WisDOT contract 20261110036 bid tabulation
West Salem - Melrose; Sand Creek B-27-0010 (STH 108, Jackson County West Salem - Melrose). Let by Wisconsin DOT on November 10, 2026, Jackson. 6 bids received; low bid $593,297 by Sheet Piling Services LLC.
- Owner
- Wisconsin DOT
- Letting
- 10 NOV 2026
- Pay items
- 58
- Data through
- 10 NOV 2026
4 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sheet Piling Services LLC | $593,297 | Low |
| 2 | Zenith Tech., Inc. - Waukesha | $593,428 | 0.0% |
| 4 | Larson Construction Co., Inc. | $602,271 | +2.0% |
| 5 | Janke General Contractors, Inc. | $644,523 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sheet Piling Services LLC | 2. Zenith Tech., Inc. - Waukesha | 3. Larson Construction Co., Inc. | 4. Janke General Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0110) | SY | 50 | $12.00 | $12.00 | $12.00 | $25.00 |
| 2 | Grubbing (201.0210) | SY | 50 | $12.00 | $12.00 | $12.00 | $22.00 |
| 3 | Removing structure over waterway debris capture (structure) 01. B-27- 10 (203.0270) | EACH | 1 | $175,000 | $78,500 | $89,837 | $132,542 |
| 4 | Removing guardrail (204.0165) | LF | 332 | $3.00 | $3.00 | $3.50 | $3.00 |
| 5 | Excavation common (205.0100) | CY | 568 | $19.00 | $19.00 | $19.00 | $25.50 |
| 6 | Borrow (208.0100) | CY | 1,251 | $22.00 | $22.00 | $22.00 | $44.00 |
| 7 | Finishing roadway (project) 01. 7930-00-72 (213.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 | $212.00 |
| 8 | Base aggregate dense 3/4-inch (305.0110) | TON | 53 | $38.00 | $38.00 | $38.00 | $55.00 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 912 | $26.00 | $26.00 | $26.00 | $33.00 |
| 10 | Tack coat (455.0605) | GAL | 102 | $8.42 | $8.42 | $8.42 | $8.42 |
| 11 | Asphaltic surface (465.0105) | TON | 308 | $148.81 | $148.81 | $148.81 | $148.81 |
| 12 | Asphaltic rumble strips, centerline (465.0560) | LF | 203 | $12.00 | $19.16 | $21.82 | $22.21 |
| 13 | Concrete masonry bridges (502.0100) | CY | 80 | $875.00 | $1,600.00 | $1,150.00 | $1,255.00 |
| 14 | Protective surface treatment (502.3200) | SY | 320 | $5.00 | $4.00 | $4.00 | $6.00 |
| 15 | Adhesive anchors no. 5 bar (502.4205) | EACH | 112 | $32.00 | $32.00 | $32.00 | $21.70 |
| 16 | Bar steel reinforcement HS coated structures (505.0600) | LB | 18,290 | $1.75 | $1.70 | $2.10 | $2.20 |
| 17 | Railing tubular type M (513.4061) | LF | 149 | $375.00 | $360.00 | $525.00 | $302.00 |
| 18 | Rubberized membrane waterproofing (516.0500) | SY | 13 | $30.00 | $70.00 | $60.00 | $28.00 |
| 19 | MGS guardrail 3 (614.2300) | LF | 50 | $27.00 | $27.00 | $28.60 | $27.00 |
| 20 | MGS thrie beam transition (614.2500) | LF | 157.60 | $88.00 | $88.00 | $95.00 | $88.00 |
| 21 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,333.00 | $3,333.00 | $3,835.00 | $4,415.00 |
| 22 | Maintenance and repair of haul roads (project) 01. 7930-00-72 (618.0100) | EACH | 1 | $0.01 | $505.05 | $500.00 | $211.00 |
| 23 | Mobilization (619.1000) | EACH | 1 | $54,114 | $85,000 | $81,800 | $45,950 |
| 24 | Water (624.0100) | MGAL | 14.60 | $25.00 | $25.00 | $25.00 | $9.25 |
| 25 | Salvaged topsoil (625.0500) | SY | 1,869 | $1.50 | $1.50 | $1.50 | $8.00 |
