Research record, not reviewed
I-285 Eastside Express Lanes
- Location
- Tucker, GA, United States. Location shown at city level. See it on the map
- Stage
- Planning, as of November 2026 (Georgia Department of Transportation).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Georgia Department of Transportation | |
| Category | Highways | |
| Amount | US$835 million (US dollars), as of July 2020 | Georgia Department of Transportation |
| What the amount covers | Budget. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$835 M | Budget | Whole project | Jul 2020 | Georgia Department of Transportation |
Contracts and teams
Contracts and teams: No construction contract awarded yet Georgia Department of Transportation.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| March 1, 2024 | procurement | Whole project | Georgia Department of Transportation |
About the project
Express lanes on the eastern side of I-285 around Atlanta, part of GDOT's Major Mobility Investment Program and of the I-285 Express Lanes P3 procurement for which GDOT released a request for information on March 1, 2024. GDOT's 2020 MMIP budget table put the Eastside Express Lanes at $835 million in year-of-expenditure dollars; the MMIP site says the conceptual designs and environmental analyses are still being evaluated and the federal environmental document must be updated.
Sources
- MMIP Projects: Updated Project Budget (estimate, millions), Georgia Department of Transportation, Jul 2020. Table rows 'I-285 Eastside Express Lanes $835; I-285 Eastside Express Lanes $798; I-285 Eastside Advanced Improvement Projects $37'. Consulted 12 Nov 2026.
- I-285 Express Lanes (Major Mobility Investment Program), Georgia Department of Transportation. 'On Friday, March 1, 2024, Georgia DOT released the I-285 Express Lanes – Request for Information (RFI)'; 'RFI Notice (RFI-484-03012024P3)'; Eastside and Westside 'conceptual designs and environmental analyses are still being evaluated and developed'; 'the federal environmental document for each project must be updated'. Consulted 12 Nov 2026.
- I-285 Express Lanes (Major Mobility Investment Program), Georgia Department of Transportation. 'Design-Build-Finance-Operate-Maintain contracting approach'; 'Draft Environmental Impact Statement (DEIS) is in development'; 'Procurement, final design, and construction of the proposed I-285 Top End Express Lanes project will be phased'. Consulted 12 Nov 2026.