Research record, not reviewed

Anderson Dam Seismic Retrofit Project

Location
Morgan Hill, CA, United States. Location shown at city level. See it on the map
Stage
Under construction, as of July 2026 (Valley Water).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorSanta Clara Valley Water District (Valley Water)
CategoryDams and hydro
AmountUS$2.8 billion (US dollars), as of July 2026Valley Water
What the amount coversCapital estimate, approx.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$2.8 bnCapital estimate, approx.Whole projectJul 2026Valley Water
US$1.88 bnContract valueOne packageJul 2026Valley Water
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Flatiron Dragados Sukut ADSRP Joint Ventureconstruction contractorAnderson Dam Seismic Retrofit construction contractValley Water
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
July 24, 2026awardWhole projectValley Water
2027startWhole projectValley Water
Dated milestones, at the precision of their source

About the project

Seismic retrofit of Anderson Dam near Morgan Hill at a total cost of about $2.8 billion. Five supporting projects precede the dam work, among them a new tunnel replacing the dam's 4-foot-diameter outlet pipe with a 13-foot-diameter outlet; the Board awarded the $1.88 billion construction contract to Flatiron Dragados Sukut ADSRP Joint Venture on July 24, 2026, and construction at the dam begins in early 2027 for about seven years.

Sources

  • Valley Water reaches major milestone in rebuilding Anderson Dam, Valley Water, 28 Jul 2026. Body: 'The board awarded the $1.88 billion construction contract to Flatiron Dragados Sukut ADSRP Joint Venture'; 'At a total cost of about $2.8 billion'; 'In early 2027, crews will begin construction at the dam'; 'Construction is expected to take about seven years'; 'on track to complete all five of the supporting projects before construction'. Consulted 13 Nov 2026.

See it on the map. How the atlas qualifies a record.