WisDOT contract 20260915028 bid tabulation
Osseo - Black River Falls; S Pole Grove Rd Bridge B-27-0026 (IH 094, Jackson County Osseo - Black River Falls). Let by Wisconsin DOT on September 15, 2026, Jackson. 3 bids received; low bid $736,924 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 15 SEP 2026
- Pay items
- 82
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $736,924 | Low |
| 2 | Norcon Corporation | $753,079 | +2.0% |
| 3 | Zenith Tech., Inc. - Waukesha | $780,597 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Norcon Corporation | 3. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 5 | $50.00 | $50.00 | $50.00 |
| 2 | Grubbing (201.0205) | STA | 5 | $50.00 | $50.00 | $50.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 2 | $250.00 | $250.00 | $250.00 |
| 4 | Abatement of asbestos containing material (structure) 01. B-27-26 (203.0211.S) | EACH | 1 | $7,500.00 | $4,780.00 | $7,000.00 |
| 5 | Debris containment (structure) 01. B-27-26 (203.0330) | EACH | 1 | $500.00 | $4,200.00 | $7,500.00 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 677 | $15.22 | $15.22 | $15.22 |
| 7 | Removing guardrail (204.0165) | LF | 386 | $3.45 | $3.45 | $3.45 |
| 8 | Removing fence (204.0170) | LF | 210 | $2.15 | $2.15 | $2.15 |
| 9 | Removing surface drains (204.0190) | EACH | 2 | $200.00 | $200.00 | $200.00 |
| 10 | Excavation common (205.0100) | CY | 355 | $10.50 | $10.50 | $10.50 |
| 11 | Borrow (208.0100) | CY | 1,965 | $29.30 | $29.30 | $29.30 |
| 12 | Prepare foundation for asphaltic paving (project) 01. 1020-00-86 (211.0101) | EACH | 1 | $2,750.00 | $6,500.00 | $2,750.00 |
| 13 | Prepare foundation for asphaltic shoulders (211.0400) | STA | 4 | $20.00 | $1,625.00 | $20.00 |
| 14 | Finishing roadway (project) 01. 1020-00-86 (213.0100) | EACH | 1 | $500.00 | $500.00 | $1,500.00 |
| 15 | Base aggregate dense 3/4-inch (305.0110) | TON | 230 | $31.00 | $31.00 | $31.00 |
| 16 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 910 | $27.75 | $27.75 | $27.75 |
| 17 | Concrete pavement 8-inch (415.0080) | SY | 24 | $155.67 | $115.00 | $155.67 |
| 18 | Concrete pavement approach slab (415.0410) | SY | 129 | $331.88 | $237.00 | $331.88 |
| 19 | Tack coat (455.0605) | GAL | 80 | $11.50 | $11.50 | $11.50 |
| 20 | Asphaltic surface (465.0105) | TON | 170 | $175.62 | $175.62 | $175.62 |
| 21 | Asphaltic surface patching (465.0110) | TON | 20 | $175.62 | $175.62 | $175.62 |
| 22 | Expansion device (502.3101) | LF | 70 | $350.00 | $477.00 | $300.00 |
| 23 | Protective surface treatment (502.3200) | SY | 712 | $4.00 | $2.25 | $5.00 |
| 24 | Pigmented surface sealer reseal (502.3205) | SY | 155 | $10.00 | $17.00 | $20.00 |
| 25 | Protective surface treatment reseal (502.3215) | SY | 91 | $15.00 | $2.25 | $20.00 |
| 26 | Adhesive anchors 3/4-inch (502.4106) | EACH | 16 | $30.00 | $37.00 | $55.00 |
| 27 | Adhesive anchors no. 5 bar (502.4205) | EACH | 88 | $25.00 | $34.00 | $35.00 |
| 28 | Bar steel reinforcement HS structures (505.0400) | LB | 3,050 | $2.85 | $3.15 | $2.85 |
| 29 | Bearing pads elastomeric laminated (506.2610) | EACH | 8 | $2,500.00 | $1,985.00 | $1,500.00 |
| 30 | Removing bearings (structure) 01. B-27-26 (506.7050.S) | EACH | 8 | $2,500.00 | $1,075.00 | $2,000.00 |
| 31 | Preparation decks type 1 (509.0301) | SY | 195 | $110.00 | $190.00 | $175.00 |
| 32 | Preparation decks type 2 (509.0302) | SY | 9 | $130.00 | $240.00 | $425.00 |
| 33 | Cleaning decks (509.0500) | SY | 712 | $32.69 | $36.00 | $37.50 |
| 34 | Joint repair (509.1000) | SY | 32 | $1,500.00 | $1,365.00 | $1,500.00 |
| 35 | Full-depth deck repair (509.2000) | SY | 1 | $200.00 | $20.00 | $1,000.00 |
| 36 | Concrete masonry overlay decks (509.2500) | CY | 40 | $2,000.00 | $1,785.00 | $3,410.00 |
| 37 | Epoxy crack sealing (509.9020.S) | LF | 30 | $20.00 | $97.00 | $100.00 |
| 38 | Preparation and coating of top flanges (structure) 01. B-27-26 (517.0901.S) | EACH | 1 | $4,000.00 | $5,360.00 | $4,000.00 |
