Research record, not reviewed

Expo and Millennium Line Upgrade Program (Mark V SkyTrain fleet)

Location
Vancouver, BC, Canada. Location shown at city level. See it on the map
Stage
Under construction, as of July 2025 (TransLink).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorTransLink
CategoryTransit vehicles
Vehicles235TransLink
AmountC$1.47 billion (Canadian dollars), as of December 2020TransLink
What the amount coversProgramme value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
C$1.47 bnProgramme valueProgrammeDec 2020TransLink
C$721 MContract valueOne packageDec 2020TransLink
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Bombardier Transportationvehicle supplierMark V SkyTrain carsTransLink
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
December 17, 2020awardWhole projectTransLink
July 10, 2025openingWhole projectTransLink
2029planned completionWhole projectTransLink
Dated milestones, at the precision of their source

About the project

TransLink's Expo Millennium Line Upgrade Program is funded with $1.47 billion through the Investing in Canada Infrastructure Program, with contributions from Canada, British Columbia and TransLink; it includes new SkyTrain cars to replace the original Mark I fleet and add capacity on the Expo and Millennium lines, and TransLink is upgrading stations, key systems and power on the two lines. The December 2020 order of 205 Mark V cars from Bombardier Transportation was worth $721.2 million; the first Mark V train entered service on the Expo Line on 10 July 2025, and TransLink states 235 Mark V cars (47 trains) will be delivered by 2029 to serve the Expo and Millennium lines.

Sources

  • TransLink overhauls aging fleet with largest ever SkyTrain order, TransLink, 17 Dec 2020. Release: 205 new cars, Bombardier, $721.2 million contract, part of the $1.47 billion Expo Millennium Line Upgrade Program funded through ICIP. Consulted 12 Nov 2026.
  • A new era for SkyTrain: The Mark V rolls into service, TransLink, 10 Jul 2025. Release: first Mark V train in service July 10, 2025; 235 Mark V cars (47 trains) to be delivered by 2029. Consulted 12 Nov 2026.
  • SkyTrain Expansion Program, TransLink. Program page: new, longer trains rolling into service; stations, key systems and power on the Expo and Millennium lines being upgraded; new operations, storage and maintenance facilities under construction (the page's 2029 date refers to the Broadway Subway and Surrey Langley extensions). Consulted 12 Nov 2026.

See it on the map. How the atlas qualifies a record.