Reviewed record

Burgos-Vitoria high-speed line: Burgos bypass-Valle de las Navas section

Location
Burgos, Rubena, Quintanapalla and Valle de las Navas, Burgos, Castile and León, Spain. See it on the map, in 3D
Stage
Contract awarded, works not confirmed, as of July 2026 (BURGOSconecta). The contract was awarded on 2026-07-01; works were expected to start in the last quarter of 2026, and no start of works was found.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerAdif Alta Velocidad
TypeRail
AmountNot found in the sources consulted
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length16.7 kmsectionBURGOSconecta
Viaducts6sectionBURGOSconecta
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€113 MContract valueaward excl. VAT (EUR 136.6M incl. VAT), 14.4% below the base budgetJuly 2026BURGOSconecta
€137 MContract valueaward incl. VATJuly 2026BURGOSconecta
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Adif Alta VelocidadOwnerBURGOSconecta
Gevora ConstruccionesGeneral contractorUTE member, share not statedBURGOSconecta
CopisaGeneral contractorUTE member, share not statedBURGOSconecta
Construcciones SarriónGeneral contractorUTE member, share not statedBURGOSconecta
GeoxaGeneral contractorUTE member, share not statedBURGOSconecta
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
July 1, 2026Works awarded; 13 bids receivedBURGOSconecta
December 2026 (planned)Start of works expected in the last quarter of 2026BURGOSconecta
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The second section of the Burgos-Vitoria high-speed line to be contracted: 16.7 km of platform from the Burgos rail bypass to Valle de las Navas, through Rubena and Quintanapalla, with six viaducts including a 643 m viaduct over the Río Vena. A joint venture of Gevora Construcciones, Copisa, Construcciones Sarrión and Geoxa won it on 1 July 2026 for EUR 136.6 million including VAT, with 42 months of works expected to start in late 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.