Madrid Puerta de Atocha through station

Location
Madrid (Arganzuela district), Community of Madrid, Spain. See it on the map, in 3D
Stage
Under construction, as of February 2026 (Madridactual). The works contract was awarded in January 2024. In February 2026 the city government said it was authorising small occupations so that Adif could work on ventilation shafts and emergency rooms.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
AmountNot found in the sources consulted
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Tracks4new through tracksLa Moncloa (Ministry of Transport)
Platforms2new platformsLa Moncloa (Ministry of Transport)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€452 MContract valueworks award, VAT not statedJanuary 31, 2024La Moncloa (Ministry of Transport)
€497 MContract valuetender estimated valueJune 22, 2023BOE
€505 MInvestment programmeinvestment reported by the press, VAT not statedSeptember 19, 2025El Debate
€550 MLoanEIB loan to Adif for Atocha capacity works: tracks 16 and 17, through station, historic canopy, square, and the Madrid-Levante to Madrid-Barcelona linkDecember 6, 2023European Investment Bank
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerLa Moncloa (Ministry of Transport)
DragadosGeneral contractorUTE member, share not statedLa Moncloa (Ministry of Transport)
TecsaGeneral contractorUTE member, share not statedLa Moncloa (Ministry of Transport)
Constructora San JoséGeneral contractorUTE member, share not statedLa Moncloa (Ministry of Transport)
Puentes y CalzadasGeneral contractorUTE member, share not statedLa Moncloa (Ministry of Transport)
European Investment BankLenderEUR 550 million loan covering this and other Atocha worksEuropean Investment Bank
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
June 22, 2023Works tender published (expediente 3.23/20830.0127)BOE
December 6, 2023EIB approves a EUR 550 million loan for the Atocha capacity worksEuropean Investment Bank
January 31, 2024Works awarded to the Dragados, Tecsa, San José and Puentes y Calzadas UTELa Moncloa (Ministry of Transport)
February 3, 2026City authorises small site occupations for ventilation shafts and emergency rooms; full closure of Méndez Álvaro delayed at least a yearMadridactual
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Adif AV is building an underground through station under Madrid Puerta de Atocha and calle de Méndez Álvaro, with four new tracks and two platforms. It will let high-speed trains run through Atocha between the tunnel to Chamartín and the southern access to Madrid. The works were awarded in January 2024 for EUR 451.6 million to a joint venture of Dragados, Tecsa, San José and Puentes y Calzadas, with an execution period of about seven years.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.