Linha do Norte: Ovar (Válega)-Espinho renewal
- Location
- Válega (Ovar) to Espinho, via Ovar and Esmoriz, Centro / Norte, Portugal. See it on the map, in 3D
- Stage
- Under construction, as of June 2026 (ECO). The works contract was signed and the works started on 2026-06-24.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Infraestruturas de Portugal | |
| Type | Rail | |
| Headline amount | EUR 160 million (EUR), as of June 2026 | Governo de Portugal |
| What it covers | Total project cost. |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €76 M | Contract value | works contract, VAT not stated (EUR 75,996,030 per a procurement aggregator, not an official source) | June 2026 | Governo de Portugal |
| €160 M | Total project cost | total investment on the Ovar-Espinho section (works plus other items), VAT not stated | June 2026 | Governo de Portugal |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Infraestruturas de Portugal | Owner | Governo de Portugal | |
| Somafel - Engenharia e Obras Ferroviárias | General contractor | consortium member, share not stated | ECO |
| Construções Gabriel Couto | General contractor | consortium member, share not stated | ECO |
| Teixeira Duarte | General contractor | consortium member, share not stated | ECO |
About the project
Infraestruturas de Portugal is renewing 19 km of the Linha do Norte between Válega, in Ovar, and Espinho, south of Porto. A consortium of Somafel, Gabriel Couto and Teixeira Duarte holds the EUR 76 million works contract, started in June 2026 for three years, within a wider investment of EUR 160 million on the section. The works replace the track and catenary, rework Ovar and Esmoriz stations, add freight refuge sidings and remove level crossings.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Investimento de 200 milhões de euros nas linhas do Norte e do Minho, Governo de Portugal (government), 24 Jun 2026. Consulted 26 Nov 2026.
- Arrancam obras de 101 milhões nas linhas do Norte e Minho, ECO (press), 24 Jun 2026. Consulted 26 Nov 2026.