WisDOT contract 20260113027 bid tabulation

STH 29 - CTH J; N Br Embarrass River Br B-58-0139 (CTH D, Shawano County STH 29 - CTH J). Let by Wisconsin DOT on January 13, 2026, Shawano. 4 bids received.

Owner
Wisconsin DOT
Letting
13 JAN 2026
Pay items
78
Data through
10 NOV 2026

3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
2Sheet Piling Services LLC$737,070+1.0%
3Lunda Construction Company$830,445+14%
4Radtke Contractors Inc.$844,767+16%
WisDOT contract 20260113027: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sheet Piling Services LLC2. Lunda Construction Company3. Radtke Contractors Inc.
1Clearing (201.0105)STA3$500.00$500.00$500.00
2Grubbing (201.0205)STA3$500.00$250.00$500.00
3Removing structure over waterway minimal debris (structure) 01. B-58- 304 (203.0260)EACH1$50,000$205,000$71,183
4Removing asphaltic surface (204.0110)SY851$8.50$5.85$8.50
5Excavation common (205.0100)CY423$20.50$16.35$20.50
6Excavation, hauling, and disposal of creosote contaminated soil (205.0506.S)TON320$95.00$32.00$99.89
7Excavation for structures bridges (structure) 01. B-58-139 (206.1001)EACH1$36,500$10,000$47,052
8Backfill structure type A (210.1500)TON320$25.05$30.15$25.05
9Finishing roadway (project) 01. 6125-02-71 (213.0100)EACH1$0.01$1,000.00$500.00
10Base aggregate dense 3/4-inch (305.0110)TON110$32.50$34.18$32.50
11Base aggregate dense 1 1/4-inch (305.0120)TON725$23.65$28.48$23.65
12Concrete pavement 6-inch (415.0060)SY8$200.00$200.00$200.00
13Drilled tie bars (416.0610)EACH20$15.00$15.00$15.00
14Tack coat (455.0605)GAL85$8.50$8.50$8.50
15Asphaltic surface (465.0105)TON277$120.75$120.75$120.75
16Concrete masonry bridges (502.0100)CY185$900.00$750.00$1,078.40
17Protective surface treatment (502.3200)SY263$2.50$3.00$3.69
18Pigmented surface sealer (502.3210)SY111$2.50$6.00$10.75
19Prestressed girder type I 36W-inch (503.0137)LF332$350.00$290.00$301.66
20Bar steel reinforcement HS structures (505.0400)LB3,680$1.50$1.15$1.33
21Bar steel reinforcement HS coated structures (505.0600)LB24,990$1.60$1.25$1.42
22Bearing pads elastomeric non- laminated (506.2605)EACH8$125.00$150.00$227.21
23Steel diaphragms (structure) 01. B- 58-139 (506.4000)EACH6$1,250.00$1,000.00$1,416.48
24Rubberized membrane waterproofing (516.0500)SY18$18.00$25.00$64.32
25Piling steel HP 10-inch X 42 LB (550.1100)LF760$42.00$50.47$38.28
26Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588)LF85$75.00$75.00$75.00
27Concrete surface drains (602.3010)CY3$1,100.00$1,100.00$1,100.00
28Riprap heavy (606.0300)CY218$75.50$104.21$75.50
29Pipe underdrain wrapped 6-inch (612.0406)LF170$6.15$7.89$6.15
30Anchor assemblies for steel plate beam guard (614.0150)EACH4$250.00$250.00$355.69
31Steel thrie beam structure approach (614.0200)LF41.40$90.00$95.10$90.00
32Steel plate beam guard class A (614.0305)LF112.50$30.00$28.50$30.00
33Steel plate beam guard short radius (614.0345)LF25$35.00$52.00$35.00
34Steel plate beam guard short radius terminal (614.0390)EACH2$2,333.00$3,150.00$2,333.00
35MGS guardrail 3 (614.2300)LF100$30.00$27.69$30.00
36MGS thrie beam transition (614.2500)LF78.80$90.00$98.50$90.00
37MGS guardrail terminal eat (614.2610)EACH2$3,433.00$3,789.00$3,433.00
38Maintenance and repair of haul roads (project) 01. 6125-02-71 (618.0100)EACH1$0.01$250.00$250.00
39Mobilization (619.1000)EACH1$56,300$78,166$116,965
40Water (624.0100)MGAL17$50.00$30.00$50.00
41Salvaged topsoil (625.0500)SY300$3.65$3.90$3.65
42Mobilizations erosion control (628.1905)EACH5$253.00$200.00$253.00
43Mobilizations emergency erosion control (628.1910)EACH3$453.00$200.00$453.00
44Erosion mat urban class I type B (628.2008)SY375$3.00$2.18$3.00
45Turbidity barriers (628.6005)SY190$41.00$52.10$41.00
46Fertilizer type A (629.0205)CWT0.70$400.00$150.00$400.00
47Seeding mixture no. 20 (630.0120)LB50$12.00$8.15$12.00
48Seeding temporary (630.0200)LB40$8.00$3.50$8.00
49Seed water (630.0500)MGAL9$75.00$39.00$75.00
50Posts wood 4X6-inch X 14-FT (634.0614)EACH4$125.00$115.00$125.00
51Signs type II reflective F (637.2230)SF12$50.00$32.00$50.00
52Moving signs type II (638.2102)EACH1$150.00$25.00$150.00
53Removing signs type II (638.2602)EACH4$50.00$10.00$50.00
54Removing small sign supports (638.3000)EACH4$50.00$10.00$50.00
55Moving small sign supports (638.4000)EACH1$150.00$75.00$150.00
56Field office type B (642.5001)EACH1$2,500.00$2,250.00$1,719.36
57Traffic control barricades type III (643.0420)DAY1,430$0.45$0.45$0.45
58Traffic control warning lights type A (643.0705)DAY2,220$0.10$0.10$0.10
59Traffic control signs (643.0900)DAY790$0.45$0.45$0.45
60Traffic control signs fixed message (643.1000)SF36$10.90$10.90$10.90
61Traffic control (643.5000)EACH1$1,925.00$1,925.00$1,925.00
62Geotextile type DF schedule A (645.0111)SY60$5.25$8.10$5.25
63Geotextile type HR (645.0120)SY415$6.05$7.50$6.05
64Marking line epoxy 6-inch (646.2020)LF1,270$4.40$4.40$4.40
65Construction staking subgrade (650.4500)LF421$0.01$0.01$0.01
66Construction staking base (650.5000)LF421$1.28$1.28$1.00
67Construction staking curb gutter and curb & gutter (650.5500)LF85$5.00$5.00$1.00
68Construction staking structure layout (structure) 01. B-58-139 (650.6501)EACH1$3,206.75$3,206.75$3,500.00
69Construction staking concrete pavement (650.7000)LF32$10.00$10.00$0.50
70Construction staking supplemental control (project) 01. 6125-02-71 (650.9911)EACH1$446.98$446.98$911.79
71Construction staking slope stakes (650.9920)LF421$0.90$0.90$2.00
72Sawing asphalt (690.0150)LF69$3.00$5.00$2.95
73Incentive strength concrete structures (715.0502)DOL1,110$1.00$1.00$1.00
74Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00
75Installing and maintaining climbing turtle exclusion fence (999.2100.S)LF1,000$4.13$5.50$4.13
76On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00
77On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00
78Special 01. infill riprap - B-58-139 (SPV.0195)TON88$7.00$36.32$7.00
WisDOT contract 20260113027: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy