WisDOT contract 20260811002 bid tabulation
STH 33 - CTH W (CTH X); Baraboo River Bridge B-56-0245 (CTH X, Sauk County STH 33 - CTH W (CTH X)). Let by Wisconsin DOT on August 11, 2026, Sauk. 5 bids received; low bid $1,536,977 by Sheet Piling Services LLC.
- Owner
- Wisconsin DOT
- Letting
- 11 AUG 2026
- Pay items
- 78
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sheet Piling Services LLC | $1,536,977 | Low |
| 2 | Radtke Contractors Inc. | $1,722,864 | +12% |
| 3 | Kraemer North America, LLC | $1,727,224 | +12% |
| 4 | Lunda Construction Company | $1,741,697 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sheet Piling Services LLC | 2. Radtke Contractors Inc. | 3. Kraemer North America, LLC | 4. Lunda Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 4 | $1,875.00 | $3,575.00 | $3,575.00 | $1,875.00 |
| 2 | Grubbing (201.0205) | STA | 4 | $1,875.00 | $725.00 | $725.00 | $1,875.00 |
| 3 | Removing structure over waterway minimal debris (structure) 01. B-56- 0020 (203.0260) | EACH | 1 | $185,000 | $150,335 | $200,000 | $120,000 |
| 4 | Removing asphaltic surface (204.0110) | SY | 300 | $9.00 | $9.00 | $9.00 | $9.00 |
| 5 | Excavation common (205.0100) | CY | 1,260 | $16.50 | $16.50 | $16.50 | $16.50 |
| 6 | Excavation for structures bridges (structure) 01. B-56-0245 (206.1001) | EACH | 1 | $95,000 | $121,426 | $75,000 | $40,000 |
| 7 | Cofferdams (structure) 01. B-56- 0245 (206.5001) | EACH | 1 | $30,000 | $212,959 | $200,000 | $100,000 |
| 8 | Backfill structure type A (210.1500) | TON | 170 | $45.00 | $36.85 | $35.00 | $28.00 |
| 9 | Prepare foundation for asphaltic paving (project) 01. 5090-00-70 (211.0101) | EACH | 1 | $6,500.00 | $5,000.00 | $6,500.00 | $6,500.00 |
| 10 | Finishing roadway (project) 01. 5090-00-70 (213.0100) | EACH | 1 | $750.00 | $750.00 | $750.00 | $750.00 |
| 11 | Base aggregate dense 3/4-inch (305.0110) | TON | 160 | $25.00 | $25.00 | $25.00 | $25.00 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 1,040 | $22.50 | $22.50 | $22.50 | $22.50 |
| 13 | Breaker run (311.0110) | TON | 1,010 | $20.50 | $20.50 | $20.50 | $20.50 |
| 14 | Tack coat (455.0605) | GAL | 52 | $3.00 | $3.00 | $3.00 | $3.00 |
| 15 | Asphaltic surface (465.0105) | TON | 296 | $103.00 | $103.00 | $103.00 | $103.00 |
| 16 | Concrete masonry bridges (502.0100) | CY | 714 | $875.00 | $680.09 | $800.00 | $950.00 |
| 17 | Protective surface treatment (502.3200) | SY | 560 | $5.00 | $3.68 | $2.00 | $5.00 |
| 18 | Pigmented surface sealer (502.3210) | SY | 202 | $5.00 | $11.67 | $7.00 | $10.00 |
| 19 | Underwater substructure inspection (structure) 01. B-56-0245 (502.9000.S) | EACH | 2 | $3,500.00 | $5,000.00 | $5,400.00 | $5,500.00 |
| 20 | Bar steel reinforcement HS structures (505.0400) | LB | 9,750 | $1.35 | $1.56 | $1.10 | $1.15 |
| 21 | Bar steel reinforcement HS coated structures (505.0600) | LB | 91,150 | $1.45 | $1.25 | $1.25 | $1.25 |
| 22 | Rubberized membrane waterproofing (516.0500) | SY | 16 | $30.00 | $75.64 | $9.00 | $25.00 |
| 23 | Pile points (550.0500) | EACH | 20 | $320.00 | $332.33 | $310.00 | $400.00 |
| 24 | Piling cip concrete 12 3/4 X 0.375- inch (550.2126) | LF | 1,050 | $75.00 | $60.63 | $93.00 | $68.00 |
| 25 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 125 | $80.27 | $80.27 | $80.27 | $80.27 |
| 26 | Concrete surface drains (602.3010) | CY | 4 | $2,239.33 | $2,239.33 | $2,239.33 | $2,239.33 |
| 27 | Riprap medium (606.0200) | CY | 12 | $70.00 | $70.00 | $70.00 | $70.00 |
| 28 | Riprap heavy (606.0300) | CY | 250 | $75.00 | $98.46 | $120.00 | $65.00 |
| 29 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 190 | $10.00 | $4.25 | $6.00 | $9.00 |
| 30 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $350.00 | $365.69 | $30.00 | $150.00 |
| 31 | MGS thrie beam transition (614.2500) | LF | 160 | $96.00 | $96.00 | $96.00 | $95.00 |
| 32 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,500.00 | $3,500.00 | $3,500.00 | $4,200.00 |
| 33 | Maintenance and repair of haul roads (project) 01. 5090-00-70 (618.0100) | EACH | 1 | $0.01 | $698.74 | $1,000.00 | $1.00 |
| 34 | Mobilization (619.1000) | EACH | 1 | $89,341 | $247,068 | $154,885 | $284,518 |
