| 1 | Grubbing (201.0205) | STA | 4 | $2,281.10 | $1,000.00 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 3 | $300.00 | $1,000.00 |
| 3 | Removing asphaltic surface (204.0110) | SY | 840 | $6.00 | $15.00 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 1,900 | $19.22 | $8.50 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 221,400 | $1.26 | $2.65 |
| 6 | Removing curb & gutter (204.0150) | LF | 2,670 | $3.50 | $20.00 |
| 7 | Removing concrete sidewalk (204.0155) | SY | 760 | $12.00 | $62.00 |
| 8 | Removing delineators and markers (204.0180) | EACH | 4 | $20.00 | $44.50 |
| 9 | Removing storm sewer (size) 01. 8- inch (204.0245) | LF | 71 | $10.00 | $35.00 |
| 10 | Removing storm sewer (size) 02. 12-inch (204.0245) | LF | 432 | $10.00 | $35.00 |
| 11 | Excavation common (205.0100) | CY | 1,230 | $24.00 | $20.00 |
| 12 | Prepare foundation for asphaltic paving (project) 01. 9250-14-71 (211.0101) | EACH | 1 | $2,376.65 | $2,500.00 |
| 13 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 2 | $558.83 | $2,500.00 |
| 14 | Finishing roadway (project) 01. 9250-14-71 (213.0100) | EACH | 1 | $3,646.95 | $5,000.00 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 3,305 | $33.78 | $28.00 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 600 | $33.00 | $29.00 |
| 17 | Concrete pavement 6-inch (415.0060) | SY | 6 | $95.12 | $85.00 |
| 18 | Tack coat (455.0605) | GAL | 16,550 | $1.90 | $5.00 |
| 19 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $7,523.20 | $9,000.00 |
| 20 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $2,110.00 | $9,000.00 |
| 21 | Incentive density PWL HMA pavement (460.2005) | DOL | 18,070 | $1.00 | $1.00 |
| 22 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 12,100 | $1.00 | $1.00 |
| 23 | Incentive air voids HMA pavement (460.2010) | DOL | 25,200 | $1.00 | $1.00 |
| 24 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 25,200 | $70.28 | $89.55 |
| 25 | Asphaltic surface (465.0105) | TON | 450 | $146.07 | $100.00 |
| 26 | Asphaltic surface patching (465.0110) | TON | 1,250 | $131.84 | $190.00 |
| 27 | Asphaltic surface driveways and field entrances (465.0120) | TON | 35 | $170.19 | $155.00 |
| 28 | Asphaltic rumble strips, centerline (465.0560) | LF | 39,000 | $0.41 | $0.35 |
| 29 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $525.00 | $500.00 |
| 30 | Apron endwalls for culvert pipe 30- inch (520.1030) | EACH | 2 | $810.00 | $750.00 |
| 31 | Culvert pipe class III-A non-metal 24-inch (520.3424) | LF | 40 | $141.00 | $120.00 |
| 32 | Culvert pipe class III-A non-metal 30-inch (520.3430) | LF | 62 | $165.00 | $180.00 |
| 33 | Concrete collars for pipe (520.8000) | EACH | 2 | $950.00 | $500.00 |
| 34 | Apron endwalls for culvert pipe steel 42-inch (521.1042) | EACH | 2 | $1,575.00 | $2,100.00 |
| 35 | Culvert pipe corrugated steel polymer coated 42-inch (521.5142) | LF | 54 | $356.00 | $350.00 |
| 36 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 2,635 | $56.14 | $55.25 |
| 37 | Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557) | LF | 250 | $58.28 | $52.65 |
| 38 | Concrete curb pedestrian (601.0600) | LF | 300 | $49.27 | $51.75 |
| 39 | Concrete sidewalk 4-inch (602.0405) | SF | 8,190 | $14.76 | $10.00 |
| 40 | Curb ramp detectable warning field yellow (602.0505) | SF | 370 | $62.51 | $60.00 |
