WisDOT contract 20260210046 bid tabulation
C Ashland, Prentice Avenue; Lake Shore Drive to 6th Street E (LOC STR, Ashland County C Ashland, Prentice Ave). Let by Wisconsin DOT on February 10, 2026, Ashland. 4 bids received; low bid $845,876 by Jake'S Excavating & Landscaping, LLC.
- Owner
- Wisconsin DOT
- Letting
- 10 FEB 2026
- Pay items
- 82
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jake'S Excavating & Landscaping, LLC | $845,876 | Low |
| 2 | Ritola Inc | $857,843 | +1.0% |
| 3 | McCabe Construction, Inc. | $946,900 | +12% |
| 4 | James Peterson Sons, Inc. | $1,007,778 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jake'S Excavating & Landscaping, LLC | 2. Ritola Inc | 3. McCabe Construction, Inc. | 4. James Peterson Sons, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0220) | ID | 362 | $13.00 | $12.98 | $21.00 | $30.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 187 | $5.50 | $8.46 | $10.30 | $7.50 |
| 3 | Removing asphaltic surface (204.0110) | SY | 160 | $4.50 | $3.69 | $7.15 | $7.50 |
| 4 | Removing curb & gutter (204.0150) | LF | 3,486 | $4.25 | $2.78 | $4.00 | $3.33 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 789 | $6.00 | $7.70 | $10.50 | $4.00 |
| 6 | Excavation common (205.0100) | CY | 6,232 | $14.25 | $14.90 | $19.30 | $17.95 |
| 7 | Backfill granular grade 1 (209.1500) | TON | 3,931 | $13.60 | $14.51 | $13.15 | $11.17 |
| 8 | Finishing roadway (project) 01. 8895-00-16 (213.0100) | EACH | 1 | $500.00 | $1,157.50 | $1,254.00 | $2,500.00 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 322 | $23.33 | $27.88 | $26.15 | $26.15 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 3,931 | $19.30 | $25.01 | $22.75 | $20.29 |
| 11 | Tack coat (455.0605) | GAL | 381 | $3.50 | $3.15 | $3.25 | $3.10 |
| 12 | Incentive density HMA pavement (460.2000) | DOL | 1,080 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | HMA pavement 3 LT 58-28 S (460.5223) | TON | 960 | $134.84 | $115.53 | $119.00 | $113.78 |
| 14 | HMA pavement 4 LT 58-34 S (460.5244) | TON | 747 | $136.20 | $128.23 | $132.00 | $126.29 |
| 15 | Asphaltic surface (465.0105) | TON | 13 | $300.00 | $297.38 | $306.10 | $292.88 |
| 16 | Asphaltic surface driveways and field entrances (465.0120) | TON | 20 | $320.00 | $322.77 | $333.80 | $317.89 |
| 17 | Concrete collars for pipe (520.8000) | EACH | 1 | $500.00 | $1,181.10 | $1,330.00 | $1,250.00 |
| 18 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 161 | $36.00 | $35.54 | $39.65 | $37.75 |
| 19 | Concrete curb pedestrian (601.0600) | LF | 29 | $101.00 | $101.53 | $43.60 | $41.52 |
| 20 | Concrete sidewalk 4-inch (602.0405) | SF | 5,591 | $7.00 | $6.60 | $14.50 | $13.80 |
| 21 | Concrete sidewalk 6-inch (602.0415) | SF | 218 | $11.00 | $9.14 | $15.60 | $14.85 |
| 22 | Curb ramp detectable warning field yellow (602.0505) | SF | 240 | $71.00 | $71.07 | $65.65 | $62.51 |
