Research record, not reviewed
Complete 540 – Phase 2
- Location
- Wake County, NC, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of October 7, 2026 (North Carolina Department of Transportation).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | North Carolina Turnpike Authority | |
| Category | Highways | |
| Amount | US$1.1 billion (US dollars), as of October 2025 | North Carolina Turnpike Authority |
| What the amount covers | Capital estimate: 'Complete Phase 2 is anticipated to open in 2028 at a cost of $1.1 billion.' (NCTA annual report for the fiscal year ended June 30, 2025.) The $1.3 billion previously shown, from the U.S. DOT Build America Bureau's project page, could not be read on 2026-11-19. | |
| Threshold evidence | Only a financed-scope figure meets the threshold; to reconcile |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$1.1 bn | Capital estimate | Whole project | Oct 2025 | North Carolina Turnpike Authority, p. 16'Complete Phase 2 is anticipated to open in 2028 at a cost of $1.1 billion.' (NCTA annual report for the fiscal year ended June 30, 2025.) The $1.3 billion previously shown, from the U.S. DOT Build America Bureau's project page, could not be read on 2026-11-19. |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Branch-S.T. Wooten Joint Venture | design-build contractor (awardee) | R-2829A: NC-540 (Triangle Expressway Southeast Extension) from I-40 to south of SR 2542 (Rock Quarry Road); Contract No. C204824 | North Carolina Department of Transportation |
| Flatiron Fred Smith Company JV | design-build contractor (awardee) | R-2829B: NC-540 (Triangle Expressway Southeast Extension) from south of SR 2542 (Rock Quarry Road) to I-87/US 64/US 264; Contract No. C204825 | North Carolina Department of Transportation |
About the project
Phase 2 extends the Triangle Expressway from I-40 toward the existing I-540 and I-87 corridor. It has a different financial boundary from the Complete 540 programme.
Scope notes
- Phase 2 extends the Triangle Expressway from I-40 toward the existing I-540 and I-87 corridor. It has a different financial boundary from the Complete 540 programme. U.S. DOT Build America Bureau
- Sponsor construction or operating announcement for the project. North Carolina Department of Transportation
Sources
- Complete 540 – Phase 2, U.S. DOT Build America Bureau, 1 Feb 2024. Phase 2 extends the Triangle Expressway from I-40 toward the existing I-540 and I-87 corridor. It has a different financial boundary from the Complete 540 programme.. Consulted 9 Nov 2026.
- Complete 540 construction and Neuse River detour, North Carolina Department of Transportation, 7 Oct 2026. Sponsor construction or operating announcement for the project.. Consulted 9 Nov 2026.
- Notification of Award, R-2829A (Design-Build Program), North Carolina Department of Transportation, 31 Oct 2023. 'BRANCH-S.T. WOOTEN JOINT VENTURE ... Contract No. C204824 ... Tip No. R-2829A ... NC-540 (TRIANGLE EXPRESSWAY SOUTHEAST EXTENSION) FROM I-40 TO SOUTH OF SR-2542 (ROCK QUARRY ROAD). ... the Secretary Of Transportation has awarded you the contract for the above project based on the bid submitted on October 17, 2023 in the amount of $287,285,000.00.'. Consulted 18 Nov 2026.
- Notification of Award, R-2829B (Design-Build Program), North Carolina Department of Transportation, 1 Sep 2023. 'Contract No. C204825 ... Tip No. R-2829B ... NOTIFICATION OF AWARD FLATIRON FRED SMITH COMPANY JV ... This is official notification that the Secretary Of Transportation has awarded you the contract for the above project based on the bid submitted on August 29, 2023 in the amount of $449,946,000.00.'. Consulted 18 Nov 2026.
- Annual Comprehensive Financial Report, Fiscal Years ended June 30, 2025 and 2024, North Carolina Turnpike Authority, 29 Oct 2025. 'The North Carolina Turnpike Authority proposed Complete 540 Phase 2 project (STIP Project R-2829) will extend the Triangle Expressway System from I-40 to I-540/I-87/U.S. 64/U.S. 264 in Knightdale ... Two Design-Build contracts, one in September and one in November of 2023, were awarded to break ground on May 16, 2024. Complete Phase 2 is anticipated to open in 2028 at a cost of $1.1 billion.'. Consulted 19 Nov 2026.