WisDOT contract 20260915016 bid tabulation
Plainfield - Stevens Point; CTH O to STH 54, Nb (IH 039, Portage County Plainfield - Stevens Point). Let by Wisconsin DOT on September 15, 2026, Portage. 2 bids received; low bid $9,544,602 by American Asphalt of Wisconsin.
- Owner
- Wisconsin DOT
- Letting
- 15 SEP 2026
- Pay items
- 160
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | American Asphalt of Wisconsin | $9,544,602 | Low |
| 2 | Rock Road Companies, Inc. | $11,774,713 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. American Asphalt of Wisconsin | 2. Rock Road Companies, Inc. |
|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 8 | $2,000.00 | $2,000.00 |
| 2 | Removing structure (structure) 01. sta 1376+57 (203.0220) | EACH | 1 | $2,000.00 | $2,000.00 |
| 3 | Removing concrete pavement (204.0100) | SY | 3,822 | $20.00 | $20.00 |
| 4 | Removing asphaltic surface (204.0110) | SY | 445 | $20.00 | $20.00 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 453 | $4.28 | $7.17 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 403,060 | $0.46 | $2.23 |
| 7 | Removing curb & gutter (204.0150) | LF | 8 | $20.00 | $20.00 |
| 8 | Removing guardrail (204.0165) | LF | 4,105 | $2.03 | $3.50 |
| 9 | Removing fence (204.0170) | LF | 210 | $5.00 | $3.10 |
| 10 | Removing concrete slope paving (204.0175) | SY | 26 | $36.00 | $25.00 |
| 11 | Removing delineators and markers (204.0180) | EACH | 51 | $15.00 | $29.65 |
| 12 | Removing inlets (204.0220) | EACH | 1 | $500.00 | $500.00 |
| 13 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 72 | $25.00 | $25.00 |
| 14 | Removing storm sewer (size) 02. 30-inch (204.0245) | LF | 27 | $25.00 | $25.00 |
| 15 | Excavation common (205.0100) | CY | 5,910 | $15.00 | $15.00 |
| 16 | Prepare foundation for asphaltic paving (project) 01. 1166-05-80 (211.0101) | EACH | 1 | $32,944 | $0.01 |
| 17 | Finishing roadway (project) 01. 1166-05-80 (213.0100) | EACH | 1 | $8,000.00 | $4,976.72 |
| 18 | Base aggregate dense 3/4-inch (305.0110) | TON | 4,684 | $35.00 | $33.45 |
| 19 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 4,415 | $35.00 | $35.00 |
| 20 | Drilled tie bars (416.0610) | EACH | 160 | $13.69 | $13.69 |
| 21 | Drilled dowel bars (416.0620) | EACH | 139 | $18.38 | $18.38 |
| 22 | Concrete pavement replacement (416.1720) | SY | 198 | $216.00 | $216.00 |
| 23 | Tack coat (455.0605) | GAL | 46,335 | $2.22 | $3.19 |
| 24 | HMA percent within limits (PWL) test strip volumetrics (460.0105.S) | EACH | 1 | $5,000.00 | $3,500.00 |
| 25 | HMA percent within limits (PWL) test strip density (460.0110.S) | EACH | 1 | $5,000.00 | $3,500.00 |
| 26 | HMA pavement test strip volumetrics (460.0115.S) | EACH | 1 | $5,000.00 | $3,500.00 |
| 27 | HMA test strip density (460.0120.S) | EACH | 1 | $5,000.00 | $3,500.00 |
| 28 | Incentive density HMA pavement (460.2000) | DOL | 34,160 | $1.00 | $1.00 |
| 29 | Incentive density PWL HMA pavement (460.2005) | DOL | 21,920 | $1.00 | $1.00 |
| 30 | Incentive density HMA pavement longitudinal joints (460.2007) | DOL | 17,440 | $1.00 | $1.00 |
| 31 | Incentive air voids HMA pavement (460.2010) | DOL | 26,163 | $1.00 | $1.00 |
| 32 | HMA pavement 4 MT 58-28 S (460.6224) | TON | 21,950 | $80.23 | $82.40 |
| 33 | HMA pavement 4 HT 58-28 S (460.7224) | TON | 26,163 | $80.23 | $83.11 |
| 34 | HMA pavement 4 SMA 58-28 H (460.8424) | TON | 27,160 | $80.23 | $102.82 |
| 35 | Material transfer vehicle (460.9000.S) | EACH | 1 | $25,000 | $0.01 |
| 36 | Asphaltic surface (465.0105) | TON | 1,787 | $90.45 | $130.27 |