| 23 | Concrete driveway 6-inch (602.0810) | SY | 214 | $87.00 | $86.30 | $85.00 | $80.96 |
| 24 | Storm sewer pipe class III-A 12- inch (608.3012) | LF | 52 | $75.00 | $57.65 | $112.00 | $177.95 |
| 25 | Inlet covers type H-S (611.0639) | EACH | 2 | $950.00 | $916.67 | $986.00 | $1,250.00 |
| 26 | Catch basins 2X3-FT (611.1230) | EACH | 2 | $3,700.00 | $5,886.10 | $4,470.00 | $4,639.00 |
| 27 | Adjusting catch basin covers (611.8105) | EACH | 11 | $450.00 | $417.81 | $300.00 | $750.00 |
| 28 | Adjusting manhole covers (611.8110) | EACH | 8 | $350.00 | $428.51 | $455.00 | $1,000.00 |
| 29 | Cover plates temporary (611.8120.S) | EACH | 19 | $75.00 | $80.28 | $168.00 | $250.00 |
| 30 | Maintenance and repair of haul roads (project) 01. 8895-00-16 (618.0100) | EACH | 1 | $250.00 | $1.00 | $1.00 | $150.00 |
| 31 | Mobilization (619.1000) | EACH | 1 | $31,250 | $40,075 | $45,858 | $130,771 |
| 32 | Water (624.0100) | MGAL | 42 | $10.00 | $23.85 | $44.00 | $55.00 |
| 33 | Salvaged topsoil (625.0500) | SY | 2,970 | $2.50 | $3.41 | $6.00 | $6.31 |
| 34 | Mulching (627.0200) | SY | 90 | $2.00 | $1.04 | $5.25 | $5.00 |
| 35 | Silt fence (628.1504) | LF | 80 | $2.50 | $2.80 | $5.25 | $5.00 |
| 36 | Silt fence maintenance (628.1520) | LF | 80 | $0.10 | $0.26 | $0.03 | $0.03 |
| 37 | Mobilizations erosion control (628.1905) | EACH | 8 | $50.00 | $86.81 | $55.50 | $53.00 |
| 38 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $50.00 | $108.52 | $367.00 | $353.00 |
| 39 | Erosion mat urban class I type A (628.2006) | SY | 2,860 | $2.00 | $2.15 | $3.15 | $3.00 |
| 40 | Inlet protection type A (628.7005) | EACH | 16 | $100.00 | $112.77 | $105.00 | $100.00 |
| 41 | Inlet protection type C (628.7015) | EACH | 16 | $50.00 | $75.69 | $78.40 | $75.00 |
| 42 | Tracking pads (628.7560) | EACH | 2 | $750.00 | $1,512.20 | $1,500.00 | $2,500.00 |
| 43 | Fertilizer type A (629.0205) | CWT | 3 | $200.00 | $105.13 | $110.00 | $105.00 |
| 44 | Seeding mixture no. 40 (630.0140) | LB | 140 | $12.00 | $6.39 | $9.40 | $9.00 |
| 45 | Seeding temporary (630.0200) | LB | 90 | $2.50 | $4.78 | $7.30 | $7.00 |
| 46 | Seed water (630.0500) | MGAL | 75 | $6.50 | $11.91 | $5.25 | $5.00 |
| 47 | Posts tubular steel 2X2-inch X 12- FT (634.0812) | EACH | 14 | $225.00 | $197.82 | $261.30 | $250.00 |
| 48 | Signs type II reflective H (637.2210) | SF | 62.65 | $20.00 | $15.61 | $36.60 | $35.00 |
| 49 | Signs type II reflective F (637.2230) | SF | 16.50 | $20.00 | $14.54 | $36.60 | $35.00 |
| 50 | Removing signs type II (638.2602) | EACH | 22 | $25.00 | $21.02 | $31.35 | $30.00 |
| 51 | Removing small sign supports (638.3000) | EACH | 14 | $25.00 | $21.02 | $31.35 | $30.00 |
| 52 | Field office type C (642.5201) | EACH | 1 | $10,000 | $2,315.00 | $7,500.00 | $8,000.00 |
| 53 | Traffic control barricades type III (643.0420) | DAY | 2,436 | $1.60 | $0.78 | $0.75 | $0.73 |
