Reviewed record
Linha do Alentejo: Poceirão-Bombel modernisation and doubling
- Location
- Palmela, Montijo and Vendas Novas, Lisbon / Alentejo, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of July 2026 (Infraestruturas de Portugal). The works were consigned on 2026-07-27, after the contract was signed on 2026-07-09.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Infraestruturas de Portugal | |
| Type | Rail | |
| Headline amount | EUR 270 million (EUR), as of July 2026 | Infraestruturas de Portugal |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 25 km | Poceirão-Bombel doubling | Infraestruturas de Portugal |
| Length | 10 km | Concordância do Poceirão | Infraestruturas de Portugal |
| Design speed | 200 km/h | conventional passenger trains (220 km/h tilting) | Infraestruturas de Portugal |
| Freight train length | 750 m | design train | Infraestruturas de Portugal |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €167 M | Contract value | works contract, 1,490 days, VAT not stated; tender estimated value EUR 170M excl. VAT | July 2026 | O Minho |
| €270 M | Total project cost | global investment of the scheme, VAT not stated | July 2026 | Infraestruturas de Portugal |
| €98 M | Investment programme | EU funds through Sustentável 2030 | July 2026 | Infraestruturas de Portugal |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Infraestruturas de Portugal | Owner | Infraestruturas de Portugal | |
| ZAGOPE - Construções e Engenharia | General contractor | sole contractor, Oeiras | O Minho |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 9, 2026 | Works contract signed with Zagope | O Minho |
| July 27, 2026 | Works consigned | Infraestruturas de Portugal |
About the project
Infraestruturas de Portugal is doubling and modernising about 35 km of the Linha do Alentejo between Poceirão and Bombel, in Palmela, Montijo and Vendas Novas, part of the freight corridor to Spain. Zagope signed the EUR 167 million works contract on 9 July 2026 and the works were consigned on 27 July, within a global investment of EUR 270 million. The line will take 750 m freight trains and passenger trains up to 200 km/h, with completion planned for 2030.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Linha do Alentejo: consignação da modernização e duplicação do troço Poceirão-Bombel, Infraestruturas de Portugal (owner), 27 Jul 2026. Consulted 26 Nov 2026.
- Grupo de Famalicão perde obra ferroviária de 167 milhões para construtora de Oeiras, O Minho (press), 19 Jul 2026. Consulted 26 Nov 2026.