Research record, not reviewed
YUL Montréal-Trudeau Flight Plan 2028-2035 transformation
- Location
- Dorval, QC, Canada. Location shown at city level. See it on the map
- Stage
- Under construction, as of July 2025 (Canada Infrastructure Bank).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | ADM Aéroports de Montréal | |
| Category | Airports | |
| Amount | C$10 billion (Canadian dollars), as of July 2025 | Canada Infrastructure Bank (via Cision Newswire) |
| What the amount covers | Programme value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| C$10 bn | Programme value | Programme | Jul 2025 | Canada Infrastructure Bank (via Cision Newswire) |
| C$1 bn | Funding commitment | Programme | Jul 2025 | Canada Infrastructure Bank |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| July 16, 2025 | financing | Whole project | Canada Infrastructure Bank (via Cision Newswire) |
About the project
ADM Aéroports de Montréal's $10 billion, ten-year capital program for YUL Montréal-Trudeau: reconfigured access roads, new parking and pick-up and drop-off areas, a building connecting the future REM station to the terminal, higher-capacity baggage systems, a new satellite jetty with additional gates and processing areas, and new taxiways and aprons. The Canada Infrastructure Bank reached financial close on a $1 billion, 30-year loan for the program in July 2025 and lists the project as under construction.
Sources
- CIB supports transformation of Montréal-Trudeau International Airport, Canada Infrastructure Bank (via Cision Newswire), 16 Jul 2025. Release: $1 billion CIB loan; ADM's Flight Plan 2028-2035 is a $10 billion investment over 10 years; list of cityside, terminal and airside projects. Consulted 12 Nov 2026.
- Montréal-Trudeau International Airport Transformation, Canada Infrastructure Bank. Project page: $1 billion loan, 30-year term, status 'Under construction', Flight Plan 2028-2035. Consulted 12 Nov 2026.