Carillon Generating Station Refurbishment Project

Location
Saint-André-d'Argenteuil, QC, Canada. Location shown at city level. See it on the map
Stage
Stage not confirmed: Not collected yet.
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorHydro-Québec
CategoryDams and hydro
AmountNot collected yet
Threshold evidenceA comparable project-wide cost is still needed
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
C$750 MBudgetOne packageOct 2020Hydro-QuébecC$750m is the investment announced for generating-unit replacement. Hydro-Québec separately discusses spillway work.
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
ANDRITZselected supplier (turbine manufacturer); supply and installation, with design, manufacturing, transportation, assembly, testing and commissioningRe-equipment of a first set of six turbine-generator units (generators, speed governors, Kaplan turbines)ANDRITZ Hydro Canada (via Cision Newswire)
ANDRITZcontractor (design, manufacture and installation of hydro-mechanical equipment)Rehabilitation of six hydraulic passages (intake gates, embedded guides, trash racks, hoists)ANDRITZ
Delivery parties, each named by the owner, a government or the company itself

About the project

C$750m is the investment announced for generating-unit replacement. Hydro-Québec separately discusses spillway work.

Scope notes

  • C$750m is the investment announced for generating-unit replacement. Hydro-Québec separately discusses spillway work. Hydro-Québec

Sources

  • Carillon Generating Station Refurbishment Project – official project evidence, Hydro-Québec, Oct 2020. C$750m is the investment announced for generating-unit replacement. Hydro-Québec separately discusses spillway work.. Consulted 9 Nov 2026.
  • ANDRITZ selected for the furbishment of the Carillon generating station, Canada, ANDRITZ Hydro Canada (via Cision Newswire), 21 Oct 2020. 'International technology group ANDRITZ has been selected by Hydro-Québec as the exclusive partner to re-equip potentially up to all fourteen 54-MW turbine generator units ... Hydro-Québec has awarded to ANDRITZ the supply and installation of a first set of six turbine-generator units on September 30, 2020. ... ANDRITZ is responsible for the design, manufacturing, transportation, assembly, testing...'. Consulted 18 Nov 2026.
  • ANDRITZ to rehabilitate the hydraulic passages at Carillon generating station, Canada, ANDRITZ, 20 Apr 2021. 'ANDRITZ has been awarded a contract by Hydro-Québec, Canada, to rehabilitate the hydraulic passages of the Carillon generating station ... design, manufacture and installation of hydro-mechanical equipment required for the repair and / or replacement of six hydraulic passages'. Consulted 18 Nov 2026.

Research leads not yet reviewed: www.renewcanada.net.

See it on the map. How the atlas qualifies a record.