WisDOT contract 20260310032 bid tabulation
STH 29 - CTH N; Eau Claire River Bridge B-37-0495 (CTH J, Marathon County STH 29 - CTH N). Let by Wisconsin DOT on March 10, 2026, Marathon. 4 bids received; low bid $1,960,083 by Sheet Piling Services LLC.
- Owner
- Wisconsin DOT
- Letting
- 10 MAR 2026
- Pay items
- 83
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sheet Piling Services LLC | $1,960,083 | Low |
| 3 | Lunda Construction Company | $2,276,268 | +16% |
| 4 | Zenith Tech., Inc. - Waukesha | $2,381,123 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sheet Piling Services LLC | 2. Lunda Construction Company | 3. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 7 | $850.00 | $850.00 | $850.00 |
| 2 | Grubbing (201.0205) | STA | 7 | $850.00 | $850.00 | $850.00 |
| 3 | Removing structure over waterway minimal debris (structure) 01. B-37- 0023 (203.0260) | EACH | 1 | $325,000 | $200,000 | $271,000 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 65 | $7.00 | $7.00 | $7.00 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 590 | $7.00 | $7.00 | $7.00 |
| 6 | Removing guardrail (204.0165) | LF | 630 | $3.79 | $3.79 | $3.79 |
| 7 | Excavation common (205.0100) | CY | 389 | $18.05 | $18.05 | $18.05 |
| 8 | Excavation marsh (205.0400) | CY | 420 | $13.03 | $13.03 | $13.03 |
| 9 | Excavation for structures bridges (structure) 01. B-37-0495 (206.1001) | EACH | 1 | $100,000 | $50,000 | $30,100 |
| 10 | Cofferdams (structure) 01. B-37- 0495 (206.5001) | EACH | 1 | $125,000 | $200,000 | $30,000 |
| 11 | Borrow (208.0100) | CY | 1,609 | $16.31 | $16.31 | $16.31 |
| 12 | Select borrow (208.1100) | CY | 630 | $29.07 | $29.07 | $29.07 |
| 13 | Backfill structure type A (210.1500) | TON | 480 | $22.55 | $25.00 | $22.55 |
| 14 | Finishing roadway (project) 01. 9471-00-70 (213.0100) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 150 | $29.50 | $29.50 | $29.50 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,550 | $21.18 | $21.18 | $21.18 |
| 17 | Tack coat (455.0605) | GAL | 120 | $6.40 | $6.40 | $6.40 |
| 18 | Asphaltic surface (465.0105) | TON | 360 | $108.94 | $108.94 | $108.94 |
| 19 | Concrete masonry bridges (502.0100) | CY | 515 | $750.00 | $800.00 | $1,495.00 |
| 20 | Protective surface treatment (502.3200) | SY | 800 | $2.50 | $5.00 | $6.00 |
| 21 | Pigmented surface sealer (502.3210) | SY | 200 | $2.50 | $8.00 | $18.00 |
| 22 | Prestressed girder type I 36W-inch (503.0137) | LF | 786 | $275.00 | $300.00 | $278.46 |
| 23 | Bar steel reinforcement HS structures (505.0400) | LB | 11,430 | $1.25 | $1.28 | $1.49 |
| 24 | Bar steel reinforcement HS coated structures (505.0600) | LB | 63,430 | $1.35 | $1.46 | $1.44 |
| 25 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 24 | $125.00 | $100.00 | $156.52 |
| 26 | Steel diaphragms (structure) 01. B- 37-0495 (506.4000) | EACH | 12 | $1,000.00 | $800.00 | $1,121.61 |
| 27 | Rubberized membrane waterproofing (516.0500) | SY | 16 | $18.00 | $25.00 | $75.00 |
| 28 | Pre-boring rock or consolidated materials (550.0020) | LF | 843 | $125.00 | $191.00 | $237.90 |
| 29 | Pile points (550.0500) | EACH | 26 | $150.00 | $200.00 | $126.60 |
| 30 | Piling steel HP 12-inch X 53 LB (550.1120) | LF | 1,230 | $50.00 | $60.00 | $90.00 |
| 31 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 108 | $61.68 | $61.68 | $61.68 |
| 32 | Concrete surface drains (602.3010) | CY | 2 | $1,163.42 | $1,163.42 | $1,163.42 |
| 33 | Riprap medium (606.0200) | CY | 6 | $60.56 | $60.56 | $60.56 |
| 34 | Riprap heavy (606.0300) | CY | 490 | $60.56 | $60.00 | $60.56 |
| 35 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 170 | $6.50 | $10.00 | $6.50 |
| 36 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $250.00 | $200.00 | $300.00 |
| 37 | MGS guardrail 3 (614.2300) | LF | 325 | $31.75 | $31.75 | $31.75 |
| 38 | MGS thrie beam transition (614.2500) | LF | 157.60 | $98.89 | $98.89 | $98.89 |
