North I-25 (I-25 North Express Lanes)
- Location
- Berthoud, CO, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of November 2026 (Colorado Department of Transportation).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Colorado Department of Transportation (with HPTE and the Bridge Enterprise) | |
| Category | Highways | |
| Amount | US$7.909 billion (US dollars), as of November 2026 | Federal Highway Administration |
| What the amount covers | Programme value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$7.91 bn | Programme value | Programme | Nov 2026 | Federal Highway Administration |
| US$415 M | Construction budget | One phase | Nov 2026 | Colorado Department of Transportation |
| US$305 M | Capital estimate, approx. | One phase | Nov 2026 | Colorado Department of Transportation |
| US$302 M | Capital estimate | One phase | Nov 2026 | Colorado Department of Transportation |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Ralph L. Wadsworth Construction / SEMA Construction | contractor | I-25 North Express Lanes, Mead to Berthoud (Segment 5) | Colorado Department of Transportation |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| May 12, 2024 | construction start | Whole project | Colorado Department of Transportation |
| 2028 | completion | Whole project | Colorado Department of Transportation |
About the project
A programme of express-lane and reconstruction segments on I-25 between Denver and Fort Collins, delivered segment by segment. FHWA lists a programme total of $7,909 million with a $2,306 million funded phase and a current completion of June 2060. CDOT reports the Mead-to-Berthoud segment (Segment 5, about six miles) at a $415 million construction cost, under construction by Ralph L. Wadsworth/SEMA since May 12, 2024 with completion in 2028; its funding page costs Segment 6 at about $305 million and Segments 7 and 8 at $302 million, and CDOT says about 20 miles of improvements between Berthoud and Fort Collins were completed over the past six years.
Sources
- FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'North I-25': Total Cost Baseline $8,618 Current $7,909; Funded Phase Cost $2,306; Completion Current Jun-2060; sponsors CDOT, HPTE, Bridge Enterprise. Consulted 12 Nov 2026.
- I-25 North Express Lanes - Mead to Berthoud, Colorado Department of Transportation. 'Construction Cost: $415 Million'; 'approximately six-mile project'; crews began construction 'Sunday, May 12, 2024'; 'Once complete in 2028'; contractor 'Ralph L Wadsworth Construction/Sema Construction'; 'approximately 20 miles of improvements that have been completed on I-25 between Berthoud to Fort Collins over the past six years'. Consulted 12 Nov 2026.
- North I-25 Funding, Colorado Department of Transportation. Segment 6 'approximately $305M' and 'fully funded'; Segments 7 and 8 '$302 million expansion'; 'A portion of the project will be substantially complete in late 2023'. Consulted 12 Nov 2026.