Palma de Mallorca airport: processor building and Module A works

Location
Palma, Mallorca, Balearic Islands, Spain. See it on the map, in 3D
Stage
Under construction, as of August 13, 2026 (Aena). Aena said in August 2026 that the remodelling, of which this is the main contract, was in its last phase of works.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAena S.M.E., S.A.
TypeAirports
Headline amountEUR 223.9 million (EUR), as of October 2019Aena
What it coversBudget.
Sourced facts of the project

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€198 MContract valueaward, VAT not statedApril 26, 2022Aena
€224 MBudgettender budget published October 2019October 2019Aena
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Aena S.M.E., S.A.OwnerAena
Acciona Construcción S.A.General contractorother final bidder: Sacyr Construcción (223,480,885.47)Aena
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
October 2019Tender published in the OJEUAena
April 26, 2022Aena board awards the contract to AccionaAena
November 3, 2025Programme more than 70% executedAena
2026 (planned)Last year of worksAena
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

This is the largest contract of the Palma airport remodelling: the processor building, Module A and the stands of Module A's west and east extensions. Aena awarded it to Acciona Construcción on 26 April 2022 for 198.5 million euros, against a tender budget of 223.9 million. Works run at night in a terminal that stays open, with 2026 given as the last year of works.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.