| 41 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 190 | $67.84 | $65.00 |
| 42 | Concrete driveway 6-inch (602.0810) | SY | 32 | $95.12 | $85.00 |
| 43 | Riprap heavy (606.0300) | CY | 30 | $111.00 | $100.00 |
| 44 | Storm sewer pipe composite 8-inch (608.6008) | LF | 71 | $62.00 | $90.00 |
| 45 | Storm sewer pipe composite 12- inch (608.6012) | LF | 432 | $72.00 | $100.00 |
| 46 | Inlet covers type H (611.0624) | EACH | 6 | $1,100.00 | $1,050.00 |
| 47 | Inlet covers type HM (611.0627) | EACH | 6 | $1,100.00 | $1,050.00 |
| 48 | Inlet covers type Z (611.0666) | EACH | 1 | $1,130.00 | $1,050.00 |
| 49 | Inlets 4-FT diameter (611.3004) | EACH | 1 | $3,450.00 | $3,500.00 |
| 50 | Adjusting manhole covers (611.8110) | EACH | 5 | $550.00 | $1,000.00 |
| 51 | Adjusting inlet covers (611.8115) | EACH | 10 | $650.00 | $850.00 |
| 52 | Adjusting steel plate beam guard (614.0400) | LF | 94 | $31.52 | $15.00 |
| 53 | Replacing guardrail posts and blocks (614.0950) | EACH | 14 | $210.93 | $150.00 |
| 54 | Replacing guardrail rail and hardware (614.0951) | LF | 25 | $66.19 | $25.00 |
| 55 | Maintenance and repair of haul roads (project) 01. 9250-14-71 (618.0100) | EACH | 1 | $1,300.00 | $1,500.00 |
| 56 | Mobilization (619.1000) | EACH | 1 | $153,943 | $384,450 |
| 57 | Water (624.0100) | MGAL | 60 | $48.50 | $50.00 |
| 58 | Topsoil (625.0100) | SY | 2,900 | $3.00 | $5.00 |
| 59 | Silt fence (628.1504) | LF | 850 | $2.20 | $2.75 |
| 60 | Silt fence maintenance (628.1520) | LF | 1,700 | $0.01 | $0.01 |
| 61 | Mobilizations erosion control (628.1905) | EACH | 5 | $500.00 | $500.00 |
| 62 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $300.00 | $500.00 |
| 63 | Erosion mat urban class I type B (628.2008) | SY | 2,900 | $2.29 | $2.20 |
| 64 | Inlet protection type A (628.7005) | EACH | 19 | $106.00 | $100.00 |
| 65 | Inlet protection type C (628.7015) | EACH | 42 | $72.00 | $75.00 |
| 66 | Temporary ditch checks (628.7504) | LF | 50 | $8.95 | $12.00 |
| 67 | Culvert pipe checks (628.7555) | EACH | 15 | $21.30 | $25.00 |
| 68 | Fertilizer type B (629.0210) | CWT | 2 | $110.00 | $100.00 |
| 69 | Seeding mixture no. 30 (630.0130) | LB | 86 | $8.80 | $15.00 |
| 70 | Seeding mixture no. 40 (630.0140) | LB | 44 | $13.80 | $15.00 |
| 71 | Seed water (630.0500) | MGAL | 70 | $50.00 | $25.00 |
| 72 | Markers culvert end (633.5200) | EACH | 4 | $71.00 | $75.00 |
| 73 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 24 | $85.00 | $150.00 |
| 74 | Signs type II reflective H (637.2210) | SF | 72 | $20.00 | $35.00 |
| 75 | Moving signs type II (638.2102) | EACH | 21 | $100.00 | $150.00 |
| 76 | Moving small sign supports (638.4000) | EACH | 21 | $90.00 | $35.00 |
| 77 | Field office type B (642.5001) | EACH | 1 | $11,130 | $10,000 |
| 78 | Traffic control drums (643.0300) | DAY | 3,206 | $2.00 | $0.56 |
| 79 | Traffic control barricades type III (643.0420) | DAY | 700 | $10.00 | $0.75 |
| 80 | Traffic control warning lights type A (643.0705) | DAY | 280 | $1.00 | $0.40 |
| 81 | Traffic control warning lights type C (643.0715) | DAY | 406 | $0.35 | $0.50 |
| 82 | Traffic control signs (643.0900) | DAY | 3,612 | $3.50 | $1.20 |
| 83 | Traffic control covering signs type II (643.0920) | EACH | 1 | $30.00 | $150.00 |
