WisDOT contract 20261110002 bid tabulation
Monroe - Brodhead; CTH S Intersection (STH 011, Green County Monroe - Broadhead). Let by Wisconsin DOT on November 10, 2026, Green. 4 bids received; low bid $2,661,820 by Rock Road Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 NOV 2026
- Pay items
- 144
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Road Companies, Inc. | $2,661,820 | Low |
| 2 | Parisi Construction, LLC | $2,793,861 | +5.0% |
| 3 | James Peterson Sons, Inc. | $2,822,629 | +6.0% |
| 4 | Zignego Company, Inc. | $2,886,869 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Road Companies, Inc. | 2. Parisi Construction, LLC | 3. James Peterson Sons, Inc. | 4. Zignego Company, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0120) | ID | 88 | $40.00 | $42.00 | $40.00 | $12.00 |
| 2 | Grubbing (201.0220) | ID | 88 | $40.00 | $42.00 | $50.00 | $12.00 |
| 3 | Removing small pipe culverts (203.0100) | EACH | 2 | $350.19 | $780.00 | $675.00 | $450.00 |
| 4 | Removing structure (structure) 01. 72-inch culvert pipe (203.0220) | EACH | 2 | $7,538.12 | $1,400.00 | $5,000.00 | $1,500.00 |
| 5 | Removing concrete pavement (204.0100) | SY | 3,460 | $17.45 | $3.80 | $0.75 | $2.50 |
| 6 | Removing asphaltic surface (204.0110) | SY | 1,307 | $10.33 | $13.50 | $3.00 | $4.00 |
| 7 | Removing curb & gutter (204.0150) | LF | 310 | $8.13 | $13.75 | $2.90 | $8.00 |
| 8 | Excavation common (205.0100) | CY | 18,550 | $10.33 | $17.25 | $13.10 | $8.45 |
| 9 | Borrow (208.0100) | CY | 1,730 | $19.09 | $11.50 | $16.23 | $7.91 |
| 10 | Finishing roadway (project) 01. 1706-04-75 (213.0100) | EACH | 1 | $5,313.51 | $500.00 | $2,500.00 | $750.00 |
| 11 | Base aggregate dense 3/4-inch (305.0110) | TON | 640 | $32.67 | $30.50 | $30.18 | $20.50 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 10,145 | $15.48 | $16.75 | $20.14 | $18.50 |
| 13 | Base aggregate open-graded (310.0115) | CY | 57 | $7.46 | $95.00 | $25.30 | $45.00 |
| 14 | Select crushed material (312.0110) | TON | 12,815 | $14.80 | $17.50 | $13.20 | $17.50 |
| 15 | Coloring concrete wisdot red (405.0100) | CY | 305 | $150.79 | $125.00 | $125.00 | $125.00 |
| 16 | Concrete pavement 9-inch (415.0090) | SY | 5,030 | $84.23 | $94.00 | $94.00 | $119.30 |
| 17 | Concrete truck apron 12-inch (415.2010) | SY | 905 | $134.22 | $125.00 | $125.00 | $164.36 |
| 18 | Concrete pavement joint filling (415.4100) | SY | 6,240 | $2.25 | $2.40 | $2.25 | $2.75 |
| 19 | Rout and seal (415.6000.S) | LF | 595 | $5.50 | $5.80 | $5.50 | $5.50 |
| 20 | Tack coat (455.0605) | GAL | 325 | $3.15 | $0.10 | $0.10 | $0.10 |
| 21 | Incentive density HMA pavement (460.2000) | DOL | 1,760 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 2,275 | $83.50 | $91.00 | $87.00 | $87.00 |
| 23 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 475 | $93.75 | $99.00 | $95.00 | $95.00 |
| 24 | Asphaltic surface driveways and field entrances (465.0120) | TON | 10 | $155.00 | $160.00 | $155.00 | $155.00 |