| 54 | Traffic control warning lights type A (643.0705) | DAY | 4,872 | $0.28 | $0.12 | $0.10 | $0.11 |
| 55 | Traffic control signs (643.0900) | DAY | 4,320 | $1.60 | $0.50 | $0.50 | $0.47 |
| 56 | Traffic control signs PCMS (643.1050) | DAY | 14 | $60.00 | $56.28 | $55.00 | $52.58 |
| 57 | Temporary marking crosswalk removable tape 6-inch (643.3350) | LF | 96 | $1.80 | $6.23 | $6.45 | $6.14 |
| 58 | Traffic control (643.5000) | EACH | 1 | $2,900.00 | $8,087.98 | $7,000.00 | $6,686.00 |
| 59 | Temporary pedestrian surface matting (644.1440) | SF | 1,445 | $4.00 | $5.39 | $4.00 | $3.82 |
| 60 | Temporary pedestrian curb ramp (644.1601) | DAY | 700 | $4.10 | $6.48 | $5.10 | $4.84 |
| 61 | Temporary pedestrian detectable warning field (644.1605) | SF | 100 | $4.10 | $9.67 | $8.20 | $7.82 |
| 62 | Temporary pedestrian barricade (644.1810) | LF | 583 | $4.60 | $6.96 | $5.55 | $5.29 |
| 63 | Geogrid type SR (645.0220) | SY | 9,122 | $1.65 | $1.49 | $1.50 | $2.59 |
| 64 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 704 | $13.00 | $17.26 | $17.80 | $17.00 |
| 65 | Marking crosswalk epoxy block style 24-inch (646.7520) | LF | 30 | $27.00 | $37.57 | $38.70 | $37.00 |
| 66 | Marking curb epoxy (646.8120) | LF | 534 | $15.75 | $10.15 | $10.45 | $10.00 |
| 67 | Construction staking storm sewer (650.4000) | EACH | 2 | $550.00 | $406.14 | $418.00 | $400.00 |
| 68 | Construction staking subgrade (650.4500) | LF | 1,760 | $0.01 | $0.01 | $0.01 | $0.01 |
| 69 | Construction staking base (650.5000) | LF | 1,760 | $1.00 | $1.17 | $1.20 | $1.15 |
| 70 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 3,622 | $1.60 | $1.52 | $1.60 | $1.50 |
| 71 | Construction staking curb ramps (650.9000) | EACH | 12 | $260.00 | $101.54 | $105.00 | $100.00 |
| 72 | Construction staking sidewalk (project) 01. 8895-00-16 (650.9500) | EACH | 1 | $500.00 | $1,776.86 | $1,838.00 | $1,750.00 |
| 73 | Construction staking supplemental control (project) 01. 8895-00-16 (650.9911) | EACH | 1 | $2,500.00 | $2,030.69 | $2,100.00 | $2,000.00 |
| 74 | Construction staking slope stakes (650.9920) | LF | 1,760 | $1.60 | $1.02 | $1.05 | $1.00 |
| 75 | Sawing asphalt (690.0150) | LF | 404 | $2.50 | $1.87 | $1.95 | $1.84 |
| 76 | Sawing concrete (690.0250) | LF | 733 | $3.00 | $2.78 | $2.90 | $2.74 |
| 77 | Incentive iri ride (740.0440) | DOL | 1,312 | $1.00 | $1.00 | $1.00 | $1.00 |
| 78 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 79 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 80 | Special 01. concrete curb & gutter 24-inch type D (SPV.0090) | LF | 3,347 | $22.25 | $22.34 | $20.00 | $19.04 |
| 81 | Special 08. concrete curb & gutter 6-inch sloped 24-inch type D (SPV.0090) | LF | 114 | $37.00 | $35.54 | $39.00 | $37.10 |
| 82 | Special 01. concrete sidewalk 8- inch (SPV.0165) | SF | 492 | $15.00 | $15.83 | $16.35 | $15.59 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.