CMH Next: John Glenn Columbus International Airport New Terminal
- Location
- Columbus, OH, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of February 2025 (Columbus Regional Airport Authority).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Columbus Regional Airport Authority | |
| Category | Airports | |
| Amount | US$2 billion (US dollars), as of February 2025 | Columbus Regional Airport Authority |
| What the amount covers | Capital estimate, approx. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2 bn | Capital estimate, approx. | Whole project | Feb 2025 | Columbus Regional Airport Authority |
| US$1.2 bn | Funding commitment | Whole project | Feb 2025 | Columbus Regional Airport Authority |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Hensel Phelps | construction manager at risk | CMH Next new terminal (preconstruction and construction services) | Columbus Regional Airport Authority (CMH Next project site) |
| Elford | construction team member | CMH Next new terminal | Columbus Regional Airport Authority (CMH Next project site) |
| CK Construction | construction team member | CMH Next new terminal | Columbus Regional Airport Authority (CMH Next project site) |
| Gensler | architect (architecture & design) | CMH Next new terminal design | Columbus Regional Airport Authority (CMH Next project site) |
| Moody Nolan | architect (local partner) | CMH Next new terminal design | Columbus Regional Airport Authority (CMH Next project site) |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| December 2024 | Groundbreaking | Whole project | Columbus Regional Airport Authority |
| February 3, 2025 | financing | Whole project | Columbus Regional Airport Authority |
| 2029 | planned opening | Whole project | Columbus Regional Airport Authority |
About the project
New terminal for John Glenn Columbus International Airport. The Columbus Regional Airport Authority broke ground on the $2 billion CMH Next project in December 2024 and expects it to open in 2029. In February 2025 the authority announced the sale of approximately $1.2 billion of general airport revenue bonds to finance construction.
Sources
- Strong, successful bond issuance supports CMH Next terminal project, Columbus Regional Airport Authority, 3 Feb 2025. Body: 'CRAA broke ground on the $2 billion CMH Next project in December 2024 ... expected to open in 2029'; '$1.2 billion in general airport revenue bonds'. Consulted 12 Nov 2026.
- FAQs, Columbus Regional Airport Authority (CMH Next project site). 'Columbus Regional Airport Authority named Hensel Phelps the Construction Manager at Risk to provide preconstruction and construction services'. Consulted 18 Nov 2026.
- Opportunities: Our partners: Building the future together, Columbus Regional Airport Authority (CMH Next project site). 'Construction ... Elford – The largest locally owned construction company in Central Ohio, bringing decades of experience to the project'. Consulted 18 Nov 2026.