| 25 | Asphaltic flumes (465.0315) | SY | 58 | $60.00 | $33.50 | $32.00 | $32.00 |
| 26 | Apron endwalls for culvert pipe 12- inch (520.1012) | EACH | 6 | $482.22 | $850.00 | $370.00 | $225.00 |
| 27 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $1,275.04 | $1,000.00 | $921.00 | $480.00 |
| 28 | Apron endwalls for culvert pipe 30- inch (520.1030) | EACH | 5 | $1,509.67 | $2,000.00 | $1,120.00 | $875.00 |
| 29 | Culvert pipe class III-A non-metal 24-inch (520.3424) | LF | 135 | $155.96 | $74.00 | $196.50 | $105.00 |
| 30 | Culvert pipe class III-A non-metal 30-inch (520.3430) | LF | 290 | $188.76 | $97.00 | $180.25 | $145.00 |
| 31 | Concrete collars for pipe (520.8000) | EACH | 2 | $608.46 | $1,700.00 | $950.00 | $750.00 |
| 32 | Apron endwalls for culvert pipe sloped side drains steel 18-inch 6 to 1 (521.1518) | EACH | 2 | $1,687.36 | $1,900.00 | $1,550.00 | $3,200.00 |
| 33 | Apron endwalls for culvert pipe sloped side drains steel 24-inch 6 to 1 (521.1524) | EACH | 2 | $2,272.22 | $2,500.00 | $2,280.00 | $4,200.00 |
| 34 | Concrete curb & gutter 18-inch type A (601.0405) | LF | 235 | $34.84 | $50.00 | $50.00 | $51.48 |
| 35 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 1,068 | $33.40 | $35.00 | $35.00 | $57.06 |
| 36 | Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551) | LF | 2,314 | $28.66 | $35.00 | $35.00 | $60.78 |
| 37 | Concrete curb & gutter 4-inch sloped 36-inch type D (601.0553) | LF | 157 | $38.92 | $60.00 | $60.00 | $60.78 |
| 38 | Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581) | LF | 356 | $38.68 | $49.00 | $49.00 | $57.06 |
| 39 | Concrete curb pedestrian (601.0600) | LF | 140 | $78.72 | $85.00 | $85.00 | $66.35 |
| 40 | Concrete sidewalk 4-inch (602.0405) | SF | 8,790 | $5.46 | $6.60 | $6.60 | $13.91 |
| 41 | Curb ramp detectable warning field natural patina (602.0515) | SF | 128 | $50.40 | $54.00 | $54.00 | $50.00 |
| 42 | Riprap medium (606.0200) | CY | 35 | $99.94 | $240.00 | $150.00 | $80.00 |
| 43 | Storm sewer pipe class III-A 12- inch (608.3012) | LF | 401 | $93.94 | $55.00 | $113.00 | $40.00 |
| 44 | Storm sewer pipe class III-A 18- inch (608.3018) | LF | 267 | $70.13 | $62.00 | $106.00 | $80.00 |
| 45 | Manhole covers type J (611.0530) | EACH | 1 | $1,092.19 | $1,000.00 | $595.00 | $1,000.00 |
| 46 | Inlet covers type H (611.0624) | EACH | 5 | $1,341.56 | $1,400.00 | $920.00 | $1,100.00 |
| 47 | Inlet covers type HM (611.0627) | EACH | 3 | $1,341.56 | $1,400.00 | $920.00 | $1,100.00 |
| 48 | Inlet covers type HM-S (611.0636) | EACH | 3 | $1,341.56 | $1,400.00 | $920.00 | $1,100.00 |
| 49 | Inlet covers type H-S (611.0639) | EACH | 4 | $1,341.56 | $1,400.00 | $920.00 | $1,100.00 |
| 50 | Inlet covers type T (611.0652) | EACH | 2 | $1,623.37 | $1,700.00 | $1,290.00 | $1,500.00 |
| 51 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $2,802.07 | $3,100.00 | $2,900.00 | $3,000.00 |
| 52 | Inlets 4-FT diameter (611.3004) | EACH | 2 | $2,802.07 | $3,100.00 | $2,700.00 | $3,000.00 |
