Research record, not reviewed

DC Clean Rivers Project

Location
Washington, DC, United States. Location shown at city level. See it on the map
Stage
Under construction, as of April 2024 (DC Water).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorDC Water
CategoryWater
Tunnel length5.5 miDC Water
AmountUS$2.99 billion (US dollars), as of April 2024DC Water
What the amount coversProgramme value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$2.99 bnProgramme valueProgrammeApr 2024DC Water
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Traylor Bros., Inc.design-build contractorBlue Plains Tunnel (24,000-foot, 26-foot-diameter CSO tunnel; completed)Traylor Bros., Inc.
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
November 2023otherWhole projectDC Water
2024startWhole projectDC Water
2030planned completionWhole projectDC Water
Dated milestones, at the precision of their source

About the project

DC Water's 25-year combined sewer overflow control program (2005 to 2030) of deep storage tunnels and green infrastructure for the Anacostia and Potomac rivers and Rock Creek, cutting overflows by 96 percent. The Potomac River Tunnel, about 5.5 miles of 18-foot finished tunnel from Georgetown to a connection at Joint Base Anacostia-Bolling, conveying flows to the Blue Plains plant, with five large and three drop or vent shafts, is the next major phase, with construction from 2024 to the 2030 consent decree deadline.

Sources

  • Clean Rivers Project - Potomac River Tunnel, briefing to the Washington Area Bicyclist Association, DC Water, 10 Apr 2024. Slide 5 'Clean Rivers Project': 'DC Clean Rivers Project: $2.99 Billion', 'Nitrogen Removal: $950 Million', 'Total > $ 3.4 Billion', '25 yr implementation (2005 - 2030)', '96% reduction in CSOs'; slide 11 'Potomac River Tunnel': 'Approx 5.5 miles of 18' ID finished tunnel', '7 shafts', 'NTP: Nov 2023', 'Construction Start: 2024', 'Consent Decree Deadline: 2030'; cover 'April 10, 2024' (PDF read locally with pymupdf from the file WebFetch downloaded from this URL on 2026-11-13; WebFetch's summariser could not read it). Consulted 13 Nov 2026.
  • Blue Plains Tunnel (project page), Traylor Bros., Inc.. 'Owner: District of Columbia Water and Sewer Authority [...] The Blue Plains Tunnel project was the design-build of a 24,000-foot-long, 26-foot-diameter CSO tunnel constructed in soft ground under and adjacent to the Potomac and Anacostia Rivers.'. Consulted 18 Nov 2026.
  • DC Clean Rivers Project, DC Water. 'The Anacostia River and Potomac River tunnel systems include more than 18 miles of tunnels'. Consulted 19 Nov 2026.
  • Potomac River Tunnel Fact Sheet, DC Water, 21 Nov 2024. 'The Potomac River Tunnel is the next major phase of the DC Clean Rivers Project. ... Construction of 5 large shafts and 3 drop/vent shafts'. Consulted 19 Nov 2026.

See it on the map. How the atlas qualifies a record.