Research record, not reviewed
Green Line Type 10 Vehicles
- Location
- Boston, MA, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of November 2026 (MBTA).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Massachusetts Bay Transportation Authority (MBTA) | |
| Category | Transit vehicles | |
| Vehicles | 102 | MBTA |
| Amount | US$816 million (US dollars), as of November 2026 | MBTA |
| What the amount covers | Project value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| CAF USA Inc. | vehicle manufacturer | 102 Type 10 light rail vehicles | MBTA |
About the project
Procurement of 102 new low-floor Type 10 light rail vehicles for the MBTA Green Line from CAF USA under a contract of $810,925,658 awarded by the MBTA Board (announced September 2, 2022), covering manufacture, delivery, tools, testing and training; the project page gives the value as $816 million. A pilot vehicle has been assembled and is in testing; the first vehicles are expected in service in 2027 and all 102 delivered by the end of 2031.
Sources
- MBTA Board of Directors Awards Contract for the Type 10 Supercars, Ensuring a Standard of Safety and Accessibility for Green Line Riders, MBTA, 2 Sep 2022. Body: '$810,925,658'; 102 vehicles; CAF USA Inc.; first pilot vehicles spring 2026. Consulted 12 Nov 2026.
- Green Line Type 10 Vehicles (project page), MBTA. Page: '$816 million', 102 vehicles, 'Pilot vehicle assembled and in testing', first in service 2027, all by end of 2031. Consulted 12 Nov 2026.