| 53 | Inlets 2X2.5-FT (611.3225) | EACH | 2 | $2,337.41 | $1,600.00 | $2,190.00 | $1,700.00 |
| 54 | Inlets 2X3-FT (611.3230) | EACH | 13 | $2,473.09 | $1,600.00 | $2,320.00 | $1,950.00 |
| 55 | Cover plates temporary (611.8120.S) | EACH | 8 | $609.49 | $670.00 | $450.00 | $100.00 |
| 56 | Pipe underdrain 6-inch (612.0106) | LF | 1,506 | $23.92 | $11.25 | $10.60 | $9.00 |
| 57 | Maintenance and repair of haul roads (project) 01. 1705-04-75 (618.0100) | EACH | 1 | $0.01 | $500.00 | $100.00 | $1.00 |
| 58 | Mobilization (619.1000) | EACH | 1 | $289,000 | $200,000 | $265,337 | $142,000 |
| 59 | Concrete median sloped nose (620.0300) | SF | 612 | $13.84 | $13.00 | $14.00 | $46.82 |
| 60 | Water (624.0100) | MGAL | 345 | $0.01 | $25.00 | $5.00 | $0.05 |
| 61 | Topsoil (625.0100) | SY | 17,520 | $0.01 | $4.00 | $2.20 | $3.00 |
| 62 | Mulching (627.0200) | SY | 14,615 | $0.40 | $0.40 | $0.40 | $0.50 |
| 63 | Silt fence (628.1504) | LF | 2,780 | $2.25 | $2.40 | $2.25 | $3.00 |
| 64 | Silt fence maintenance (628.1520) | LF | 2,780 | $0.01 | $0.01 | $0.01 | $0.01 |
| 65 | Mobilizations erosion control (628.1905) | EACH | 9 | $100.00 | $100.00 | $100.00 | $500.00 |
| 66 | Mobilizations emergency erosion control (628.1910) | EACH | 7 | $100.00 | $100.00 | $100.00 | $1.00 |
| 67 | Erosion mat class I type B (628.2004) | SY | 2,380 | $1.45 | $1.50 | $1.45 | $3.00 |
| 68 | Erosion mat class II type B (628.2023) | SY | 215 | $3.00 | $3.10 | $3.00 | $3.00 |
| 69 | Inlet protection type A (628.7005) | EACH | 3 | $150.00 | $160.00 | $150.00 | $200.00 |
| 70 | Inlet protection type C (628.7015) | EACH | 17 | $65.00 | $68.00 | $65.00 | $100.00 |
| 71 | Stone ditch checks (628.7515.S) | CY | 180 | $94.66 | $88.00 | $75.00 | $1.00 |
| 72 | Culvert pipe checks (628.7555) | EACH | 25 | $20.00 | $21.00 | $90.00 | $25.00 |
| 73 | Tracking pads (628.7560) | EACH | 4 | $100.00 | $1,200.00 | $2,000.00 | $1.00 |
| 74 | Fertilizer type B (629.0210) | CWT | 16 | $90.00 | $94.00 | $90.00 | $100.00 |
| 75 | Seeding mixture no. 20 (630.0120) | LB | 750 | $8.50 | $8.90 | $20.00 | $9.00 |
| 76 | Seeding mixture no. 40 (630.0140) | LB | 25 | $20.00 | $21.00 | $4.50 | $12.00 |
| 77 | Seeding temporary (630.0200) | LB | 345 | $4.50 | $4.70 | $4.50 | $3.00 |
| 78 | Seed water (630.0500) | MGAL | 490 | $10.00 | $10.50 | $10.00 | $0.01 |
| 79 | Markers culvert end (633.5200) | EACH | 17 | $65.00 | $68.00 | $65.00 | $100.00 |
| 80 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 13 | $80.00 | $84.00 | $80.00 | $150.00 |
| 81 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 7 | $90.00 | $94.00 | $90.00 | $150.00 |
| 82 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 10 | $100.00 | $100.00 | $100.00 | $180.00 |
| 83 | Posts tubular steel 2X2-inch X 12- FT (634.0812) | EACH | 10 | $185.00 | $190.00 | $185.00 | $300.00 |
| 84 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 4 | $200.00 | $210.00 | $200.00 | $300.00 |
| 85 | Signs type II reflective H (637.2210) | SF | 471.25 | $23.00 | $24.00 | $23.00 | $24.00 |
