Research record, not reviewed
DFW Terminal C Reimagining
- Location
- Dallas Fort Worth International Airport, TX, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of October 2026 (DFW International Airport).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Dallas Fort Worth International Airport Board | |
| Category | Airports | |
| Amount | US$3 billion (US dollars), as of August 2024 | DFW International Airport |
| What the amount covers | Capital estimate, approx. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$3 bn | Capital estimate, approx. | Whole project | Aug 2024 | DFW International Airport |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Austin Commercial / Azteca Enterprises / Alpha & Omega joint venture | design-build contractor | Terminal C first phase and expansion, and Terminal A expansion | DFW International Airport |
| HOK with Muller & Muller, Ltd. | design partners | Terminal C | DFW International Airport |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| August 29, 2024 | announcement | Whole project | DFW International Airport |
| 2030 | planned completion | Whole project | DFW International Airport |
About the project
Phased reconstruction of DFW's busiest and most outdated terminal: removal of more than 400 view-blocking columns, new dynamic glass windows and a raised roof, all-new shops, restaurants, lounge space, check-in areas and security checkpoints, pier expansions adding 115,000 sq ft and four gates at Terminal C and 140,000 sq ft and five gates at Terminal A, and a completely rebuilt south parking garage. The design-build team for the Terminal C project's first phase and expansion and for the Terminal A expansion is a joint venture of Austin Commercial, Azteca Enterprises and Alpha & Omega, with HOK and Muller & Muller, Ltd. as design team members. Approximately $3 billion; the release of August 29, 2024 announced it as the start of work on the airport's nearly $9 billion DFW Forward capital plan, and overall completion of the terminal is expected in 2030. The pier-style expansion at Terminal C is complete (nine gates: five fully rebuilt and four entirely new) and the reconstruction continues in phases.
Sources
- DFW Airport Announces Start of Transformational Work on $9 Billion Capital Plan with Reimagining of Terminal C, DFW International Airport, 29 Aug 2024. Body: 'The approximately $3 billion project will transform the airport's busiest'; completion expected in 2030. Consulted 12 Nov 2026.
- Terminal C Construction & Improvement Project, DFW International Airport. Project page: 'approximately $3 billion project'; 'The pier-style expansion at Terminal C is now complete, adding nine gates'; south garage reconstruction then the two other garages; fact sheet file dated October 2026. Consulted 12 Nov 2026.