Washington Dulles Concourse E (Tier-2 Concourse East)
- Location
- Dulles (Loudoun County), VA, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of November 2026 (Metropolitan Washington Airports Authority).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Metropolitan Washington Airports Authority | |
| Category | Airports | |
| Amount | US$674.7 million (US dollars), as of April 2022 | Metropolitan Washington Airports Authority |
| What the amount covers | Budget. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$675 M | Budget | Whole project | Apr 2022 | Metropolitan Washington Airports Authority |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| United Airlines | airline tenant of the 14 gates | Concourse E | Metropolitan Washington Airports Authority |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| April 2022 | approval | Whole project | Metropolitan Washington Airports Authority |
| November 10, 2026 | opening | Whole project | Metropolitan Washington Airports Authority |
About the project
New 435,000 sq ft concourse at Washington Dulles International Airport with 14 United Airlines gates, direct AeroTrain access and new dining and retail, replacing a 110,000 sq ft facility and built as the first of four concourse phases of the airport's transformation programme. In April 2022 the signatory airlines gave the project Majority-in-Interest approval and Airports Authority staff asked the Board to add it to the capital construction programme at a total uninflated project cost of $674.7 million (up to $545.7 million bond-financed). Concourse E opened to flights on November 10, 2026.
Sources
- Dulles International Unveils Concourse E, Metropolitan Washington Airports Authority, 9 Nov 2026. Body: 435,000-square-foot facility; 14 new United gates; first of four concourse construction phases; flights from November 10. Consulted 12 Nov 2026.
- Report to the Finance Committee: Recommendation to Amend the Aviation Enterprise Fund Capital Construction Program Budget to Add Tier-2 Concourse (East) Project at Washington Dulles International Airport, Metropolitan Washington Airports Authority, Apr 2022. Report (April 2022, PDF): 'The total uninflated project cost is $674.7 million, requiring $670.7 million to be added to the initial $4.0 million budgeted in the 2022 Budget'; 'a new 14-gate concourse that would replace the single level regional gate portion of Concourse A'; 'nearly 400,000 square feet versus 110,000 square feet currently'; 'up to $545.7 million in bond financing, with the remaining $125.0 million' from Bipartisan Infrastructure Law grants. Consulted 12 Nov 2026.
- Official Statement, Airport System Revenue Bonds Series 2023A (dated 24 May 2023), Metropolitan Washington Airports Authority, 24 May 2023. 'In April 2022 the Airports Authority received Majority In Interest approval from the Signatory Airlines in accordance with the Airline Agreement for an additional project at Dulles International Airport. ... The concourse is referred to as the Tier 2 Concourse (East)'. Consulted 19 Nov 2026.