| 84 | Traffic control signs fixed message (643.1000) | SF | 36 | $10.60 | $16.00 |
| 85 | Traffic control cones 42-inch (643.1070) | DAY | 2,758 | $1.00 | $0.50 |
| 86 | Temporary marking line paint 6- inch (643.3165) | LF | 185,300 | $0.36 | $0.25 |
| 87 | Temporary marking line removable tape 6-inch (643.3180) | LF | 9,520 | $1.70 | $1.85 |
| 88 | Temporary marking crosswalk paint 6-inch (643.3305) | LF | 840 | $2.00 | $4.00 |
| 89 | Traffic control (643.5000) | EACH | 1 | $18,100 | $10,000 |
| 90 | Temporary pedestrian surface plate (644.1430) | SF | 150 | $11.00 | $25.00 |
| 91 | Temporary pedestrian surface matting (644.1440) | SF | 2,030 | $5.00 | $5.00 |
| 92 | Temporary pedestrian curb ramp (644.1601) | DAY | 427 | $4.00 | $5.00 |
| 93 | Temporary pedestrian detectable warning field (644.1605) | SF | 488 | $4.00 | $5.00 |
| 94 | Temporary pedestrian barricade (644.1810) | LF | 3,100 | $4.00 | $5.00 |
| 95 | Temporary audible message devices (644.1900.S) | DAY | 56 | $12.00 | $10.00 |
| 96 | Geotextile type HR (645.0120) | SY | 60 | $7.00 | $10.00 |
| 97 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 208,060 | $1.25 | $1.40 |
| 98 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 200 | $2.10 | $3.00 |
| 99 | Marking arrow epoxy (646.5020) | EACH | 4 | $275.00 | $350.00 |
| 100 | Marking word epoxy (646.5120) | EACH | 2 | $350.00 | $350.00 |
| 101 | Marking stop line epoxy 18-inch (646.6120) | LF | 80 | $22.00 | $18.00 |
| 102 | Marking diagonal epoxy 12-inch (646.7120) | LF | 105 | $17.00 | $14.00 |
| 103 | Marking removal line 6-inch (646.9002) | LF | 4,930 | $3.00 | $1.70 |
| 104 | Construction staking storm sewer (650.4000) | EACH | 1 | $800.00 | $800.00 |
| 105 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 2,785 | $1.77 | $1.77 |
| 106 | Construction staking pipe culverts (650.6000) | EACH | 3 | $800.00 | $800.00 |
| 107 | Construction staking resurfacing reference (650.8000) | LF | 60,480 | $0.13 | $0.13 |
| 108 | Construction staking curb ramps (650.9000) | EACH | 47 | $325.00 | $325.00 |
| 109 | Construction staking sidewalk (project) 01. 9250-14-71 (650.9500) | EACH | 1 | $3,000.00 | $3,000.00 |
| 110 | Construction staking supplemental control (project) 01. 9250-14-71 (650.9911) | EACH | 1 | $2,750.00 | $2,750.00 |
| 111 | Construction staking slope stakes (650.9920) | LF | 467 | $1.77 | $1.77 |
| 112 | Public land reference monument verify and reset (680.0100) | EACH | 2 | $900.00 | $900.00 |
| 113 | Sawing asphalt (690.0150) | LF | 3,385 | $3.09 | $3.00 |
| 114 | Sawing concrete (690.0250) | LF | 455 | $11.20 | $5.00 |
| 115 | Incentive iri ride (740.0440) | DOL | 45,820 | $1.00 | $1.00 |
| 116 | Special 01. inlet covers type H-D (SPV.0060) | EACH | 1 | $1,100.00 | $1,200.00 |
| 117 | Special 02. adjusting water valve boxes (SPV.0060) | EACH | 2 | $300.00 | $1,000.00 |
| 118 | Special 03. pipe connection to existing structure (SPV.0060) | EACH | 6 | $1,200.00 | $1,000.00 |
| 119 | Special 01. marking mobile reflectometer measurements (MRM) (SPV.0125) | MI | 39.40 | $155.00 | $260.00 |
| 120 | Special 01. removing distressed asphaltic surface milling (SPV.0180) | SY | 11,150 | $3.02 | $2.50 |
| 121 | Special 02. protective thermoplastic coating at snowmobile trail crossing (SPV.0180) | SY | 390 | $159.85 | $135.00 |