Birmingham Northern Beltline

Location
Birmingham, AL, United States. Location shown at city level. See it on the map
Stage
Under construction, as of 2025 (Alabama Department of Transportation).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorAlabama Department of Transportation
CategoryHighways
Route length52 miFederal Highway Administration
AmountUS$1.926 billion (US dollars), as of November 2026Federal Highway Administration
What the amount coversCapital estimate.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.93 bnCapital estimateWhole projectNov 2026Federal Highway Administration
Financial records, each with its kind and scope

Contracts and teams

Contracts and teams: Not found in the sources consulted.

Milestones

DateMilestoneScopeSource
September 2048completionWhole projectFederal Highway Administration
2026openingWhole projectAlabama Department of Transportation
Dated milestones, at the precision of their source

About the project

A proposed 52-mile freeway around the north of Birmingham, from I-59/20 west of the city to I-59 on the east, delivered in phases by design-bid-build. FHWA lists a current total cost of $1,926 million with $760 million funded, and a current completion date of September 2048. ALDOT's FY2025 annual report says multiple bridges are under construction on the first section, SR-79 to SR-75, for a phase expected to welcome traffic by the end of 2026.

Sources

  • FHWA Active Major Project Status Report (FOIS), Federal Highway Administration. Project 'Birmingham Northern Beltline - BNB (Corridor X-1, AHS)': Total Cost Baseline $1,966 Current $1,926; Funded Phase Cost $760; Completion Current Sep-2048. Consulted 12 Nov 2026.
  • ALDOT 2025 Annual Report, Alabama Department of Transportation, 2025. 'Birmingham Northern Beltline (SR-79 to SR-75): ... Multiple bridges are under construction between SR-79 and SR-75 for the phase expected to welcome traffic by the end of 2026'. Consulted 12 Nov 2026.

See it on the map. How the atlas qualifies a record.