Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | U.S. Army Corps of Engineers | |
| Category | Navigation locks | |
| Chamber length | 1,200 ft | U.S. Army Corps of Engineers, Detroit District (via DVIDS) |
| Chamber width | 110 ft | U.S. Army Corps of Engineers, Detroit District (via DVIDS) |
| Chamber depth | 32 ft | U.S. Army Corps of Engineers, Detroit District (via DVIDS) |
| Amount | Not collected yet | |
| Threshold evidence | A comparable project-wide cost is still needed |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$3.22 bn | Authorized amount | Whole project | Dec 2022 | U.S. Army Corps of Engineers, Detroit District (via DVIDS) |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| 2030 | Planned construction completion | Whole project | U.S. Army Corps of Engineers, Detroit District (via DVIDS) |
About the project
Second lock the size of the Poe Lock, built in the footprint of the decommissioned Sabin Lock.
Scope notes
- WRDA 2022 reauthorization amount. Authorization is a distinct measure from an approved cost baseline or amount spent. U.S. Army Corps of Engineers
Sources
- New Lock at the Soo, U.S. Army Corps of Engineers. Chamber dimensions and programme outlook. Consulted 9 Nov 2026.
- New Lock at the Soo reauthorization, U.S. Army Corps of Engineers, Dec 2022. WRDA project authorization amount. Consulted 9 Nov 2026.
- New Lock at the Soo reauthorized in WRDA 2022 at $3.219 billion, U.S. Army Corps of Engineers, Detroit District (via DVIDS), 27 Dec 2022. '$3.219 billion' authorized 'on Dec 23, 2022' in the Water Resources Development Act (WRDA) 2022; previous authorized cost '$922 million'; 'a second Poe-sized lock (110' by 1,200')' on 'the existing decommissioned Davis and Sabin locks site'. Consulted 19 Nov 2026.
- Chamber Lock Operational Option 3 awarded for New Lock at the Soo, U.S. Army Corps of Engineers, Detroit District (via DVIDS), 12 Sep 2024. '1,200 feet long, 110 feet wide and 32 feet deep'; 'will be the same size as the Poe Lock'; 'constructed in the footprint of the Sabin Lock'; 'on track for completion in 2030'. Consulted 19 Nov 2026.
- New Lock at the Soo Phase 3 reaches 50% complete milestone, U.S. Army Corps of Engineers, Detroit District (via DVIDS), 29 Sep 2026. 'The U.S. Army Corps of Engineers, Detroit District announced a major milestone in the construction of the New Lock at the Soo, with Phase 3 of the project reaching 50% complete.'; 'Despite the harsh conditions of Michigan's Upper Peninsula, the project remains on schedule for its 2030 target completion.'. Consulted 19 Nov 2026.