| 86 | Signs type II reflective F (637.2230) | SF | 43 | $23.00 | $24.00 | $23.00 | $26.00 |
| 87 | Moving signs type II (638.2102) | EACH | 27 | $175.00 | $180.00 | $175.00 | $150.00 |
| 88 | Removing signs type II (638.2602) | EACH | 23 | $35.00 | $36.75 | $35.00 | $50.00 |
| 89 | Removing small sign supports (638.3000) | EACH | 13 | $35.00 | $36.75 | $35.00 | $50.00 |
| 90 | Moving small sign supports (638.4000) | EACH | 16 | $100.00 | $100.00 | $100.00 | $50.00 |
| 91 | Field office type C (642.5201) | EACH | 1 | $6,750.00 | $6,500.00 | $15,000 | $25,000 |
| 92 | Traffic control drums (643.0300) | DAY | 10,100 | $0.09 | $0.10 | $0.25 | $0.25 |
| 93 | Traffic control barricades type III (643.0420) | DAY | 1,840 | $0.65 | $0.70 | $0.50 | $0.50 |
| 94 | Traffic control warning lights type A (643.0705) | DAY | 2,780 | $0.06 | $0.05 | $0.10 | $0.10 |
| 95 | Traffic control warning lights type C (643.0715) | DAY | 1,480 | $0.06 | $0.05 | $0.10 | $0.10 |
| 96 | Traffic control signs (643.0900) | DAY | 8,620 | $0.40 | $0.40 | $0.75 | $0.75 |
| 97 | Traffic control signs PCMS (643.1050) | DAY | 30 | $35.00 | $36.75 | $55.00 | $55.00 |
| 98 | Temporary marking line removable tape 6-inch (643.3180) | LF | 10,495 | $1.60 | $1.70 | $1.75 | $1.75 |
| 99 | Temporary marking stop line paint 18-inch (643.3805) | LF | 21 | $3.00 | $3.10 | $4.00 | $4.00 |
| 100 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 40 | $4.80 | $5.00 | $5.00 | $5.00 |
| 101 | Traffic control (643.5000) | EACH | 1 | $20,000 | $20,900 | $16,000 | $16,000 |
| 102 | Geotextile type DF schedule A (645.0111) | SY | 839 | $1.26 | $3.80 | $6.00 | $5.00 |
| 103 | Geotextile type HR (645.0120) | SY | 140 | $2.58 | $10.50 | $7.50 | $8.00 |
| 104 | Geotextile type R (645.0130) | SY | 360 | $1.51 | $4.80 | $2.00 | $4.00 |
| 105 | Marking line epoxy 6-inch (646.2020) | LF | 3,955 | $0.75 | $0.80 | $0.75 | $0.75 |
| 106 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 8,085 | $1.60 | $1.70 | $1.60 | $1.60 |
| 107 | Marking line epoxy 10-inch (646.4020) | LF | 275 | $2.75 | $2.90 | $2.75 | $2.75 |
| 108 | Marking dotted extension epoxy 18-inch (646.6320) | LF | 65 | $11.00 | $11.50 | $11.00 | $11.00 |
| 109 | Marking diagonal epoxy 12-inch (646.7120) | LF | 190 | $9.00 | $9.40 | $9.00 | $9.00 |
| 110 | Marking curb epoxy (646.8120) | LF | 205 | $8.00 | $8.40 | $8.00 | $8.00 |
| 111 | Marking island nose epoxy (646.8220) | EACH | 4 | $350.00 | $370.00 | $350.00 | $350.00 |
| 112 | Marking removal line 4-inch (646.9000) | LF | 2,515 | $0.80 | $0.85 | $0.70 | $0.70 |
| 113 | Construction staking storm sewer (650.4000) | EACH | 26 | $1.00 | $50.00 | $200.00 | $200.00 |
| 114 | Construction staking subgrade (650.4500) | LF | 3,256 | $0.01 | $0.01 | $0.01 | $0.01 |
| 115 | Construction staking base (650.5000) | LF | 3,256 | $0.01 | $0.01 | $2.00 | $2.00 |
| 116 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 157 | $1.00 | $0.01 | $3.00 | $3.00 |
