RiverRenew Tunnel System
- Location
- Alexandria, VA, United States. Location shown at city level. See it on the map
- Stage
- Stage not confirmed: Not collected yet.
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | AlexRenew | |
| Category | Water | |
| Amount | US$655 million (US dollars), as of February 3, 2021 | U.S. Environmental Protection Agency |
| What the amount covers | Cost of the WIFIA-financed scope: Cost for the scope covered in this EPA fact sheet. It can be a phase or tranche and is not automatically the latest programme-wide cost. | |
| Threshold evidence | Only a financed-scope figure meets the threshold; to reconcile |
Water projects are counted apart and left out of totals while their place in the atlas is decided.
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$655 M | Cost of the WIFIA-financed scope | Scope financed by WIFIA | 3 Feb 2021 | U.S. Environmental Protection AgencyCost for the scope covered in this EPA fact sheet. It can be a phase or tranche and is not automatically the latest programme-wide cost. |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Traylor-Shea Joint Venture (Traylor Bros, Inc. and J.F. Shea Co. joint venture) | design-builder | RiverRenew Tunnel System Project | Virginia Department of Environmental Quality (transmitting AlexRenew's 2021 General Assembly Report) |
| Brown and Caldwell | owner's advisor | RiverRenew program, professional services contract 17-022 | AlexRenew |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| February 3, 2021 | Financing closed | Scope financed by WIFIA | U.S. Environmental Protection Agency |
About the project
System to intercept four combined sewer outfalls and route flows to treatment.
Scope notes
- System to intercept four combined sewer outfalls and route flows to treatment. U.S. Environmental Protection Agency
Sources
- RiverRenew Tunnel System – WIFIA profile, U.S. Environmental Protection Agency. Total WIFIA Project Costs; Project Description. The EPA closed-loan register gives the separate closing date.. Consulted 9 Nov 2026.
- WIFIA Closed Loans, U.S. Environmental Protection Agency. Borrower, Project Name, Close Date and Loan Amount columns.. Consulted 9 Nov 2026.
- Alexandria Combined Sewer Overflow Outfall Progress Report (2021), Virginia Department of Environmental Quality (transmitting AlexRenew's 2021 General Assembly Report), 1 Jan 2022. 'AlexRenew awarded the $454.4 million Tunnel System Project to Traylor-Shea Joint Venture (Traylor-Shea) on November 17, 2020. Notice to Proceed with design-build services was subsequently issued on December 1, 2020. [...] The Traylor-Shea design-build team consists of Traylor Bros, Inc. and J.F. Shea Co. a joint venture, with support from Jacobs Engineering and Kokosing Construction Co.'. Consulted 18 Nov 2026.
- RiverRenew Overview (program dashboard, data as of July 31, 2022), AlexRenew. 'RiverRenew Tunnel Project Contracts: Vendor Role Contract Type Contract No. Contract Date [...] Traylor-Shea Joint Venture Design-Builder Tunnel System Project Design-Build 19-079 Dec 2020 [...] Brown and Caldwell Owner's Advisor Professional Services 17-022 Nov 2017'. Consulted 18 Nov 2026.