-inch (415.0090) | SY | 38 | $135.00 | $140.11 | $200.00 | $98.00 |
| 12 | Rout and seal (415.6000.S) | LF | 190,000 | $0.65 | $0.66 | $0.65 | $0.66 |
| 13 | Drilled tie bars (416.0610) | EACH | 4,040 | $13.00 | $10.92 | $15.00 | $10.00 |
| 14 | Drilled dowel bars (416.0620) | EACH | 11,640 | $17.00 | $13.85 | $20.00 | $17.50 |
| 15 | Concrete pavement repair (416.1710) | SY | 5,960 | $94.00 | $107.94 | $108.00 | $115.89 |
| 16 | Concrete pavement repair shes (416.1715) | SY | 20 | $107.00 | $112.68 | $500.00 | $185.00 |
| 17 | Concrete pavement replacement (416.1720) | SY | 9,790 | $95.00 | $107.94 | $108.00 | $120.89 |
| 18 | Concrete pavement replacement shes (416.1725) | SY | 310 | $107.00 | $112.68 | $200.00 | $190.00 |
| 19 | Continuous diamond grinding concrete pavement (420.1000) | SY | 276,400 | $3.66 | $3.69 | $3.45 | $3.65 |
| 20 | Tack coat (455.0605) | GAL | 7,940 | $5.24 | $5.30 | $5.24 | $5.24 |
| 21 | Incentive density HMA pavement (460.2000) | DOL | 7,330 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 11,400 | $104.47 | $105.62 | $104.47 | $104.47 |
| 23 | Asphaltic surface (465.0105) | TON | 1,200 | $182.04 | $184.41 | $182.04 | $182.04 |
| 24 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 190,000 | $0.13 | $0.13 | $0.13 | $0.13 |
| 25 | Apron endwalls for culvert pipe reinforced concrete 18-inch (522.1018) | EACH | 2 | $4,500.00 | $3,164.43 | $1,764.00 | $1,980.00 |
| 26 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624) | EACH | 2 | $4,000.00 | $3,942.90 | $2,594.00 | $1,635.00 |
| 27 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 410 | $45.00 | $66.03 | $93.00 | $64.00 |
| 28 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 3,010 | $48.00 | $68.20 | $93.00 | $66.50 |
| 29 | Concrete curb & gutter 6-inch sloped 36-inch type A (601.0555) | LF | 100 | $51.00 | $69.79 | $95.00 | $68.00 |
| 30 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 72 | $51.00 | $69.79 | $95.00 | $68.00 |
| 31 | Concrete curb pedestrian (601.0600) | LF | 335 | $55.00 | $42.00 | $93.00 | $55.00 |
| 32 | Concrete sidewalk 4-inch (602.0405) | SF | 3,940 | $11.00 | $14.61 | $11.00 | $15.25 |
| 33 | Concrete sidewalk 6-inch (602.0415) | SF | 6,465 | $12.00 | $15.50 | $12.00 | $16.00 |
| 34 | Curb ramp detectable warning field natural patina (602.0515) | SF | 540 | $35.00 | $61.18 | $45.00 | $35.00 |
| 35 | Curb ramp detectable warning field radial natural patina (602.0615) | SF | 496 | $47.00 | $68.59 | $75.00 | $60.00 |
| 36 | Concrete safety islands (602.2400) | SF | 250 | $13.00 | $16.42 | $20.00 | $18.00 |
| 37 | Reconstructing inlets (611.0430) | EACH | 17 | $6,200.00 | $1,415.40 | $2,525.00 | $1,500.00 |
| 38 | Inlet covers type H (611.0624) | EACH | 3 | $1,400.00 | $1,627.71 | $1,100.00 | $776.00 |
| 39 | Inlet covers type HM (611.0627) | EACH | 4 | $1,300.00 | $1,627.71 | $1,100.00 | $776.00 |
| 40 | Adjusting inlet covers (611.8115) | EACH | 200 | $650.00 | $945.29 | $1,200.00 | $790.00 |
| 41 | Maintenance and repair of haul roads (project) 01. 1520-01-60 (618.0100) | EACH | 1 | $0.01 | $1.01 | $1.00 | $0.01 |
| 42 | Mobilization (619.1000) | EACH | 1 | $474,168 | $322,826 | $510,000 | $840,000 |
| 43 | Water (624.0100) | MGAL | 140 | $50.00 | $1.01 | $45.00 | $50.00 |
