Site C (John Horgan Dam and Generating Station)
- Location
- Fort St. John / Peace River, BC, Canada. Location shown at city level. See it on the map
- Stage
- Opened, as of August 9, 2025 (BC Hydro).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | BC Hydro | |
| Category | Dams and hydro | |
| Installed capacity lower bound | 1,100 MW | BC Hydro |
| Generating units | 6 | BC Hydro |
| Amount | C$16 billion (Canadian dollars), as of 2023 | BC Hydro |
| What the amount covers | Budget: Budget approved in June 2021 ('the Site C project budget is $16 billion with a project in-service date of calendar year 2025'). BC Hydro: the total includes capital costs, charges subject to regulatory deferral and certain operating expenditures. Not to be read as a construction cost. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| C$16 bn | Budget | Whole project | 2023 | BC HydroBudget approved in June 2021 ('the Site C project budget is $16 billion with a project in-service date of calendar year 2025'). BC Hydro: the total includes capital costs, charges subject to regulatory deferral and certain operating expenditures. |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Peace River Hydro Partners (ACCIONA Infrastructure Canada Inc., Petrowest Corporation and Samsung C&T Canada Ltd.) | contractor | Main civil works (earthfill dam, two diversion tunnels, roller-compacted-concrete foundation for the generating station and spillways) | BC Hydro |
| Aecon-Flatiron-Dragados-EBC Partnership (AFDE Partnership) (Aecon Constructors, a division of Aecon Construction Group Inc.; Flatiron Constructors Canada Limited; Dragados Canada, Inc.; EBC Inc.) | contractor | Generating station and spillways civil works (powerhouse, penstocks, spillways, power intakes) | BC Hydro |
| Voith Hydro Inc. | contractor (design, supply and installation) | Turbines and generators (six Francis turbines, six generators and associated equipment) | BC Hydro |
| Allteck Line Contractors Inc. | contractor | Site C transmission line construction (two 500 kV lines, 75 km) | BC Hydro |
| Mitchell Installations Ltd. | contractor | Balance of plant, mechanical work | BC Hydro |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| August 9, 2025 | Full operation | Whole project | BC Hydro |
About the project
BC Hydro announced commissioning of the sixth unit on August 9, 2025. The owner describes capacity of more than 1,100 MW and notes that some construction work remained.
Sources
- Site C project comes into full operation, BC Hydro, 9 Aug 2025. Sixth unit commissioning and generation capacity. Consulted 9 Nov 2026.
- BC Hydro and Power Authority 2023/24–2025/26 Service Plan, BC Hydro, 2023. Major capital projects and approved budget. Consulted 9 Nov 2026.
- BC Hydro awards contract for Site C main civil works to Peace River Hydro Partners, BC Hydro, 21 Dec 2015. 'Peace River Hydro Partners include ACCIONA Infrastructure Canada Inc., Petrowest Corporation and Samsung C&T Canada Ltd. ... includes the construction of an earthfill dam, two diversion tunnels and a roller-compacted-concrete foundation for the generating station and spillways ... The main civil works contract value is now confirmed at approximately $1.75 billion'. Consulted 18 Nov 2026.
- BC Hydro awards three Site C project contracts, BC Hydro, 16 Mar 2018. 'BC Hydro has signed a contract with the Aecon-Flatiron-Dragados-EBC Partnership (AFDE Partnership) for the generating station and spillways civil works component of the Site C project. The contract is valued at $1.6 billion (members per BC Hydro, 2017-12-21: "The AFDE Partnership includes Aecon Constructors, a division of Aecon Construction Group Inc. (Aecon), Flatiron Constructors Canada Limited...'. Consulted 18 Nov 2026.
- BC Hydro awards contract for Site C turbines and generators, BC Hydro, 6 Apr 2016. 'The award of the turbines and generators contract to Voith Hydro Inc. ... the design, supply and installation of six vertical axis, Francis-style turbines, six generators and associated equipment ... The contract has a value of approximately $470 million'. Consulted 18 Nov 2026.
- B.C.-based company awarded contract to build Site C transmission line, BC Hydro, 20 Jun 2018. 'BC Hydro has awarded the Site C transmission line construction contract to Allteck Line Contractors Inc.'. Consulted 18 Nov 2026.
- BC Hydro awards Site C balance of plant mechanical contract, BC Hydro, 29 Jul 2021. 'BC Hydro today announced it has awarded the $70 million Site C balance of plant contract for mechanical work to Mitchell Installations Ltd.'. Consulted 18 Nov 2026.