North I-25 (I-25 North Express Lanes)

Location
Berthoud, CO, United States. Location shown at city level. See it on the map
Stage
Under construction, as of November 2026 (Colorado Department of Transportation).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorColorado Department of Transportation (with HPTE and the Bridge Enterprise)
CategoryHighways
AmountUS$7.909 billion (US dollars), as of November 2026Federal Highway Administration
What the amount coversProgramme value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$7.91 bnProgramme valueProgrammeNov 2026Federal Highway Administration
US$415 MConstruction budgetOne phaseNov 2026Colorado Department of Transportation
US$305 MCapital estimate, approx.One phaseNov 2026Colorado Department of Transportation
US$302 MCapital estimateOne phaseNov 2026Colorado Department of Transportation
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Ralph L. Wadsworth Construction / SEMA ConstructioncontractorI-25 North Express Lanes, Mead to Berthoud (Segment 5)Colorado Department of Transportation
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
May 12, 2024construction startWhole projectColorado Department of Transportation
2028completionWhole projectColorado Department of Transportation
Dated milestones, at the precision of their source

About the project

A programme of express-lane and reconstruction segments on I-25 between Denver and Fort Collins, delivered segment by segment. FHWA lists a programme total of $7,909 million with a $2,306 million funded phase and a current completion of June 2060. CDOT reports the Mead-to-Berthoud segment (Segment 5, about six miles) at a $415 million construction cost, under construction by Ralph L. Wadsworth/SEMA since May 12, 2024 with completion in 2028; its funding page costs Segment 6 at about $305 million and Segments 7 and 8 at $302 million, and CDOT says about 20 miles of improvements between Berthoud and Fort Collins were completed over the past six years.

Sources

  • FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'North I-25': Total Cost Baseline $8,618 Current $7,909; Funded Phase Cost $2,306; Completion Current Jun-2060; sponsors CDOT, HPTE, Bridge Enterprise. Consulted 12 Nov 2026.
  • I-25 North Express Lanes - Mead to Berthoud, Colorado Department of Transportation. 'Construction Cost: $415 Million'; 'approximately six-mile project'; crews began construction 'Sunday, May 12, 2024'; 'Once complete in 2028'; contractor 'Ralph L Wadsworth Construction/Sema Construction'; 'approximately 20 miles of improvements that have been completed on I-25 between Berthoud to Fort Collins over the past six years'. Consulted 12 Nov 2026.
  • North I-25 Funding, Colorado Department of Transportation. Segment 6 'approximately $305M' and 'fully funded'; Segments 7 and 8 '$302 million expansion'; 'A portion of the project will be substantially complete in late 2023'. Consulted 12 Nov 2026.

See it on the map. How the atlas qualifies a record.