Reviewed record
Madrid Metro Line 6 (Circular) automation programme
- Location
- Madrid (whole Line 6 ring), Community of Madrid, Spain. See it on the map, in 3D
- Stage
- Under construction, as of May 6, 2026 (Comunidad de Madrid). Line renovation works ran from June 2025; the systems contracts were signed in January 2025 and the platform adaptation contract was awarded in May 2026. Driverless operation is planned for 2027.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Metro de Madrid, S.A. | |
| Type | Urban transit | |
| Headline amount | Nearly EUR 231 million (EUR), as of May 6, 2026 | Comunidad de Madrid |
| What it covers | Budget, approx. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Stations | 28 stations | whole line | Comunidad de Madrid |
| Length | 23 km | line length | Comunidad de Madrid |
| Trains | 48 trains | new driverless trains | Comunidad de Madrid |
| Technical rooms | 60 rooms | technical rooms renovated | Comunidad de Madrid |
| Ridership | 430,000 users per day | current | Comunidad de Madrid |
| Headway | 2 minutes | after automation; capacity +17% | Comunidad de Madrid |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €1 bn | Investment programme | whole Line 6 transformation incl. 48 trains, VAT not stated | May 6, 2026 | Comunidad de Madrid |
| €531 M | Contract value | 48 new driverless trains | May 6, 2026 | Comunidad de Madrid |
| Nearly €231 M | Budget | infrastructure renewal | May 6, 2026 | Comunidad de Madrid |
| €112 M | Budget | platform doors | May 6, 2026 | Comunidad de Madrid |
| €85 M | Budget | signalling | May 6, 2026 | Comunidad de Madrid |
| €69 M | Contract value | CBTC signalling works, Alstom Movilidad, excl. VAT (83,500,030.74 incl. VAT); modified +719,840.60 excl. VAT on 2025-12-15 | January 16, 2025 | Portal de Contratación Pública de la Comunidad de Madrid (Metro de Madrid) |
| €8 M | Contract value | platform adaptation at 28 stations, ten months | May 6, 2026 | Comunidad de Madrid |
| €10 M | Budget | renovation of 60 technical rooms (tender announced) | March 23, 2025 | Comunidad de Madrid |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Metro de Madrid, S.A. | Owner | Comunidad de Madrid, Consejería de Vivienda, Transportes e Infraestructuras | Portal de Contratación Pública de la Comunidad de Madrid (Metro de Madrid) |
| Alstom Movilidad | Contractor, one lot | CBTC signalling, contract of 2025-01-16, single bid | Portal de Contratación Pública de la Comunidad de Madrid (Metro de Madrid) |
| UTE Puertas Andén Línea 6 (Faiveley Transport Ibérica, COMSA Instalaciones y Sistemas Industriales, COMSA) | Contractor, one lot | platform screen doors | Portal de Contratación Pública de la Comunidad de Madrid (Metro de Madrid) |
Milestones
| Date | Milestone | Source |
|---|---|---|
| June 2025 | Integral renovation works begin, south-west arc then north-east arc | Comunidad de Madrid |
| May 6, 2026 | Platform adaptation contract (8 million, ten months) awarded | Comunidad de Madrid |
| 2027 (planned) | Driverless operation | Comunidad de Madrid |
About the project
Metro de Madrid is converting Line 6, the Circular, into the first driverless line of its network. The programme renews the track and infrastructure, raises the platforms of all 28 stations and fits them with platform screen doors, rebuilds 60 technical rooms, installs CBTC signalling (Alstom) and buys 48 driverless trains. The Comunidad de Madrid puts the total at more than 1,000 million euros and plans driverless service in 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- La Comunidad de Madrid adecúa los andenes de las 28 estaciones de la Circular de Metro para convertirla en la primera línea sin conductor de la red, Comunidad de Madrid (government), 6 May 2026. Consulted 26 Nov 2026.
- La Comunidad de Madrid invierte 10 millones en la renovación de los cuartos técnicos que alojarán los equipos para la automatización de la L6 de Metro, Comunidad de Madrid (government), 23 Mar 2025. Consulted 26 Nov 2026.
- Suministro, instalación, puesta en servicio y mantenimiento de puertas de andén en la Línea 6 de Metro de Madrid (C6079), Portal de Contratación Pública de la Comunidad de Madrid (Metro de Madrid) (government), 5 Aug 2024. Consulted 26 Nov 2026.
- Obras de actualización sistema señalización y CBTC asociados a la renovación de material móvil y plataforma de vía de la línea 6 de Metro de Madrid (C7736), Portal de Contratación Pública de la Comunidad de Madrid (Metro de Madrid) (government), 20 Dec 2024. Consulted 26 Nov 2026.