Peninsula Corridor Electrification Project
- Location
- San Carlos, CA, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of March 2025 (Caltrain (Peninsula Corridor Joint Powers Board)).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Peninsula Corridor Joint Powers Board (Caltrain) | |
| Category | Rail | |
| Route length | 51 mi | Caltrain (Peninsula Corridor Joint Powers Board) |
| Vehicles | 19 | Caltrain (Peninsula Corridor Joint Powers Board) |
| Amount | US$2.443 billion (US dollars), as of March 2025 | Caltrain (Peninsula Corridor Joint Powers Board) |
| What the amount covers | Budget. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2.44 bn | Budget | Whole project | Mar 2025 | Caltrain (Peninsula Corridor Joint Powers Board) |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Stadler | EMU manufacturer | 19 electric multiple-unit trainsets (17 delivered by January 2025) | Caltrain (Peninsula Corridor Joint Powers Board) |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| December 6, 2021 | budget revision | Whole project | Caltrain (Peninsula Corridor Joint Powers Board) |
| September 21, 2024 | opening | Whole project | Caltrain (Peninsula Corridor Joint Powers Board) |
| December 20, 2024 | final acceptance | Whole project | Caltrain (Peninsula Corridor Joint Powers Board) |
About the project
Electrification of 51 miles of the Caltrain corridor between San Francisco and San Jose (Tamien) with overhead catenary, traction power and 19 Stadler electric multiple-unit trainsets (17 delivered by January 2025), replacing diesel service. The JPB's programme budget is $2.44 billion ($2,442,690,697, fully funded). Caltrain began full electrified revenue service on September 21, 2024 and reached final acceptance of the project on December 20, 2024.
Sources
- JPB Board of Directors Meeting of March 6, 2025: Caltrain Electrification project update (agenda packet), Caltrain (Peninsula Corridor Joint Powers Board), 6 Mar 2025. Project update: '$2,442,690,697'; 'Board adopted budget of $2.44 billion'; 'commenced full electrified revenue service on September 21, 2024'; Final Acceptance December 20, 2024; 51 miles; 17 EMU trainsets. Consulted 12 Nov 2026.
- Cost of Caltrain Electrification Increases, Project on Track for 2024, Caltrain, 6 Dec 2021. Body: cost increased to '$2.44 billion', an additional '$462 million over the initial estimate'. Consulted 12 Nov 2026.