| 39 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,800.00 | $3,800.00 | $3,800.00 |
| 40 | Maintenance and repair of haul roads (project) 01. 9471-00-70 (618.0100) | EACH | 1 | $0.01 | $0.01 | $2,500.00 |
| 41 | Mobilization (619.1000) | EACH | 1 | $178,525 | $466,740 | $255,300 |
| 42 | Water (624.0100) | MGAL | 50 | $25.00 | $25.00 | $25.00 |
| 43 | Topsoil (625.0100) | SY | 2,270 | $4.55 | $4.55 | $4.55 |
| 44 | Mulching (627.0200) | SY | 540 | $1.00 | $1.00 | $1.00 |
| 45 | Silt fence (628.1504) | LF | 1,470 | $3.85 | $3.85 | $3.85 |
| 46 | Silt fence maintenance (628.1520) | LF | 2,940 | $0.10 | $0.10 | $0.10 |
| 47 | Mobilizations erosion control (628.1905) | EACH | 5 | $100.00 | $100.00 | $100.00 |
| 48 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $100.00 | $100.00 | $100.00 |
| 49 | Erosion mat class II type C (628.2027) | SY | 1,740 | $3.56 | $3.56 | $3.56 |
| 50 | Turbidity barriers (628.6005) | SY | 50 | $0.01 | $56.50 | $56.50 |
| 51 | Temporary ditch checks (628.7504) | LF | 50 | $15.10 | $15.10 | $15.10 |
| 52 | Fertilizer type B (629.0210) | CWT | 2 | $100.00 | $100.00 | $100.00 |
| 53 | Seeding mixture no. 20 (630.0120) | LB | 100 | $6.50 | $6.50 | $6.50 |
| 54 | Seed water (630.0500) | MGAL | 50 | $25.00 | $25.00 | $25.00 |
| 55 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $135.00 | $135.00 | $135.00 |
| 56 | Signs type II reflective F (637.2230) | SF | 12 | $30.00 | $30.00 | $30.00 |
| 57 | Removing signs type II (638.2602) | EACH | 4 | $20.00 | $20.00 | $20.00 |
| 58 | Removing small sign supports (638.3000) | EACH | 4 | $20.00 | $20.00 | $20.00 |
| 59 | Field office type B (642.5001) | EACH | 1 | $4,000.00 | $6,000.00 | $9,000.00 |
| 60 | Traffic control barricades type III (643.0420) | DAY | 1,644 | $0.30 | $0.30 | $0.30 |
| 61 | Traffic control warning lights type A (643.0705) | DAY | 2,192 | $0.10 | $0.10 | $0.10 |
| 62 | Traffic control signs (643.0900) | DAY | 18,495 | $0.30 | $0.30 | $0.30 |
| 63 | Traffic control covering signs type I (643.0910) | EACH | 2 | $600.00 | $600.00 | $600.00 |
| 64 | Traffic control covering signs type II (643.0920) | EACH | 5 | $30.00 | $30.00 | $30.00 |
| 65 | Traffic control signs PCMS (643.1050) | DAY | 14 | $45.00 | $45.00 | $45.00 |
| 66 | Traffic control (643.5000) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 67 | Geotextile type DF schedule A (645.0111) | SY | 120 | $8.10 | $5.00 | $8.10 |
| 68 | Geotextile type HR (645.0120) | SY | 860 | $6.99 | $5.00 | $6.99 |
| 69 | Marking line epoxy 6-inch (646.2020) | LF | 2,010 | $2.50 | $2.50 | $2.50 |
| 70 | Construction staking subgrade (650.4500) | LF | 201 | $0.01 | $0.01 | $0.01 |
| 71 | Construction staking base (650.5000) | LF | 201 | $1.50 | $1.50 | $1.50 |
| 72 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 108 | $1.00 | $1.00 | $1.00 |
| 73 | Construction staking structure layout (structure) 01. B-37-0495 (650.6501) | EACH | 1 | $4,200.00 | $4,200.00 | $4,200.00 |
| 74 | Construction staking resurfacing reference (650.8000) | LF | 190 | $1.00 | $1.00 | $1.00 |
| 75 | Construction staking supplemental control (project) 01. 9471-00-70 (650.9911) | EACH | 1 | $600.00 | $600.00 | $600.00 |
| 76 | Construction staking slope stakes (650.9920) | LF | 420 | $2.50 | $2.50 | $2.50 |
| 77 | Sawing asphalt (690.0150) | LF | 55 | $6.00 | $6.00 | $6.00 |
| 78 | Incentive strength concrete structures (715.0502) | DOL | 2,664 | $1.00 | $1.00 | $1.00 |
| 79 | Maintaining bird deterrent system (station) 01. sta 10+00 (999.2005.S) | EACH | 1 | $0.01 | $0.01 | $5,000.00 |
| 80 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 1,550 | $5.80 | $5.80 | $5.80 |
| 81 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 |
| 82 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,260 | $5.00 | $5.00 | $5.00 |
| 83 | Special 01. infill riprap - B-37-0495 (SPV.0195) | TON | 125 | $35.90 | $50.00 | $35.90 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.