WisDOT contract 20260113049 bid tabulation
Ashland - Bayfield; Little Whittlesey Creek B-04-0126 (STH 013, Bayfield County Little Whittlesey Creek Bridge B-04-0126). Let by Wisconsin DOT on January 13, 2026, Bayfield. 2 bids received; low bid $1,491,067 by Northern Interstate Construction, Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 82
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northern Interstate Construction, Inc. | $1,491,067 | Low |
| 2 | Lunda Construction Company | $1,544,763 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northern Interstate Construction, Inc. | 2. Lunda Construction Company |
|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 1 | $3,413.00 | $3,413.83 |
| 2 | Grubbing (201.0205) | STA | 1 | $5,122.00 | $5,122.38 |
| 3 | Removing structure (structure) 01. B-04-0037 (203.0220) | EACH | 1 | $8,084.10 | $32,890 |
| 4 | Removing concrete pavement (204.0100) | SY | 253 | $12.95 | $12.54 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 859 | $12.06 | $11.87 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 1,957 | $10.21 | $7.05 |
| 7 | Excavation common (205.0100) | CY | 5,843 | $11.00 | $11.53 |
| 8 | Excavation for structures bridges (structure) 01. B-04-0126 (206.1001) | EACH | 1 | $8,975.00 | $33,976 |
| 9 | Cofferdams (structure) 01. B-04- 0126 (206.5001) | EACH | 1 | $127,813 | $75,000 |
| 10 | Select borrow (208.1100) | CY | 6,731 | $19.50 | $21.00 |
| 11 | Backfill structure type A (210.1500) | TON | 1,184 | $19.50 | $19.90 |
| 12 | Finishing roadway (project) 01. 8160-00-73 (213.0100) | EACH | 1 | $100.00 | $500.00 |
| 13 | Base aggregate dense 3/4-inch (305.0110) | TON | 100 | $50.00 | $55.00 |
| 14 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,940 | $22.25 | $23.17 |
| 15 | Concrete pavement 6-inch (415.0060) | SY | 126 | $116.51 | $114.23 |
| 16 | Concrete pavement approach slab (415.0410) | SY | 80 | $272.38 | $267.04 |
| 17 | Tack coat (455.0605) | GAL | 453 | $4.36 | $4.27 |
| 18 | Asphaltic surface (465.0105) | TON | 608 | $142.95 | $140.15 |
| 19 | Asphaltic surface temporary (465.0125) | TON | 460 | $142.08 | $139.29 |
| 20 | Concrete masonry bridges (502.0100) | CY | 308 | $808.00 | $800.00 |
| 21 | Protective surface treatment (502.3200) | SY | 352 | $3.06 | $3.00 |
| 22 | Pigmented surface sealer (502.3210) | SY | 72 | $5.10 | $5.00 |
| 23 | Bar steel reinforcement HS structures (505.0400) | LB | 5,180 | $1.38 | $1.35 |
| 24 | Bar steel reinforcement HS coated structures (505.0600) | LB | 42,090 | $1.43 | $1.40 |
| 25 | Bar steel reinforcement HS stainless structures (505.0800.S) | LB | 390 | $4.18 | $4.10 |
| 26 | Temporary shoring (structure) 01. B-04-0126 (511.1200) | SF | 225 | $45.90 | $45.00 |
| 27 | Piling steel sheet temporary (512.1000) | SF | 180 | $54.00 | $45.00 |
| 28 | Rubberized membrane waterproofing (516.0500) | SY | 24 | $25.50 | $25.00 |
| 29 | Culvert pipe temporary 30-inch (520.2030) | LF | 65 | $91.66 | $89.95 |
| 30 | Temporary structure (station) 01. 40+25 (526.0101) | EACH | 1 | $50,000 | $150,000 |
| 31 | Piling cip concrete 10 3/4 X 0.365- inch (550.2106) | LF | 1,680 | $52.50 | $50.00 |
| 32 | Riprap heavy (606.0300) | CY | 67 | $135.55 | $135.00 |
| 33 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $204.00 | $200.00 |
| 34 | MGS guardrail temporary (614.1000) | LF | 420 | $12.92 | $12.60 |
| 35 | MGS guardrail temporary thrie beam transition (614.1100) | LF | 156 | $30.34 | $29.60 |
| 36 | MGS guardrail temporary terminal eat (614.1200) | EACH | 4 | $1,700.48 | $1,659.00 |
