Project Clean Lake
- Location
- Cleveland, OH, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of December 2025 (Northeast Ohio Regional Sewer District).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Northeast Ohio Regional Sewer District | |
| Category | Water | |
| Amount | US$3 billion (US dollars), as of March 2026 | Northeast Ohio Regional Sewer District |
| What the amount covers | Programme value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$3 bn | Programme value | Programme | Mar 2026 | Northeast Ohio Regional Sewer District |
| US$325 M | Construction budget | One package | Mar 2026 | Northeast Ohio Regional Sewer District |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| 2036 | planned completion | Whole project | Northeast Ohio Regional Sewer District |
About the project
A $3 billion program begun in 2011 under a federal consent decree that became official in July 2011 to cut combined sewer overflows to Lake Erie from 4.5 billion gallons to 494 million gallons a year through seven storage tunnels of two to five miles, treatment plant work and green infrastructure. The Euclid Creek, Dugway, Doan Valley and Westerly tunnels are operational, the Shoreline Storage Tunnel (online in 2026) and the Southerly Storage Tunnel are under construction and the Big Creek Tunnel, the last of them, is scheduled for fall 2026 to 2031 at a construction cost of $325 million; the District has spent or awarded more than $2.4 billion to date and the program is complete in 2036.
Sources
- About Project Clean Lake, Northeast Ohio Regional Sewer District. Body: 'Project Clean Lake is a 25-year program'; 'reduce the total volume of raw sewage discharges from 4.5 billion gallons to 494 million gallons annually'; 'We will construct seven tunnels, ranging from two to five miles in length'; consent decree 'became official in July 2011'; tunnel status list (as of December 2025); 'complete in 2036'; 'We have spent or awarded more than $2.4 billion to date'. The '$3 billion' the researcher quoted from this page was not in the text WebFetch returned on 2026-11-13 (asked twice). Consulted 13 Nov 2026.
- Big Creek Tunnel fact sheet, Northeast Ohio Regional Sewer District, 4 Mar 2026. 'ABOUT THE PROJECT': 'part of Project Clean Lake, a $3 billion, 24-year program the Northeast Ohio Regional Sewer District (NEORSD) began in 2011 to meet Clean Water Act standards'; 'PROJECT COST AND TIMELINE': 'BCT construction is scheduled for fall 2026 - 2031. The cost of construction is $325 million'; slides dated 3/4/2026 (PDF read locally with pymupdf from the file WebFetch downloaded from this URL on 2026-11-13; WebFetch's summariser could not read it). Consulted 13 Nov 2026.
- It's official: CSO consent decree is signed, Northeast Ohio Regional Sewer District, 7 Jul 2011. Body: consent decree 'approved by the US District Court on June 30 and filed on the Court's docket today'; '$3 billion of investments'; '25-year consent decree'. Consulted 13 Nov 2026.