| 26 | Silt fence (628.1504) | LF | 778 | $2.25 | $2.50 | $2.15 | $2.50 |
| 27 | Silt fence maintenance (628.1520) | LF | 778 | $0.01 | $0.03 | $0.01 | $0.03 |
| 28 | Mobilizations erosion control (628.1905) | EACH | 2 | $200.00 | $153.00 | $400.00 | $153.00 |
| 29 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $250.00 | $153.00 | $200.00 | $153.00 |
| 30 | Erosion mat urban class I type B (628.2008) | SY | 1,869 | $2.25 | $2.00 | $2.15 | $2.00 |
| 31 | Fertilizer type B (629.0210) | CWT | 1.50 | $100.00 | $100.00 | $100.00 | $100.00 |
| 32 | Seeding mixture no. 20 (630.0120) | LB | 98 | $8.50 | $12.00 | $8.00 | $12.00 |
| 33 | Seeding temporary (630.0200) | LB | 59 | $7.00 | $7.00 | $3.55 | $7.00 |
| 34 | Seed water (630.0500) | MGAL | 49 | $1.00 | $5.00 | $10.00 | $5.00 |
| 35 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $100.00 | $125.00 | $85.00 | $125.00 |
| 36 | Moving signs type II (638.2102) | EACH | 4 | $25.00 | $175.00 | $100.00 | $242.22 |
| 37 | Removing small sign supports (638.3000) | EACH | 4 | $25.00 | $50.00 | $22.00 | $50.00 |
| 38 | Field office type B (642.5001) | EACH | 1 | $1,200.00 | $4,000.00 | $3,600.00 | $4,000.00 |
| 39 | Traffic control drums (643.0300) | DAY | 145 | $0.15 | $0.20 | $0.20 | $0.20 |
| 40 | Traffic control barricades type III (643.0420) | DAY | 1,598 | $0.75 | $0.58 | $0.58 | $0.58 |
| 41 | Traffic control warning lights type A (643.0705) | DAY | 2,614 | $0.11 | $0.10 | $0.10 | $0.10 |
| 42 | Traffic control signs (643.0900) | DAY | 10,918 | $0.20 | $0.38 | $0.38 | $0.38 |
| 43 | Traffic control covering signs type II (643.0920) | EACH | 8 | $50.00 | $35.00 | $35.00 | $35.00 |
| 44 | Traffic control signs PCMS (643.1050) | DAY | 14 | $45.00 | $65.00 | $65.00 | $65.00 |
| 45 | Traffic control (643.5000) | EACH | 1 | $11,550 | $14,300 | $14,300 | $14,300 |
| 46 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 426 | $12.90 | $12.90 | $12.90 | $12.90 |
| 47 | Construction staking subgrade (650.4500) | LF | 254 | $0.01 | $0.01 | $0.01 | $0.01 |
| 48 | Construction staking base (650.5000) | LF | 254 | $1.00 | $1.00 | $1.00 | $1.00 |
| 49 | Construction staking structure layout (structure) 01. B-27-0010 (650.6501) | EACH | 1 | $3,000.00 | $2,650.00 | $3,000.00 | $2,650.00 |
| 50 | Construction staking supplemental control (project) 01. 7930-00-72 (650.9911) | EACH | 1 | $1,200.00 | $750.00 | $1,200.00 | $750.00 |
| 51 | Construction staking slope stakes (650.9920) | LF | 254 | $1.00 | $1.00 | $1.00 | $1.00 |
| 52 | Sawing asphalt (690.0150) | LF | 69 | $5.00 | $4.00 | $5.00 | $4.00 |
| 53 | Incentive strength concrete structures (715.0502) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Installing and maintaining bird deterrent system (station) 01. station 15+00 (999.2000.S) | EACH | 1 | $0.01 | $2,500.00 | $3,800.00 | $11,000 |
| 55 | Installing and maintaining climbing turtle exclusion fence (999.2100.S) | LF | 778 | $4.25 | $4.00 | $2.33 | $4.00 |
| 56 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 57 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 58 | Special 01. flashing stainless steel (SPV.0090) | LF | 137 | $65.00 | $60.00 | $66.00 | $56.78 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way