Research record, not reviewed
Transbay Program Downtown Extension (The Portal)
- Location
- San Francisco, CA, United States. Location shown at city level. See it on the map
- Stage
- Development, as of June 2026 (Transbay Joint Powers Authority).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Transbay Joint Powers Authority | |
| Category | Rail | |
| Route length | 2.2 mi | Transbay Joint Powers Authority |
| Stations | 2 | Transbay Joint Powers Authority |
| Amount | US$8.254 billion (US dollars), as of June 2026 | Transbay Joint Powers Authority |
| What the amount covers | Capital estimate: FTA-approved project budget based on the 2023 Entry-to-Engineering estimate, 'inclusive of the completed train box, contingency, and financing costs': it includes financing, so it is not a construction cost. Not to be read as a construction cost. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$8.25 bn | Capital estimate | Whole project | Jun 2026 | Transbay Joint Powers AuthorityFTA-approved project budget based on the 2023 Entry-to-Engineering estimate, 'inclusive of the completed train box, contingency, and financing costs': it includes financing, so it is not a construction cost. |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| July 16, 2036 | FTA service-year assumption | Whole project | Transbay Joint Powers Authority |
About the project
A downtown extension from the Caltrain corridor to Salesforce Transit Center. TJPA's $8.254 billion project budget includes contingency and financing costs.
Sources
- FY 2027 CIG and EPD Project Profiles, Federal Transit Administration, Apr 2026. PDF page 15 · Profile summary, description and status. Consulted 9 Nov 2026.
- Capital Investment Grants Dashboard – September 2026, Federal Transit Administration, 11 Sep 2026. Page 1 project phase, scope and Project Cost column. The PDF indicates a 10 September update.. Consulted 9 Nov 2026.
- The Portal Monthly Status Report, June 2026, Transbay Joint Powers Authority, Jun 2026. 'The Portal continues to advance through the Engineering phase of the Federal Transit Administration's (FTA) Capital Investment Grants (CIG) program'; 'The FTA-approved project budget is $8.254 billion, based on the Entry-to-Engineering cost estimate submitted in 2023'; 'the 2023 cost estimate of $8.254 billion, inclusive of the completed train box, contingency, and financing costs'; 'a target ready-for-service date of July 16, 2036'; 'The total project length is 2.2 miles'. Consulted 19 Nov 2026.
- About The Portal, Transbay Joint Powers Authority. 'The total planned construction length of the Portal is approximately 2.2 miles'; 'The TJPA is leading the delivery of The Portal, in cooperation with five other agencies'. Consulted 19 Nov 2026.
Research leads not yet reviewed: www.transit.dot.gov.