Loja bypass: Valle del Genil section

Location
Loja, Salar and Huétor-Tájar, Granada, Andalusia, Spain. See it on the map, in 3D
Stage
Under construction, as of February 2026 (Ceacop (citing Granada Hoy)). Awarded on 8 October 2025; preliminary works (tree clearing, site signalling) began in late January and February 2026.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
Headline amountEUR 341 million (EUR), as of February 21, 2025La Moncloa (Ministry of Transport)
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length7.9 kmsectionRailway News
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€283 MContract valueaward, VAT not stated by the sources; equals the 234.12 million excl. VAT plus 21% VATOctober 8, 2025Railway News
€282 MContract valuetender estimated valueApril 21, 2025BOE
€341 MBudgettender budget, VAT includedFebruary 21, 2025La Moncloa (Ministry of Transport)
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerLa Moncloa (Ministry of Transport)
Puentes y Calzadas InfraestructurasGeneral contractorUTE memberCeacop (citing Granada Hoy)
Rover InfraestructurasGeneral contractorUTE memberCeacop (citing Granada Hoy)
GeotúnelGeneral contractorUTE memberCeacop (citing Granada Hoy)
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
December 2024Construction project approvedLa Moncloa (Ministry of Transport)
April 21, 2025Works tender publishedBOE
October 8, 2025Works awarded to the Puentes y Calzadas, Rover and Geotúnel UTECeacop (citing Granada Hoy)
February 2026Preliminary works start: tree clearing and site signalling near km 400Ceacop (citing Granada Hoy)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Valle del Genil is the 7.9 km eastern section of the Loja bypass on the Antequera-Granada high-speed line, through Loja, Salar and Huétor-Tájar. It includes the 794 m Genil viaduct over the river and the A-92, the 693 m Salar viaduct and the 1.3 km Cerro de los Limones tunnel. Adif AV awarded it on 8 October 2025 for EUR 283.3 million including VAT to Puentes y Calzadas Infraestructuras, Rover Infraestructuras and Geotúnel, and preliminary works began in early 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources