Research record, not reviewed
Northwater Treatment Plant
- Location
- Golden, CO, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of June 2024 (Denver Water).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Denver Water | |
| Category | Water | |
| Capacity mgd | 75 mgd | Denver Water |
| Amount | US$520 million (US dollars) | Denver Water |
| What the amount covers | Capital estimate. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$520 M | Capital estimate | Whole project | Undated | Denver Water |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Kiewit | construction manager at risk | Northwater Treatment Plant | Denver Water |
| Jacobs | owner's representative | Northwater Treatment Plant | Denver Water |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| September 2018 | start | Whole project | Denver Water |
| June 2024 | opening | Whole project | Denver Water |
About the project
New drinking water treatment plant on a 183-acre site next to Ralston Reservoir, north of Golden in Jefferson County, treating up to 75 million gallons a day with a scalable design, built with an 8.5-mile pipeline to the Moffat facility and Moffat facility upgrades under Denver Water's North System Renewal. Construction commenced in September 2018; the plant began operations in 2024, completed under budget, and Denver Water celebrated its completion in June 2024. The fact sheet's cost table gives $520 million for the plant plus the Moffat facility upgrades and $80 million for the pipeline.
Sources
- Northwater Treatment Plant fact sheet (North System Renewal), Denver Water. Page 2, 'PROJECT COSTS': 'Northwater Treatment Plant + Moffat Facility Upgrades $520 million', 'Northwater Pipeline $80 million'; page 1: 'capable of treating up to 75 million gallons of water a day when it is operational in 2024', '183-acre site next to Ralston Reservoir, north of Golden'; page 2: 'A 8.5-mile pipeline from Northwater to Moffat' (PDF read locally with pymupdf from the file WebFetch downloaded from this URL on 2026-11-13; WebFetch's summariser could not read it). Consulted 13 Nov 2026.
- Denver Water celebrates new Northwater Treatment Plant, Denver Water, 21 Jun 2024. Body: 'The Northwater Treatment Plant began operations earlier this year and was completed under budget'; 'Denver Water in June 2024 celebrated the completion'; construction commenced September 2018; 'can clean up to 75 million gallons of water per day'; 'designed to be expanded if needed'; pipeline 'more than 8 miles'. Consulted 13 Nov 2026.
- Safety culture remains at forefront as Northwater Treatment Plant moves forward, Denver Water, 8 Sep 2023. 'This initiative led by Kiewit, the construction manager at risk for the project, is called CVIS for short.'. Consulted 18 Nov 2026.