| 44 | Topsoil (625.0100) | SY | 1,920 | $10.00 | $10.62 | $12.00 | $9.50 |
| 45 | Silt fence (628.1504) | LF | 600 | $2.50 | $2.53 | $2.50 | $3.00 |
| 46 | Silt fence maintenance (628.1520) | LF | 300 | $0.01 | $0.01 | $0.01 | $0.01 |
| 47 | Mobilizations erosion control (628.1905) | EACH | 4 | $200.00 | $202.20 | $200.00 | $450.00 |
| 48 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $100.00 | $101.10 | $100.00 | $1.00 |
| 49 | Erosion mat urban class I type A (628.2006) | SY | 1,920 | $1.80 | $1.82 | $1.80 | $3.00 |
| 50 | Inlet protection type B (628.7010) | EACH | 2 | $60.00 | $60.66 | $60.00 | $75.00 |
| 51 | Inlet protection type C (628.7015) | EACH | 217 | $60.00 | $60.66 | $60.00 | $85.00 |
| 52 | Temporary ditch checks (628.7504) | LF | 60 | $9.00 | $9.10 | $9.00 | $10.00 |
| 53 | Culvert pipe checks (628.7555) | EACH | 12 | $20.00 | $20.22 | $20.00 | $10.00 |
| 54 | Seeding mixture no. 40 (630.0140) | LB | 52 | $15.00 | $15.17 | $15.00 | $15.00 |
| 55 | Seed water (630.0500) | MGAL | 49 | $80.00 | $80.88 | $80.00 | $1.00 |
| 56 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 11 | $125.00 | $126.38 | $125.00 | $165.00 |
| 57 | Signs type II reflective H (637.2210) | SF | 50 | $32.00 | $32.35 | $32.00 | $40.00 |
| 58 | Signs type II reflective F (637.2230) | SF | 9 | $32.00 | $32.35 | $32.00 | $40.00 |
| 59 | Field office type C (642.5201) | EACH | 1 | $25,000 | $7,582.50 | $20,000 | $12,000 |
| 60 | Traffic control drums (643.0300) | DAY | 105,000 | $0.15 | $0.15 | $0.15 | $0.15 |
| 61 | Digital speed reduction system (DSRS) (643.0370.S) | DAY | 362 | $95.00 | $96.05 | $95.00 | $95.00 |
| 62 | Traffic control barricades type III (643.0420) | DAY | 13,110 | $0.50 | $0.51 | $0.50 | $0.50 |
| 63 | Traffic control flexible tubular marker posts (643.0500) | EACH | 10 | $50.00 | $50.55 | $50.00 | $50.00 |
| 64 | Traffic control flexible tubular marker bases (643.0600) | EACH | 10 | $20.00 | $20.22 | $20.00 | $20.00 |
| 65 | Traffic control warning lights type A (643.0705) | DAY | 13,110 | $0.25 | $0.25 | $0.25 | $0.25 |
| 66 | Traffic control warning lights type C (643.0715) | DAY | 6,720 | $0.20 | $0.20 | $0.20 | $0.20 |
| 67 | Traffic control connected arrow boards (643.0810) | DAY | 120 | $35.00 | $35.39 | $35.00 | $35.00 |
| 68 | Traffic control signs (643.0900) | DAY | 15,900 | $0.35 | $0.35 | $0.35 | $0.35 |
| 69 | Traffic control signs fixed message (643.1000) | SF | 44 | $15.00 | $15.17 | $15.00 | $15.00 |
| 70 | Traffic control signs PCMS (643.1050) | DAY | 350 | $15.00 | $15.17 | $15.00 | $15.00 |
| 71 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 120 | $20.00 | $20.22 | $20.00 | $20.00 |
| 72 | Temporary marking line removable tape 4-inch (643.3150) | LF | 1,350 | $1.75 | $1.77 | $1.75 | $1.75 |
| 73 | Temporary marking line removable tape 6-inch (643.3180) | LF | 535 | $2.00 | $2.02 | $2.00 | $2.00 |
| 74 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 6,800 | $2.00 | $2.02 | $2.00 | $2.00 |
| 75 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 24 | $6.50 | $6.57 | $6.50 | $6.50 |
| 76 | Traffic control (643.5000) | EACH | 1 | $79,250 | $80,122 | $79,250 | $79,250 |
| 77 | Temporary pedestrian surface matting (644.1440) | SF | 2,860 | $3.00 | $3.03 | $3.00 | $3.00 |
