Research record, not reviewed
Gross Reservoir Expansion Project
- Location
- Boulder, CO, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of 2026 (Denver Water).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Denver Water | |
| Category | Dams and hydro | |
| Amount | US$602 million (US dollars), as of 2026 | Denver Water |
| What the amount covers | Construction budget. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$602 M | Construction budget | Whole project | 2026 | Denver Water |
| US$531 M | Contract value | Whole project | Dec 2021 | Denver Water |
| US$464 M | Capital estimate | Whole project | Aug 2019 | Denver Water |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Kiewit-Barnard Joint Venture | construction contractor | Gross Reservoir Expansion construction contract | Denver Water |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| April 1, 2022 | start | Whole project | Denver Water |
| December 2021 | award | Whole project | Denver Water |
| 2027 | planned completion | Whole project | Denver Water |
About the project
Raising Gross Dam in Boulder County by 131 feet to triple Gross Reservoir's capacity from about 42,000 to 119,000 acre-feet. Construction started on April 1, 2022 and takes five years; the Board approved a $531 million construction contract with Kiewit-Barnard Joint Venture in December 2021, increased to just under $602 million through budget amendments approved in 2023 and 2026, and the reservoir begins to fill to its new capacity in 2027.
Sources
- Gross Reservoir Expansion Project: About the Project, Denver Water. Body: '$531 million construction contract'; 'increased to just under $602 million through budget amendments approved in 2023 and 2026'; 'begins to fill to its new, increased capacity in 2027'. Consulted 13 Nov 2026.
- Gross Reservoir Expansion Project, Denver Water. Body: 'The project will raise the height of the dam by 131 feet'; 'tripling the reservoir's capacity from approximately 42,000 acre-feet to 119,000 acre-feet'; 'Construction for the Gross Reservoir Expansion Project started April 1, 2022'; 'It will take five years to finish the work to raise the height of Gross Dam'. Consulted 13 Nov 2026.
- Gross Reservoir Expansion Project hits new milestone, Denver Water, 8 Aug 2019. Body: 'the $464 million project'; 'approved a two-year, $4.5 million contract with Kiewit Barnard'. Consulted 13 Nov 2026.