30 Crossing

Location
Little Rock, AR, United States. Location shown at city level. See it on the map
Stage
Opened, as of December 2024 (Arkansas Department of Transportation).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorArkansas Department of Transportation
CategoryHighways
AmountUS$1.322 billion (US dollars), as of November 2026Federal Highway Administration
What the amount coversCapital estimate.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.32 bnCapital estimateWhole projectNov 2026Federal Highway Administration
US$633 MContract valueOne package2025Arkansas Department of Transportation
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Kiewit-Massman Constructiondesign-build contractor30 CrossingArkansas Department of Transportation
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
December 3, 2024openingWhole projectArkansas Department of Transportation
2019awardWhole projectArkansas Department of Transportation
Dated milestones, at the precision of their source

About the project

Reconstruction of I-30 through downtown Little Rock and North Little Rock, including a new bridge over the Arkansas River, rebuilt I-30/I-40 and I-30/I-630 interchanges and widened lanes, delivered by Kiewit-Massman Construction under ARDOT's first design-build contract, awarded in 2019. ARDOT says the $632.9 million lump-sum project finished in November 2024 and announced a ribbon-cutting ceremony for December 3, 2024. FHWA lists the wider I-30 and I-40 corridor from I-530 to Hwy 67 as a phased major project at $1,322 million with a $638 million funded phase and a current completion of December 2035.