Anderson Dam Seismic Retrofit Project
- Location
- Morgan Hill, CA, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of July 2026 (Valley Water).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Santa Clara Valley Water District (Valley Water) | |
| Category | Dams and hydro | |
| Amount | US$2.8 billion (US dollars), as of July 2026 | Valley Water |
| What the amount covers | Capital estimate, approx. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2.8 bn | Capital estimate, approx. | Whole project | Jul 2026 | Valley Water |
| US$1.88 bn | Contract value | One package | Jul 2026 | Valley Water |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Flatiron Dragados Sukut ADSRP Joint Venture | construction contractor | Anderson Dam Seismic Retrofit construction contract | Valley Water |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| July 24, 2026 | award | Whole project | Valley Water |
| 2027 | start | Whole project | Valley Water |
About the project
Seismic retrofit of Anderson Dam near Morgan Hill at a total cost of about $2.8 billion. Five supporting projects precede the dam work, among them a new tunnel replacing the dam's 4-foot-diameter outlet pipe with a 13-foot-diameter outlet; the Board awarded the $1.88 billion construction contract to Flatiron Dragados Sukut ADSRP Joint Venture on July 24, 2026, and construction at the dam begins in early 2027 for about seven years.
Sources
- Valley Water reaches major milestone in rebuilding Anderson Dam, Valley Water, 28 Jul 2026. Body: 'The board awarded the $1.88 billion construction contract to Flatiron Dragados Sukut ADSRP Joint Venture'; 'At a total cost of about $2.8 billion'; 'In early 2027, crews will begin construction at the dam'; 'Construction is expected to take about seven years'; 'on track to complete all five of the supporting projects before construction'. Consulted 13 Nov 2026.