Mactaquac Life Achievement Project
- Location
- Mactaquac, NB, Canada. Location shown at city level. See it on the map
- Stage
- Stage not confirmed: Not collected yet.
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | NB Power | |
| Category | Dams and hydro | |
| Amount | C$7.6 billion to C$9 billion (Canadian dollars) | NB Power |
| What the amount covers | Capital estimate range: Current estimate includes interest and inflation over the life of the project. The estimate is scope-qualified and cannot be directly compared to construction-only costs. Not to be read as a construction cost. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| C$7.6 bn to 9 bn | Capital estimate range | Whole project | Undated | NB PowerCurrent estimate includes interest and inflation over the life of the project. The estimate is scope-qualified and cannot be directly compared to construction-only costs. |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Mactaquac Improvement Partnership (a consortium of Aecon, FlatironDragados and Green Infrastructure Partners) | contractor, development phase agreement (does not authorize construction) | Civil work, 12-month development phase (design, scheduling and cost estimates) | NB Power |
| Andritz Canada Inc. | turbine and generator contractor (planning-phase agreement) | Turbine and generator component (rehabilitation and modernization of the generating units) | NB Power |
About the project
Current estimate includes interest and inflation over the life of the project. The estimate is scope-qualified and cannot be directly compared to construction-only costs.
Scope notes
- Current estimate includes interest and inflation over the life of the project. The estimate is scope-qualified and cannot be directly compared to construction-only costs. NB Power
Sources
- Mactaquac Life Achievement Project – official project evidence, NB Power. Current estimate includes interest and inflation over the life of the project. The estimate is scope-qualified and cannot be directly compared to construction-only costs.. Consulted 9 Nov 2026.
- NB Power advances planning for the Mactaquac Life Achievement Project, NB Power, 30 Jul 2026. 'NB Power has signed an agreement with the Mactaquac Improvement Partnership, a consortium of Aecon, FlatironDragados and Green Infrastructure Partners. ... This agreement is for the development phase only and does not authorize the contractor to proceed with construction. ... Subject to successful completion of this phase and the necessary approvals, the construction phase is expected to begin...'. Consulted 18 Nov 2026.
- NB Power advances next phase of planning for MLAP turbines and generators, NB Power, 27 Aug 2026. 'NB Power has signed an agreement with Andritz Canada Inc. to advance the turbine and generator component of the Mactaquac Life Achievement Project (MLAP)'. Consulted 18 Nov 2026.