Reviewed record
Madrid Metro Line 5 extension: Alameda de Osuna to Airport T1-T2-T3
- Location
- Madrid (Barajas district: Alameda de Osuna, Madrid-Barajas airport), Community of Madrid, Spain. See it on the map, in 3D
- Stage
- Under construction, as of May 19, 2025 (El Debate). The Comunidad de Madrid started the works on 19 May 2025, after the contract was formalised on 11 April 2025; completion is planned in 2028.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Comunidad de Madrid, Dirección General de Infraestructuras de Transporte Colectivo | |
| Type | Urban transit | |
| Headline amount | EUR 189.2 million (EUR), as of May 19, 2025 | Comunidad de Madrid |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Track length | 3,922.714 m | new track | Comunidad de Madrid |
| Length | 1.7 km | route length | El Debate |
| Turnback tracks | 4 tracks of 210 m | new yard for eight trains | El Debate |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €181 M | Contract value | works award as reported, VAT not stated | December 4, 2024 | El Debate |
| €189 M | Budget | award budget of the works contract and two complementary service contracts, incl. VAT | May 19, 2025 | Comunidad de Madrid |
| €15 M | Investment programme | Aena maximum contribution | May 19, 2025 | Comunidad de Madrid |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Comunidad de Madrid, Dirección General de Infraestructuras de Transporte Colectivo | Owner | Comunidad de Madrid | |
| FCC Construcción, Sacyr Construcción and Becsa (Grupo Simetría), UTE Aeropuerto L5 | General contractor | shares not found; 36-month term | El Debate |
| Aena | Lender | co-funder, up to 15 million euros | Comunidad de Madrid |
| European Union, FEDER 2021-2027 programme of the Comunidad de Madrid | Lender | EU co-financing rate 40% | Comunidad de Madrid |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 4, 2024 | Works awarded to FCC, Sacyr and Becsa | El Debate |
| May 19, 2025 | Start of works | El Debate |
| 2028 (planned) | End of works | Comunidad de Madrid |
About the project
Line 5 of the Madrid Metro is being extended from Alameda de Osuna to the airport's T1-T2-T3 station, where it will connect with Line 8 and let riders cross the city from Carabanchel to the airport without changing. The route is about 1.7 km in tunnel under the M-11 and M-14. FCC, Sacyr and Becsa won the works for 181 million euros; the Comunidad de Madrid started works in May 2025 and plans to finish in 2028. Aena contributes up to 15 million euros.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Obras para la ampliación de la Línea 5 del Metro de Madrid al Aeropuerto Adolfo Suárez Madrid-Barajas (ficha FEDER), Comunidad de Madrid (government), 19 May 2025. Consulted 26 Nov 2026.
- FCC, Sacyr y Becsa se adjudican por 181 millones la nueva conexión de Metro con el aeropuerto de Barajas, El Debate (press), 4 Dec 2024. Consulted 26 Nov 2026.
- Esta será la nueva conexión de Metro de Madrid con el aeropuerto de Barajas, El Debate (press), 20 May 2025. Consulted 26 Nov 2026.
- Prolongación de la Línea 5 de Metro, Comunidad de Madrid (government), 10 Apr 2026. Consulted 26 Nov 2026.