| 78 | Temporary pedestrian curb ramp (644.1601) | DAY | 210 | $33.75 | $34.12 | $33.75 | $33.75 |
| 79 | Temporary pedestrian detectable warning field (644.1605) | SF | 495 | $3.10 | $3.13 | $3.10 | $3.10 |
| 80 | Temporary pedestrian barricade (644.1810) | LF | 4,200 | $4.25 | $4.30 | $4.25 | $4.25 |
| 81 | Temporary audible message devices (644.1900.S) | DAY | 115 | $11.50 | $11.63 | $11.50 | $11.50 |
| 82 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 34,500 | $0.74 | $0.75 | $0.74 | $0.74 |
| 83 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 299,500 | $1.26 | $1.27 | $1.26 | $1.26 |
| 84 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 19,000 | $2.71 | $2.74 | $2.71 | $2.71 |
| 85 | Marking arrow epoxy (646.5020) | EACH | 113 | $249.18 | $251.92 | $249.18 | $249.18 |
| 86 | Marking word epoxy (646.5120) | EACH | 34 | $372.18 | $376.27 | $372.18 | $372.18 |
| 87 | Marking railroad crossing epoxy (646.5320) | EACH | 10 | $3,607.31 | $3,646.99 | $3,607.31 | $3,607.31 |
| 88 | Marking stop line epoxy 18-inch (646.6120) | LF | 725 | $15.42 | $15.59 | $15.42 | $15.42 |
| 89 | Marking yield line epoxy 18-inch (646.6220) | EACH | 32 | $36.83 | $37.24 | $36.83 | $36.83 |
| 90 | Marking diagonal epoxy 12-inch (646.7120) | LF | 175 | $15.02 | $15.19 | $15.02 | $15.02 |
| 91 | Marking chevron epoxy 12-inch (646.7320) | LF | 2,200 | $15.02 | $15.19 | $15.02 | $15.02 |
| 92 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 4,030 | $10.56 | $10.68 | $10.56 | $10.56 |
| 93 | Marking curb epoxy (646.8120) | LF | 3,500 | $7.38 | $7.46 | $7.38 | $7.38 |
| 94 | Marking island nose epoxy (646.8220) | EACH | 110 | $277.32 | $280.37 | $277.32 | $277.32 |
| 95 | Marking removal line 6-inch (646.9002) | LF | 1,750 | $2.00 | $2.02 | $2.00 | $2.00 |
| 96 | Construction staking resurfacing reference (650.8000) | LF | 190,000 | $0.07 | $0.07 | $0.07 | $0.09 |
| 97 | Construction staking curb ramps (650.9000) | EACH | 68 | $117.65 | $118.94 | $117.65 | $129.00 |
| 98 | Construction staking sidewalk (project) 01. 1520-01-60 (650.9500) | EACH | 1 | $1,500.00 | $1,516.50 | $1,500.00 | $1,350.00 |
| 99 | Construction staking supplemental control (project) 01. 1520-01-60 (650.9911) | EACH | 1 | $5,000.00 | $5,055.00 | $5,000.00 | $460.92 |
| 100 | Sawing asphalt (690.0150) | LF | 4,905 | $0.90 | $1.77 | $1.39 | $1.39 |
| 101 | Sawing concrete (690.0250) | LF | 35,810 | $2.50 | $2.38 | $4.25 | $2.25 |
| 102 | Incentive compressive strength concrete pavement (715.0720) | DOL | 150 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | Incentive iri ride (740.0440) | DOL | 72,610 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 |
| 105 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,760 | $5.00 | $5.00 | $5.00 | $5.00 |
| 106 | Special 01. fertilizer for lawn type turf (SPV.0030) | CWT | 1.22 | $100.00 | $101.10 | $100.00 | $500.00 |
| 107 | Special 01. repair and regrout structures (SPV.0060) | EACH | 8 | $4,500.00 | $2,022.00 | $1,150.00 | $1,625.00 |
| 108 | Special 02. reconstructing sanitary manholes (SPV.0060) | EACH | 2 | $6,500.00 | $6,379.41 | $3,500.00 | $7,560.00 |
| 109 | Special 01. preparing topsoil for lawn type turf (SPV.0180) | SY | 1,920 | $0.80 | $0.81 | $0.80 | $2.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.