Marking line grooved contrast permanent tape 8-inch, WisDOT 646.3555
Low bidders on WisDOT contracts carried a median of $14.54 per LF for this item, over the 24 months to 10 NOV 2026, across 2 low bids. Half of all 5 bids fell between $15.45 and $15.45.
- Owner
- Wisconsin DOT
- Item
- 646.3555
- Unit
- LF
- Data through
- 10 NOV 2026
WisDOT prints this item as “Marking Line Grooved Contrast Permanent Tape 8-Inch”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 19 | 17 | $15.42 | 55 | $15.00 |
| 2023 | 17 | 16 | $15.28 | 57 | $15.00 |
| 2024 | 4 | 4 | $13.32 | 16 | $13.50 |
| 2025 | 1 | 1 | $13.62 | 2 | $22.31 |
| 2026 | 1 | 1 | $15.45 | 3 | $15.45 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Milwaukee | 8 | $15.00 | 28 | $15.00 |
| Dane | 4 | $15.58 | 12 | $16.00 |
| Southeast Region Wide | 3 | $25.00 | 6 | $28.00 |
| Waushara | 3 | $15.50 | 3 | $15.50 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 6 to 600 | 9 | $20.00 |
| 679 to 4,400 | 10 | $15.00 |
| 4,527 to 9,042 | 10 | $14.80 |
| 9,540 to 30,645 | 10 | $15.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Zignego Company, Inc. | 20 | 15 (75%) |
| Zenith Tech., Inc. - Waukesha | 12 | 9 (75%) |
| Hoffman Construction Company | 12 | 9 (75%) |
| James Peterson Sons, Inc. | 8 | 6 (75%) |
| Michels Road & Stone, Inc. | 9 | 5 (56%) |
| Payne and Dolan, Inc | 7 | 5 (71%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 11 AUG 2026 | 20260811010 | Brown | 5,430 | $15.45 | $15.45 | 3 | Zignego Company, Inc. | WisDOT |
| 14 JAN 2025 | 20250114016 | Southeast Region Wide | 50 | $13.62 | $22.31 | 2 | Sir Lines-A-Lot LLC | WisDOT |
| 08 OCT 2024 | 20241008002 | Rock | 1,773 | $12.00 | $12.00 | 4 | Rock Road Companies, Inc. | WisDOT |
| 09 APR 2024 | 20240409016 | Milwaukee | 200 | $70.00 | $35.70 | 5 | Highway Landscapers, Inc. | WisDOT |
| 12 MAR 2024 | 20240312008 | Walworth | 8,063 | $13.13 | $13.13 | 3 | Payne and Dolan, Inc | WisDOT |
| 12 MAR 2024 | 20240312017 | Winnebago | 4,990 | $13.50 | $13.50 | 4 | Sheet Piling Services LLC | WisDOT |
| 12 DEC 2023 | 20231212014 | Southeast Region Wide | 50 | $25.00 | $55.00 | 2 | Mega Rentals, Inc. | WisDOT |
| 14 NOV 2023 | 20231114014 | Dane | 50 | $20.00 | $21.00 | 4 | Zignego Company, Inc. | WisDOT |
| 14 NOV 2023 | 20231114021 | Winnebago | 547 | $19.33 | $19.33 | 3 | Vinton Construction Company | WisDOT |
| 14 NOV 2023 | 20231114047 | Waukesha | 6 | $20.00 | $20.00 | 8 | Michels Road & Stone, Inc. | WisDOT |
| 12 SEP 2023 | 20230912014 | Eau Claire | 4,915 | $14.50 | $14.50 | 3 | Hoffman Construction Company | WisDOT |
| 08 AUG 2023 | 20230808006 | Milwaukee | 2,927 | $14.00 | $14.00 | 3 | Zenith Tech., Inc. - Waukesha | WisDOT |
| 11 JUL 2023 | 20230711002 | Ozaukee | 8,294 | $15.80 | $15.80 | 5 | Zignego Company, Inc. | WisDOT |
| 11 JUL 2023 | 20230711010 | Milwaukee | 17,892 | n/a | $15.00 | 3 | WisDOT | |
| 09 MAY 2023 | 20230509008 | Milwaukee | 970 | $15.00 | $15.00 | 4 | Zenith Tech., Inc. - Waukesha | WisDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.
How these prices were read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.