635 East Project (LBJ East)

Location
Garland, TX, United States. Location shown at city level. See it on the map
Stage
Under construction, as of November 2026 (Texas Department of Transportation).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorTexas Department of Transportation
CategoryHighways
Route length11 miTexas Department of Transportation
AmountUS$1.74 billion (US dollars), as of November 2026Texas Department of Transportation
What the amount coversProject value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.74 bnProject valueWhole projectNov 2026Texas Department of Transportation
US$1.74 bnCapital estimateWhole projectNov 2026Texas Department of Transportation
US$1.85 bnCapital estimateWhole projectNov 2026Federal Highway Administration
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Pegasus Link Constructors (Fluor Enterprises and Balfour Beatty)design-build contractor635 East ProjectTexas Department of Transportation
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
2020construction startWhole projectTexas Department of Transportation
2026completionWhole projectTexas Department of Transportation
Dated milestones, at the precision of their source

About the project

An 11-mile design-build reconstruction and widening of I-635 from just east of US 75 in North Dallas to I-30 in Mesquite, including the I-635/I-30 interchange, by Pegasus Link Constructors (Fluor Enterprises and Balfour Beatty). TxDOT describes a $1.74 billion design-build project with construction from spring 2020 lasting until 2026; FHWA lists the project at $1,852 million.

Sources

  • 635 East Project, Texas Department of Transportation. '$1.74 billion design-build roadway construction project'; 11 miles; Pegasus Link Constructors; spring 2020; completion 2026. Consulted 12 Nov 2026.
  • Texas Clear Lanes: Dallas projects, Texas Department of Transportation. Row 'I-635 LBJ East: US 75 to I-30 | $1,740,000,000 | 2020 | 2026'. Consulted 12 Nov 2026.
  • FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'LBJ East (I-635)': Total Cost Baseline $1,696 Current $1,852; Completion Current Sep-2024. Consulted 12 Nov 2026.

See it on the map. How the atlas qualifies a record.