| 37 | MGS thrie beam transition (614.2500) | LF | 156 | $97.63 | $95.25 |
| 38 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,666.43 | $3,577.00 |
| 39 | Maintenance and repair of haul roads (project) 01. 8160-00-73 (618.0100) | EACH | 1 | $1.00 | $0.01 |
| 40 | Mobilization (619.1000) | EACH | 1 | $225,000 | $184,819 |
| 41 | Topsoil (625.0105) | CY | 17 | $52.16 | $27.00 |
| 42 | Salvaged topsoil (625.0500) | SY | 1,579 | $6.57 | $5.82 |
| 43 | Mulching (627.0200) | SY | 1,634 | $0.77 | $0.75 |
| 44 | Erosion bales (628.1104) | EACH | 10 | $17.34 | $30.00 |
| 45 | Silt fence (628.1504) | LF | 960 | $2.64 | $2.40 |
| 46 | Silt fence maintenance (628.1520) | LF | 960 | $0.01 | $0.01 |
| 47 | Mobilizations erosion control (628.1905) | EACH | 2 | $525.00 | $2,113.00 |
| 48 | Mobilizations emergency erosion control (628.1910) | EACH | 1 | $262.50 | $300.00 |
| 49 | Erosion mat class I type B (628.2004) | SY | 223 | $1.73 | $1.90 |
| 50 | Turbidity barriers (628.6005) | SY | 44 | $52.80 | $60.00 |
| 51 | Fertilizer type B (629.0210) | CWT | 2.51 | $126.00 | $175.00 |
| 52 | Seeding mixture no. 10 (630.0110) | LB | 30 | $12.96 | $26.25 |
| 53 | Seeding temporary (630.0200) | LB | 50 | $58.25 | $6.95 |
| 54 | Seed water (630.0500) | MGAL | 40 | $26.55 | $0.01 |
| 55 | Delineators temporary (633.1100) | EACH | 44 | $19.11 | $18.00 |
| 56 | Markers culvert end (633.5200) | EACH | 2 | $73.84 | $70.00 |
| 57 | Field office type C (642.5201) | EACH | 1 | $8,500.00 | $4,500.00 |
| 58 | Traffic control drums (643.0300) | DAY | 1,300 | $1.01 | $1.00 |
| 59 | Traffic control barricades type III (643.0420) | DAY | 1,040 | $2.02 | $2.00 |
| 60 | Traffic control warning lights type C (643.0715) | DAY | 1,300 | $0.20 | $0.20 |
| 61 | Traffic control signs (643.0900) | DAY | 2,080 | $2.53 | $2.50 |
| 62 | Temporary marking line paint 6- inch (643.3165) | LF | 3,000 | $0.40 | $1.30 |
| 63 | Temporary marking raised pavement marker type I (643.3760) | EACH | 32 | $4.78 | $4.50 |
| 64 | Traffic control (643.5000) | EACH | 1 | $2,800.73 | $2,773.00 |
| 65 | Geotextile type DF schedule A (645.0111) | SY | 40 | $4.84 | $4.76 |
| 66 | Geotextile type HR (645.0120) | SY | 81 | $8.19 | $8.05 |
| 67 | Geotextile type sas (645.0140) | SY | 2,598 | $1.60 | $2.50 |
| 68 | Marking line epoxy 6-inch (646.2020) | LF | 3,600 | $2.55 | $2.50 |
| 69 | Marking removal line 4-inch (646.9000) | LF | 450 | $0.92 | $0.90 |
| 70 | Construction staking subgrade (650.4500) | LF | 728 | $0.27 | $0.25 |
| 71 | Construction staking base (650.5000) | LF | 728 | $1.33 | $1.25 |
| 72 | Construction staking structure layout (structure) 01. B-04-0126 (650.6501) | EACH | 1 | $3,716.70 | $3,500.00 |
| 73 | Construction staking resurfacing reference (650.8000) | LF | 1,446 | $0.27 | $0.25 |
| 74 | Construction staking supplemental control (project) 01. 8160-00-73 (650.9911) | EACH | 1 | $2,123.83 | $2,000.00 |
| 75 | Construction staking slope stakes (650.9920) | LF | 550 | $2.12 | $2.00 |
| 76 | Sawing asphalt (690.0150) | LF | 136 | $3.72 | $3.10 |
| 77 | Incentive strength concrete structures (715.0502) | DOL | 1,848 | $1.00 | $1.00 |
| 78 | Incentive strength concrete barrier (715.0603) | DOL | 58 | $1.00 | $1.00 |
| 79 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 |
| 80 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 |
| 81 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 |
| 82 | Special 01. relocate access (SPV.0060) | EACH | 1 | $5,000.00 | $8,240.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.