| 35 | Water (624.0100) | MGAL | 34 | $0.01 | $0.01 | $0.01 | $0.01 |
| 36 | Topsoil (625.0105) | CY | 56 | $45.00 | $45.00 | $45.00 | $45.00 |
| 37 | Salvaged topsoil (625.0500) | SY | 1,990 | $4.00 | $4.00 | $4.00 | $4.00 |
| 38 | Mulching (627.0200) | SY | 1,990 | $0.30 | $0.30 | $0.30 | $1.00 |
| 39 | Silt fence (628.1504) | LF | 1,020 | $2.50 | $2.50 | $2.50 | $3.00 |
| 40 | Silt fence maintenance (628.1520) | LF | 2,040 | $0.01 | $0.01 | $0.01 | $0.01 |
| 41 | Mobilizations erosion control (628.1905) | EACH | 7 | $200.00 | $200.00 | $200.00 | $100.00 |
| 42 | Mobilizations emergency erosion control (628.1910) | EACH | 5 | $300.00 | $300.00 | $300.00 | $100.00 |
| 43 | Erosion mat urban class I type B (628.2008) | SY | 340 | $3.00 | $3.00 | $3.00 | $3.00 |
| 44 | Polyethylene sheeting (628.5505) | SY | 1,510 | $0.01 | $2.37 | $0.01 | $3.00 |
| 45 | Temporary ditch checks (628.7504) | LF | 64 | $9.25 | $9.25 | $9.25 | $15.00 |
| 46 | Fertilizer type B (629.0210) | CWT | 2 | $60.00 | $60.00 | $60.00 | $150.00 |
| 47 | Seeding mixture no. 20 (630.0120) | LB | 94 | $9.00 | $9.00 | $9.00 | $15.00 |
| 48 | Seeding mixture no. 75 (630.0175) | LB | 12 | $70.00 | $70.00 | $70.00 | $85.00 |
| 49 | Seeding temporary (630.0200) | LB | 56 | $2.00 | $2.00 | $2.00 | $7.00 |
| 50 | Seed water (630.0500) | MGAL | 89 | $1.00 | $1.00 | $1.00 | $10.00 |
| 51 | Markers row (633.5100) | EACH | 10 | $60.00 | $60.00 | $60.00 | $70.00 |
| 52 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 5 | $85.00 | $85.00 | $85.00 | $90.00 |
| 53 | Signs type II reflective H (637.2210) | SF | 6.19 | $22.00 | $22.00 | $22.00 | $30.00 |
| 54 | Signs type II reflective F (637.2230) | SF | 17.56 | $25.00 | $25.00 | $25.00 | $30.00 |
| 55 | Removing signs type II (638.2602) | EACH | 7 | $40.00 | $40.00 | $40.00 | $40.00 |
| 56 | Removing small sign supports (638.3000) | EACH | 5 | $40.00 | $40.00 | $40.00 | $40.00 |
| 57 | Field office type B (642.5001) | EACH | 1 | $2,000.00 | $3,438.72 | $7,500.00 | $5,500.00 |
| 58 | Traffic control barricades type III (643.0420) | DAY | 2,844 | $0.50 | $0.50 | $0.40 | $0.40 |
| 59 | Traffic control warning lights type A (643.0705) | DAY | 4,424 | $0.10 | $0.10 | $0.01 | $0.01 |
| 60 | Traffic control signs (643.0900) | DAY | 2,212 | $0.50 | $0.50 | $0.45 | $0.45 |
| 61 | Traffic control signs PCMS (643.1050) | DAY | 14 | $95.00 | $95.00 | $60.00 | $60.00 |
| 62 | Traffic control (643.5000) | EACH | 1 | $1,500.00 | $3,000.00 | $4,400.00 | $4,400.00 |
| 63 | Geotextile type DF schedule A (645.0111) | SY | 60 | $5.00 | $6.27 | $1.60 | $9.00 |
| 64 | Geotextile type HR (645.0120) | SY | 440 | $5.00 | $6.87 | $1.90 | $8.00 |
| 65 | Marking line epoxy 4-inch (646.1020) | LF | 1,560 | $2.99 | $2.99 | $2.99 | $2.99 |
| 66 | Construction staking subgrade (650.4500) | LF | 341 | $1.80 | $0.01 | $1.80 | $1.80 |
| 67 | Construction staking base (650.5000) | LF | 341 | $1.80 | $2.00 | $1.80 | $1.80 |
| 68 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 125 | $4.55 | $4.00 | $4.55 | $4.55 |
| 69 | Construction staking structure layout (structure) 01. B-56-0245 (650.6501) | EACH | 1 | $3,250.00 | $5,000.00 | $3,250.00 | $3,250.00 |
| 70 | Construction staking supplemental control (project) 01. 5090-00-70 (650.9911) | EACH | 1 | $3,450.00 | $2,500.00 | $3,450.00 | $3,450.00 |
| 71 | Construction staking slope stakes (650.9920) | LF | 341 | $2.55 | $2.00 | $2.55 | $2.55 |
| 72 | Sawing asphalt (690.0150) | LF | 45 | $8.00 | $2.95 | $2.95 | $8.00 |
| 73 | Incentive strength concrete structures (715.0502) | DOL | 4,284 | $1.00 | $1.00 | $1.00 | $1.00 |
| 74 | Installing and maintaining bird deterrent system (station) 01. sta. 12+62 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $0.01 | $1.00 |
| 75 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 | $5.00 |
| 76 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 77 | Special 01. site mowing (SPV.0060) | EACH | 10 | $450.00 | $450.00 | $450.00 | $1,800.00 |
| 78 | Special 01. temporary pedestrian portage (SPV.0060) | EACH | 1 | $3,000.00 | $10,266 | $0.01 | $6,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of August 11, 2026. Compiled by Mirage Metrics.