| 37 | Asphaltic surface patching (465.0110) | TON | 707 | $93.67 | $126.63 |
| 38 | Asphaltic flumes (465.0315) | SY | 103 | $52.29 | $72.50 |
| 39 | Asphaltic rumble strips, shoulder divided roadway (465.0510) | LF | 173,460 | $0.13 | $0.10 |
| 40 | Temporary shoring (511.1100) | SF | 9,450 | $18.25 | $24.00 |
| 41 | Apron endwalls for culvert pipe 30- inch (520.1030) | EACH | 1 | $1,500.00 | $1,500.00 |
| 42 | Concrete collars for pipe (520.8000) | EACH | 6 | $1,000.00 | $1,000.00 |
| 43 | Apron endwalls for culvert pipe steel 12-inch (521.1012) | EACH | 1 | $600.00 | $600.00 |
| 44 | Culvert pipe corrugated steel 30- inch (521.3130) | LF | 13 | $150.00 | $150.00 |
| 45 | Culvert pipe reinforced concrete class III 30-inch (522.0130) | LF | 160 | $175.00 | $175.00 |
| 46 | Culvert pipe reinforced concrete class IV 24-inch (522.0424) | LF | 77 | $150.00 | $150.00 |
| 47 | Culvert pipe reinforced concrete class IV 30-inch (522.0430) | LF | 80 | $175.00 | $175.00 |
| 48 | Culvert pipe reinforced concrete class IV 36-inch (522.0436) | LF | 80 | $200.00 | $200.00 |
| 49 | Culvert pipe reinforced concrete class IV 48-inch (522.0448) | LF | 168 | $400.00 | $400.00 |
| 50 | Culvert pipe reinforced concrete class IV 60-inch (522.0460) | LF | 80 | $450.00 | $450.00 |
| 51 | Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024) | EACH | 1 | $1,300.00 | $1,300.00 |
| 52 | Apron endwalls for culvert pipe reinforced concrete 30-inch (522.1030) | EACH | 3 | $1,800.00 | $1,800.00 |
| 53 | Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036) | EACH | 1 | $2,300.00 | $2,300.00 |
| 54 | Apron endwalls for culvert pipe reinforced concrete 48-inch (522.1048) | EACH | 2 | $4,000.00 | $4,000.00 |
| 55 | Apron endwalls for culvert pipe reinforced concrete 60-inch (522.1060) | EACH | 1 | $5,700.00 | $5,700.00 |
| 56 | Culvert pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (522.2419) | LF | 80 | $200.00 | $200.00 |
| 57 | Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619) | EACH | 1 | $1,500.00 | $1,500.00 |
| 58 | Culvert pipe corrugated polyethylene 12-inch (530.0112) | LF | 70 | $50.00 | $50.00 |
| 59 | Concrete curb & gutter 4-inch sloped 30-inch type TBTT (601.0586) | LF | 49 | $126.81 | $126.81 |
| 60 | Concrete barrier type S42 (603.1142) | LF | 83 | $478.76 | $478.76 |
| 61 | Concrete barrier temporary precast delivered (603.8000) | LF | 3,570 | $12.20 | $12.20 |
| 62 | Concrete barrier temporary precast installed (603.8125) | LF | 7,580 | $6.70 | $6.70 |
| 63 | Anchoring concrete barrier temporary precast (603.8500) | LF | 5,200 | $11.25 | $11.25 |
| 64 | Slope paving concrete (604.0400) | SY | 23 | $263.98 | $263.98 |
| 65 | Riprap medium (606.0200) | CY | 252 | $150.00 | $150.00 |
| 66 | Storm sewer pipe reinforced concrete class III 30-inch (608.0330) | LF | 83 | $150.00 | $150.00 |
| 67 | Storm sewer pipe class III-A 30- inch (608.3030) | LF | 14 | $100.00 | $100.00 |
| 68 | Manhole covers type J (611.0530) | EACH | 2 | $750.00 | $750.00 |
| 69 | Inlet covers type V (611.0654) | EACH | 1 | $950.00 | $950.00 |
| 70 | Manholes 5-FT diameter (611.2005) | EACH | 1 | $5,000.00 | $5,000.00 |
| 71 | Manholes 6-FT diameter (611.2006) | EACH | 1 | $7,000.00 | $7,000.00 |
| 72 | Inlets 2X2.5-FT (611.3225) | EACH | 1 | $3,000.00 | $3,000.00 |
| 73 | Barrier system grading shaping finishing (614.0010) | EACH | 25 | $2,500.00 | $2,950.00 |
| 74 | Replacing guardrail posts and blocks (614.0950) | EACH | 3 | $125.00 | $124.00 |
| 75 | Replacing guardrail rail and hardware (614.0951) | LF | 75 | $20.00 | $19.60 |
