Reviewed record
Porto Metro Ruby line (H): Casa da Música to Santo Ovídio, with the Ferreirinha bridge
- Location
- Porto (Boavista, Campo Alegre) and Vila Nova de Gaia (Arrábida, Candal, Devesas, Santo Ovídio), Norte, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of April 18, 2026 (Observador (Lusa)). Works began with the consignação in January 2024. In April 2026 the project documents set 22 July 2028 as the general end of works, with the bridge deck to be completed in April 2028.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Metro do Porto, S.A. | |
| Type | Urban transit | |
| Headline amount | EUR 487.9 million (EUR), as of April 18, 2026 | Observador (Lusa) |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 6.27 km | between station axes, execution project | Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) |
| Length | 6.4 km | line length as reported | ECO |
| Stations | 8 stations | incl. existing Casa da Música; seven new | Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) |
| Bridge length | 838 m | Ponte Ferreirinha | Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) |
| Ridership | 12 million additional passengers per year | forecast | ECO |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €380 M | Contract value | main works contract, VAT not stated | January 2024 | ECO |
| €488 M | Budget | infrastructure project budget, VAT not stated | April 18, 2026 | Observador (Lusa) |
| €299 M | Investment programme | PRR 100% financing originally allocated to the line | August 2023 | Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) |
| €24 M | Contract value | signalling tender relaunched (not awarded) | April 2026 | Observador (Lusa) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Metro do Porto, S.A. | Owner | Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) | |
| ACA - Alberto Couto Alves | General contractor | consortium member, shares not found | ECO |
| FCC Construcción | General contractor | consortium member | ECO |
| Contratas y Ventas | General contractor | consortium member | ECO |
| Profico Ambiente e Ordenamento | Engineer | author of the RECAPE environmental compliance report | Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) |
Milestones
| Date | Milestone | Source |
|---|---|---|
| January 2024 | Start of works (consignação) | ECO |
| March 2027 (planned) | Porto tunnel (Campo Alegre) to be finished | Observador (Lusa) |
| April 2027 (planned) | Gaia tunnel (Santo Ovídio to Devesas) to be finished | Observador (Lusa) |
| April 2028 (planned) | Bridge deck completed | Observador (Lusa) |
| July 22, 2028 (planned) | General end of works | Observador (Lusa) |
About the project
The Ruby line is a 6.4 km metro line linking Casa da Música in Porto with Santo Ovídio in Vila Nova de Gaia, with eight stations and a new bridge over the Douro, the Ponte D. Antónia Ferreira (Ferreirinha), reserved for the metro, pedestrians and cyclists. The ACA, FCC Construcción and Contratas y Ventas consortium won the 379.5 million euro works contract in 2023 and works started in January 2024. The end of works is now set for July 2028 and the project budget at 487.9 million euros.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Relatório de Conformidade Ambiental do Projeto de Execução da Linha Casa da Música - Santo Ovídio (Linha Rubi), Resumo Não Técnico, Metro do Porto / Profico Ambiente (RECAPE, Resumo Não Técnico) (owner), 16 Aug 2023. Consulted 26 Nov 2026.
- Linha Rubi vai acrescentar 12 milhões de utilizadores por ano ao Metro do Porto, ECO (press), 9 Jan 2024. Consulted 26 Nov 2026.
- Prazo das obras da Linha Rubi do Metro do Porto derrapa mais de um ano para 2028, Observador (Lusa) (press), 18 Apr 2026. Consulted 26 Nov 2026.
- Ponte Ferreirinha sobre o rio Douro, Construção Magazine (press), 19 May 2025. Consulted 26 Nov 2026.