I-95 Betsy Ross Interchange and Bridge Street Ramps
- Location
- Philadelphia, PA, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of November 2026 (Pennsylvania Department of Transportation).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Pennsylvania Department of Transportation | |
| Category | Highways | |
| Amount | US$1.641 billion (US dollars), as of November 2026 | Federal Highway Administration |
| What the amount covers | Capital estimate. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$1.64 bn | Capital estimate | Whole project | Nov 2026 | Federal Highway Administration |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| December 2030 | completion | Whole project | Federal Highway Administration |
About the project
Part of PennDOT's 95Revive reconstruction of I-95 through Philadelphia: the rebuilding of the Betsy Ross Bridge interchange and the Bridge Street ramps in Sector A (Girard Avenue to Cottman Avenue), covering 2.7 miles of I-95 and its bridges from the Levick Street overpass to Frankford Creek. FHWA lists it as a major project at a current $1,641 million with completion in December 2030; the section's 95Revive page carries construction updates through fall 2026 and progress photos from July 2024 to April 2026.
Sources
- FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'I-95 Betsy Ross Interchange and Bridge Street Ramps': Total Cost Baseline $1,410 Current $1,641; Completion Current Dec-2030. Consulted 12 Nov 2026.
- 95Revive: I-95 Reconstruction Project in Philadelphia, Pennsylvania Department of Transportation. Sector A (Girard to Cottman) lists the sections AFC, BSR/BRI (Betsy Ross Bridge thru Bridge Street), CPR and GIR; the home page states no construction status. Consulted 12 Nov 2026.
- BSR/BRI: Betsy Ross Bridge thru Bridge Street (95Revive), Pennsylvania Department of Transportation. '2.7 miles of I-95 and its bridges from the Levick Street overpass to the Frankford Creek'; Bridge Street (Exit 27) and Betsy Ross Bridge / Aramingo Avenue (Exit 26) interchanges; construction updates dated Fall 2026, progress photos July 2024 to April 2026. Consulted 12 Nov 2026.