| 76 | MGS guardrail 3 (614.2300) | LF | 3,275 | $28.95 | $28.60 |
| 77 | MGS guardrail 3 L (614.2340) | LF | 112.50 | $33.00 | $41.00 |
| 78 | MGS thrie beam transition (614.2500) | LF | 608 | $96.00 | $92.00 |
| 79 | MGS guardrail terminal eat (614.2610) | EACH | 14 | $3,615.00 | $3,835.00 |
| 80 | MGS guardrail terminal type 2 (614.2620) | EACH | 12 | $3,215.00 | $3,876.00 |
| 81 | Fence woven wire (height) 01. 4 - feet (616.0100) | LF | 210 | $15.00 | $17.00 |
| 82 | Maintenance and repair of haul roads (project) 01. 1160-05-80 (618.0100) | EACH | 1 | $10.00 | $0.01 |
| 83 | Mobilization (619.1000) | EACH | 1 | $7,500.00 | $494,000 |
| 84 | Water (624.0100) | MGAL | 137.30 | $130.00 | $0.01 |
| 85 | Topsoil (625.0100) | SY | 3,230 | $1.50 | $1.50 |
| 86 | Silt fence (628.1504) | LF | 11,880 | $1.70 | $2.20 |
| 87 | Silt fence maintenance (628.1520) | LF | 11,880 | $0.03 | $0.01 |
| 88 | Mobilizations erosion control (628.1905) | EACH | 8 | $253.00 | $600.00 |
| 89 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $303.00 | $100.00 |
| 90 | Erosion mat urban class I type B (628.2008) | SY | 3,230 | $1.85 | $2.15 |
| 91 | Inlet protection type A (628.7005) | EACH | 4 | $125.00 | $106.00 |
| 92 | Inlet protection type C (628.7015) | EACH | 2 | $75.00 | $72.00 |
| 93 | Temporary ditch checks (628.7504) | LF | 50 | $8.00 | $8.95 |
| 94 | Culvert pipe checks (628.7555) | EACH | 125 | $12.00 | $21.30 |
| 95 | Rock bags (628.7570) | EACH | 50 | $10.00 | $14.00 |
| 96 | Fertilizer type B (629.0210) | CWT | 3 | $100.00 | $110.00 |
| 97 | Seeding mixture no. 20 (630.0120) | LB | 100 | $15.00 | $8.75 |
| 98 | Seeding temporary (630.0200) | LB | 33 | $7.00 | $3.55 |
| 99 | Seed water (630.0500) | MGAL | 75 | $5.00 | $25.00 |
| 100 | Delineator posts steel (633.0100) | EACH | 51 | $35.00 | $51.00 |
| 101 | Delineator reflectors (633.0500) | EACH | 51 | $20.00 | $9.80 |
| 102 | Markers culvert end (633.5200) | EACH | 9 | $75.00 | $71.00 |
| 103 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 12 | $100.00 | $108.00 |
| 104 | Posts wood 4X6-inch X 16-FT (634.0616) | EACH | 4 | $125.00 | $116.00 |
| 105 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 3 | $125.00 | $129.00 |
| 106 | Moving signs type II (638.2102) | EACH | 17 | $150.00 | $119.00 |
| 107 | Removing small sign supports (638.3000) | EACH | 19 | $35.00 | $34.30 |
| 108 | Field office type B (642.5001) | EACH | 1 | $12,330 | $9,000.00 |
| 109 | Traffic control drums (643.0300) | DAY | 85,500 | $0.20 | $0.20 |
| 110 | Digital speed reduction system (DSRS) (643.0370.S) | DAY | 102 | $338.00 | $338.00 |
| 111 | Traffic control barricades type III (643.0420) | DAY | 1,160 | $0.75 | $0.75 |
| 112 | Traffic control warning lights type A (643.0705) | DAY | 2,300 | $0.11 | $0.11 |
| 113 | Traffic control warning lights type C (643.0715) | DAY | 10,400 | $0.13 | $0.13 |
| 114 | Traffic control connected arrow boards (643.0810) | DAY | 270 | $17.25 | $17.25 |
| 115 | Traffic control signs (643.0900) | DAY | 12,040 | $0.30 | $0.30 |
| 116 | Traffic control covering signs type I (643.0910) | EACH | 13 | $180.00 | $180.00 |
| 117 | Traffic control covering signs type II (643.0920) | EACH | 32 | $45.00 | $45.00 |
| 118 | Traffic control signs fixed message (643.1000) | SF | 173 | $11.00 | $11.00 |
| 119 | Traffic control signs PCMS with TMC communications (643.1051) | DAY | 150 | $23.00 | $23.00 |
| 120 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 270 | $11.50 | $11.50 |
| 121 | Temporary marking line paint 6- inch (643.3165) | LF | 469,400 | $0.30 | $0.30 |
