Lisbon Humberto Delgado airport: Terminal 1 South Pier expansion

Location
Lisboa, Lisbon, Portugal. See it on the map, in 3D
Stage
Under construction, as of January 7, 2026 (ECO). On 7 January 2026 the minister visited the South Pier works, with 150 workers on site and 300 expected at the peak.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
ConcessionaireANA, Aeroportos de Portugal, S.A. (VINCI Airports)
TypeAirports
Headline amountEUR 233 million (EUR), as of November 27, 2024VINCI Concessions newsroom (ANA, VINCI Airports)
What it coversContract value, Terminal 1 main works contract, VAT not stated.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
South pier area33,000 m2Terminal 1 South PierVINCI Concessions newsroom (ANA, VINCI Airports)
Boarding bridges10 bridgesSouth PierVINCI Concessions newsroom (ANA, VINCI Airports)
Aircraft stands12 standsSouth PierVINCI Concessions newsroom (ANA, VINCI Airports)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€233 MContract valueTerminal 1 main works contract, VAT not statedNovember 27, 2024VINCI Concessions newsroom (ANA, VINCI Airports)
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
ANA, Aeroportos de Portugal, S.A. (VINCI Airports)Concessionaireworks clientVINCI Concessions newsroom (ANA, VINCI Airports)
Mota-EngilGeneral contractorleader of the Terminal 1 consortiumVINCI Concessions newsroom (ANA, VINCI Airports)
VINCI Construction Grands ProjetsGeneral contractorTerminal 1 consortiumVINCI Concessions newsroom (ANA, VINCI Airports)
Alves RibeiroGeneral contractorTerminal 1 consortiumVINCI Concessions newsroom (ANA, VINCI Airports)
HCIGeneral contractorTerminal 1 consortiumVINCI Concessions newsroom (ANA, VINCI Airports)
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
November 27, 2024Terminal 1 main contract signedVINCI Concessions newsroom (ANA, VINCI Airports)
January 7, 2026150 workers on siteECO
2027 (planned)Terminal 1 South Pier completionVINCI Concessions newsroom (ANA, VINCI Airports)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A new South Pier of 33,000 m2 is being added to Terminal 1 of Lisbon's Humberto Delgado airport, with 10 boarding bridges and 12 aircraft stands, and the Central Pier is remodelled to join it. ANA signed the 233 million euro main contract with a consortium led by Mota-Engil, with VINCI Construction Grands Projets, Alves Ribeiro and HCI, in November 2024. Completion is planned for 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.