| 117 | Construction staking pipe culverts (650.6000) | EACH | 5 | $10.00 | $100.00 | $500.00 | $500.00 |
| 118 | Construction staking electrical installations (project) 01. 1706-04- 75 (650.8501) | EACH | 1 | $7,500.00 | $500.00 | $5,000.00 | $5,000.00 |
| 119 | Construction staking supplemental control (project) 01. 1706-04-75 (650.9911) | EACH | 1 | $6,000.00 | $500.00 | $4,000.00 | $4,000.00 |
| 120 | Construction staking slope stakes (650.9920) | LF | 3,256 | $0.01 | $1.10 | $2.00 | $2.00 |
| 121 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 1,785 | $10.00 | $10.50 | $10.00 | $10.00 |
| 122 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 190 | $13.00 | $13.50 | $13.00 | $13.00 |
| 123 | Conduit rigid nonmetallic schedule 80 2-inch (652.0325) | LF | 425 | $11.00 | $11.50 | $11.00 | $11.00 |
| 124 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 8 | $2,200.00 | $2,300.00 | $2,200.00 | $2,200.00 |
| 125 | Concrete bases type 5 (654.0105) | EACH | 14 | $1,250.00 | $1,300.00 | $1,250.00 | $1,250.00 |
| 126 | Concrete control cabinet bases type L30 (654.0230) | EACH | 1 | $2,000.00 | $2,100.00 | $2,000.00 | $2,000.00 |
| 127 | Electrical wire lighting 12 AWG (655.0610) | LF | 2,292 | $1.25 | $1.30 | $1.25 | $1.25 |
| 128 | Electrical wire lighting 10 AWG (655.0615) | LF | 10,315 | $1.50 | $1.60 | $1.50 | $1.50 |
| 129 | Electrical service meter breaker pedestal (location) 01. STH 11 & CTH S (656.0201) | EACH | 1 | $2,000.00 | $2,100.00 | $2,000.00 | $2,000.00 |
| 130 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 14 | $600.00 | $630.00 | $600.00 | $600.00 |
| 131 | Poles type 5-aluminum (657.0322) | EACH | 14 | $2,400.00 | $2,500.00 | $2,400.00 | $2,400.00 |
| 132 | Luminaire arms single member 4 1/2-inch clamp 8-FT (657.0615) | EACH | 14 | $350.00 | $370.00 | $350.00 | $350.00 |
| 133 | Luminaires utility LED A (659.1115) | EACH | 14 | $200.00 | $210.00 | $200.00 | $200.00 |
| 134 | Lighting control cabinets 120/240 30-inch (659.2130) | EACH | 1 | $8,700.00 | $9,100.00 | $8,700.00 | $8,700.00 |
| 135 | Sawing asphalt (690.0150) | LF | 283 | $1.40 | $1.50 | $2.25 | $2.25 |
| 136 | Sawing concrete (690.0250) | LF | 70 | $2.20 | $2.30 | $3.25 | $3.25 |
| 137 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,780 | $1.00 | $1.00 | $1.00 | $1.00 |
| 138 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 |
| 139 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 | $5.00 |
| 140 | Special 01. foundation backfill (SPV.0035) | CY | 200 | $24.45 | $38.75 | $46.00 | $37.00 |
| 141 | Special 01. construction staking roundabout (SPV.0060) | EACH | 1 | $2,500.00 | $1,500.00 | $30,000 | $30,000 |
| 142 | Special 02. temporary pipe seal (SPV.0060) | EACH | 2 | $1,052.56 | $360.00 | $1,500.00 | $20.00 |
| 143 | Special 03. temporary lighting (SPV.0060) | EACH | 1 | $7,500.00 | $7,900.00 | $7,500.00 | $7,500.00 |
| 144 | Special 01. temporary marking wet reflective epoxy 6-inch (SPV.0090) | LF | 4,375 | $1.60 | $2.40 | $2.25 | $1.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.