Research record, not reviewed

I-95 Betsy Ross Interchange and Bridge Street Ramps

Location
Philadelphia, PA, United States. Location shown at city level. See it on the map
Stage
Under construction, as of November 2026 (Pennsylvania Department of Transportation).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorPennsylvania Department of Transportation
CategoryHighways
AmountUS$1.641 billion (US dollars), as of November 2026Federal Highway Administration
What the amount coversCapital estimate.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.64 bnCapital estimateWhole projectNov 2026Federal Highway Administration
Financial records, each with its kind and scope

Contracts and teams

Contracts and teams: Not found in the sources consulted.

Milestones

DateMilestoneScopeSource
December 2030completionWhole projectFederal Highway Administration
Dated milestones, at the precision of their source

About the project

Part of PennDOT's 95Revive reconstruction of I-95 through Philadelphia: the rebuilding of the Betsy Ross Bridge interchange and the Bridge Street ramps in Sector A (Girard Avenue to Cottman Avenue), covering 2.7 miles of I-95 and its bridges from the Levick Street overpass to Frankford Creek. FHWA lists it as a major project at a current $1,641 million with completion in December 2030; the section's 95Revive page carries construction updates through fall 2026 and progress photos from July 2024 to April 2026.

Sources

  • FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'I-95 Betsy Ross Interchange and Bridge Street Ramps': Total Cost Baseline $1,410 Current $1,641; Completion Current Dec-2030. Consulted 12 Nov 2026.
  • 95Revive: I-95 Reconstruction Project in Philadelphia, Pennsylvania Department of Transportation. Sector A (Girard to Cottman) lists the sections AFC, BSR/BRI (Betsy Ross Bridge thru Bridge Street), CPR and GIR; the home page states no construction status. Consulted 12 Nov 2026.
  • BSR/BRI: Betsy Ross Bridge thru Bridge Street (95Revive), Pennsylvania Department of Transportation. '2.7 miles of I-95 and its bridges from the Levick Street overpass to the Frankford Creek'; Bridge Street (Exit 27) and Betsy Ross Bridge / Aramingo Avenue (Exit 26) interchanges; construction updates dated Fall 2026, progress photos July 2024 to April 2026. Consulted 12 Nov 2026.

See it on the map. How the atlas qualifies a record.