| 39 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 160 | $71.58 | $68.00 | $71.58 |
| 40 | Concrete curb & gutter 4-inch sloped 36-inch type TBTT (601.0590) | LF | 40 | $71.58 | $68.00 | $71.58 |
| 41 | Concrete surface drains (602.3010) | CY | 4 | $1,610.04 | $1,180.00 | $1,610.04 |
| 42 | Riprap medium (606.0200) | CY | 115 | $72.00 | $72.00 | $72.00 |
| 43 | MGS guardrail 3 (614.2300) | LF | 125 | $25.85 | $25.85 | $25.85 |
| 44 | MGS thrie beam transition (614.2500) | LF | 157.60 | $113.95 | $113.95 | $113.95 |
| 45 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,845.00 | $3,845.00 | $3,845.00 |
| 46 | Fence woven wire (height) 01. 4- FT (616.0100) | LF | 210 | $18.00 | $18.00 | $18.00 |
| 47 | Maintenance and repair of haul roads (project) 01. 1020-00-86 (618.0100) | EACH | 1 | $1.00 | $100.00 | $250.00 |
| 48 | Mobilization (619.1000) | EACH | 1 | $131,928 | $145,668 | $99,000 |
| 49 | Water (624.0100) | MGAL | 24 | $17.50 | $17.50 | $17.50 |
| 50 | Salvaged topsoil (625.0500) | SY | 3,910 | $1.40 | $1.40 | $1.40 |
| 51 | Silt fence (628.1504) | LF | 1,000 | $1.80 | $1.80 | $1.80 |
| 52 | Silt fence maintenance (628.1520) | LF | 1,000 | $0.01 | $0.01 | $0.01 |
| 53 | Mobilizations erosion control (628.1905) | EACH | 5 | $150.00 | $150.00 | $150.00 |
| 54 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $75.00 | $75.00 | $75.00 |
| 55 | Erosion mat urban class I type B (628.2008) | SY | 4,890 | $1.80 | $1.80 | $1.80 |
| 56 | Fertilizer type A (629.0205) | CWT | 3.50 | $105.00 | $105.00 | $105.00 |
| 57 | Seeding mixture no. 20 (630.0120) | LB | 250 | $8.50 | $8.50 | $8.50 |
| 58 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $105.00 | $105.00 | $105.00 |
| 59 | Signs type II reflective F (637.2230) | SF | 12 | $30.00 | $30.00 | $30.00 |
| 60 | Removing signs type II (638.2602) | EACH | 4 | $31.40 | $31.40 | $31.40 |
| 61 | Removing small sign supports (638.3000) | EACH | 4 | $31.40 | $31.40 | $31.40 |
| 62 | Field office type B (642.5001) | EACH | 1 | $3,000.00 | $6,500.00 | $5,000.00 |
| 63 | Traffic control drums (643.0300) | DAY | 700 | $0.50 | $0.50 | $0.50 |
| 64 | Traffic control barricades type III (643.0420) | DAY | 1,360 | $0.45 | $0.45 | $0.45 |
| 65 | Traffic control warning lights type A (643.0705) | DAY | 2,190 | $0.12 | $0.12 | $0.12 |
| 66 | Traffic control connected arrow boards (643.0810) | DAY | 20 | $50.00 | $50.00 | $50.00 |
| 67 | Traffic control signs (643.0900) | DAY | 1,150 | $0.25 | $0.25 | $0.25 |
| 68 | Traffic control connected work zone start and end location markers (643.1220) | DAY | 20 | $25.00 | $25.00 | $25.00 |
| 69 | Temporary marking line removable tape 6-inch (643.3180) | LF | 840 | $2.20 | $2.20 | $2.20 |
| 70 | Traffic control (643.5000) | EACH | 1 | $34,600 | $34,600 | $34,600 |
| 71 | Geotextile type HR (645.0120) | SY | 363 | $3.75 | $3.75 | $3.75 |
| 72 | Construction staking subgrade (650.4500) | LF | 550 | $0.01 | $0.01 | $0.01 |
| 73 | Construction staking base (650.5000) | LF | 500 | $2.00 | $2.00 | $2.00 |
| 74 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 160 | $5.00 | $5.00 | $5.00 |
| 75 | Construction staking concrete pavement (650.7000) | LF | 74 | $6.00 | $6.00 | $6.00 |
| 76 | Construction staking resurfacing reference (650.8000) | LF | 270 | $1.00 | $1.00 | $1.00 |
| 77 | Construction staking supplemental control (project) 01. 1020-00-86 (650.9911) | EACH | 1 | $800.00 | $800.00 | $800.00 |
| 78 | Construction staking slope stakes (650.9920) | LF | 550 | $3.00 | $3.00 | $3.00 |
| 79 | Sawing asphalt (690.0150) | LF | 584 | $1.96 | $2.00 | $1.96 |
| 80 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 81 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 1,000 | $1.80 | $1.80 | $1.80 |
| 82 | Special 01. abutment seat cleaning and sealing (SPV.0180) | SY | 18 | $150.00 | $145.00 | $150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of September 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.