Train Control Upgrade Project (TCUP)
- Location
- San Francisco, CA, United States. Location shown at city level. See it on the map
- Stage
- Development, as of November 2026 (SFMTA).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | San Francisco Municipal Transportation Agency (SFMTA) | |
| Category | Urban transit | |
| Amount | US$700 million (US dollars), as of October 2024 | SFMTA |
| What the amount covers | Budget. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Hitachi Rail | train control supplier | CBTC design and supply | SFMTA |
About the project
Replacement of the Muni Metro subway's train control system with communications-based train control, extended in seven phases to all on-street Metro corridors (J, K, L, M, N and T lines). A supplier contract with Hitachi Rail of up to $212 million for nine years of design and procurement, within a total project budget of $700,000,000, was put to the SFMTA Board on October 15, 2024 and finalized in January 2025; the budget is funded mainly by $375 million of FTA transit capital priorities and a $130 million TIRCP grant. Detailed design began in 2025 and completion is projected for 2034.
Sources
- Train Control Upgrade Project, SFMTA Board of Directors presentation, October 15, 2024, SFMTA, 15 Oct 2024. Slides 14-15: Total Train Control Capital Budget $700M; Total Project Budget $700,000,000; supplier contract $212M; FTA $375,000,000; TIRCP $130,000,000. Consulted 12 Nov 2026.
- Train Control Upgrade Project page, SFMTA. Page: 'TCUP is projected to be completed in seven phases'; 'Current Phase or Stage: Detailed Design. Predicted Completion: 2034'; Hitachi Rail named as partner. Consulted 12 Nov 2026.
- SFMTA partners with Hitachi Rail to upgrade Muni Metro technology (project update), SFMTA. 'We finalized a historic supplier contract with Hitachi Rail in January 2025'. Consulted 19 Nov 2026.