| 122 | Temporary marking line removable tape 6-inch (643.3180) | LF | 4,440 | $2.25 | $2.25 |
| 123 | Temporary marking line paint 10- inch (643.3265) | LF | 9,200 | $0.60 | $0.60 |
| 124 | Temporary marking line removable tape 10-inch (643.3280) | LF | 950 | $4.00 | $4.00 |
| 125 | Temporary marking stop line paint 18-inch (643.3805) | LF | 460 | $10.50 | $10.50 |
| 126 | Traffic control (643.5000) | EACH | 1 | $177,000 | $177,000 |
| 127 | Geotextile type HR (645.0120) | SY | 646 | $10.00 | $10.00 |
| 128 | Marking line epoxy 6-inch (646.2020) | LF | 10,113 | $0.60 | $0.60 |
| 129 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 22,350 | $0.65 | $0.65 |
| 130 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 193,571 | $1.20 | $1.20 |
| 131 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 22,962 | $6.45 | $6.45 |
| 132 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 353 | $1.80 | $1.80 |
| 133 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 5,265 | $10.75 | $10.75 |
| 134 | Marking aerial enforcement bar epoxy (646.5420) | EACH | 20 | $300.00 | $300.00 |
| 135 | Marking outfall epoxy (646.5520) | EACH | 716 | $25.00 | $25.00 |
| 136 | Marking stop line epoxy 18-inch (646.6120) | LF | 224 | $18.00 | $18.00 |
| 137 | Marking chevron epoxy 24-inch (646.7220) | LF | 586 | $18.00 | $18.00 |
| 138 | Marking removal line 6-inch (646.9002) | LF | 126,245 | $0.15 | $0.15 |
| 139 | Construction staking storm sewer (650.4000) | EACH | 3 | $450.00 | $450.00 |
| 140 | Construction staking pipe culverts (650.6000) | EACH | 9 | $180.00 | $180.00 |
| 141 | Construction staking resurfacing reference (650.8000) | LF | 99,974 | $0.10 | $0.10 |
| 142 | Construction staking supplemental control (project) 01. 1166-05-80 (650.9911) | EACH | 1 | $10.00 | $10.00 |
| 143 | Sawing asphalt (690.0150) | LF | 1,279 | $2.00 | $2.00 |
| 144 | Sawing concrete (690.0250) | LF | 3,249 | $2.55 | $2.75 |
| 145 | Incentive iri ride (740.0440) | DOL | 33,704 | $1.00 | $1.00 |
| 146 | Special 01. locate and clean underdrain outfalls (SPV.0060) | EACH | 716 | $33.00 | $80.00 |
| 147 | Special 02. temporary pipe connection 19X30-inch (SPV.0060) | EACH | 1 | $1,000.00 | $1,000.00 |
| 148 | Special 03. temporary pipe connection 30-inch (SPV.0060) | EACH | 4 | $1,000.00 | $1,000.00 |
| 149 | Special 04. temporary pipe connection 36-inch (SPV.0060) | EACH | 1 | $1,000.00 | $1,000.00 |
| 150 | Special 05. temporary pipe connection 48-inch (SPV.0060) | EACH | 2 | $1,500.00 | $1,500.00 |
| 151 | Special 06. temporary pipe connection 60-inch (SPV.0060) | EACH | 1 | $2,000.00 | $2,000.00 |
| 152 | Special 07. culvert pipe replacement limits exploration (SPV.0060) | EACH | 6 | $100.00 | $100.00 |
| 153 | Special 08. connecting to existing inlets (SPV.0060) | EACH | 4 | $1,500.00 | $1,500.00 |
| 154 | Special 09. adjusting eat (SPV.0060) | EACH | 8 | $603.00 | $2,025.00 |
| 155 | Special 10. digital speed limit trailer pad (SPV.0060) | EACH | 21 | $1,500.00 | $1,500.00 |
| 156 | Special 11. temporary water diversion culvert 49039007554 (SPV.0060) | EACH | 1 | $100.00 | $100.00 |
| 157 | Special 12. sealing storm structure openings (SPV.0060) | EACH | 3 | $1,500.00 | $1,500.00 |
| 158 | Special 01. fill existing rumble strips (SPV.0090) | LF | 27,780 | $0.94 | $4.28 |
| 159 | Special 02. removing excess material under guardrail (SPV.0090) | LF | 1,160 | $6.23 | $10.57 |
| 160 | Special 01. removing distress asphaltic surface milling (SPV.0180) | SY | 4,940 | $3.43 | $6.88 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.