Reviewed record
València rail access canal and Joaquín Sorolla station remodelling
- Location
- València (Quatre Carreres, Jesús and L'Eixample districts), Valencian Community, Spain. See it on the map, in 3D
- Stage
- Under construction, as of July 2026 (elDiario.es). Works began in May 2023; in July 2026 the press reported them advancing towards completion in mid-2028.
- Status
- Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Adif Alta Velocidad | |
| Type | Rail | |
| Headline amount | EUR 665 million (EUR), as of March 11, 2024 | Ministerio de Transportes y Movilidad Sostenible |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Tracks | 10 | standard-gauge tracks at Joaquín Sorolla | Valencia Plaza |
| Collector diversion length | 2 km | southern sewer collector diversion | Valencia Plaza |
| Parking spaces added | 300 | Joaquín Sorolla car park | elDiario.es |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €665 M | Total project cost | planned investment for the access canal and Joaquín Sorolla remodelling, VAT not stated | March 11, 2024 | Ministerio de Transportes y Movilidad Sostenible |
| €443 M | Contract value | main works award, VAT included (tender budget EUR 453.7 million) | December 2022 | Valencia Plaza |
| €31 M | Contract value | adaptation of signalling and communications installations, VAT included | March 11, 2024 | Ministerio de Transportes y Movilidad Sostenible |
| €17 M | Contract value | tender estimated value, installations of the new Joaquín Sorolla rail access, 48 months | April 27, 2026 | BOE |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Adif Alta Velocidad | Owner | with the Generalitat Valenciana and València city council | Ministerio de Transportes y Movilidad Sostenible |
| Dragados | General contractor | UTE member, 45% | Valencia Plaza |
| Rover Infraestructuras | General contractor | UTE member, 20% | Valencia Plaza |
| Rover Rail | General contractor | UTE member, 20% | Valencia Plaza |
| Tecsa Empresa Constructora | General contractor | UTE member, 15% | Valencia Plaza |
| GTS Transportation Spain | Contractor, one lot | signalling and communications adaptation, EUR 31.3 million incl. VAT | Ministerio de Transportes y Movilidad Sostenible |
| Sener Mobility | Designer | basic design of the future central station (a later phase), EUR 6.1 million | elDiario.es |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 28, 2022 | Main works awarded to the Dragados, Rover and Tecsa UTE | Valencia Plaza |
| May 2023 | Works begin | elDiario.es |
| March 11, 2024 | Signalling and communications adaptation awarded to GTS Transportation Spain; EUR 37 million executed on the main works | Ministerio de Transportes y Movilidad Sostenible |
| April 27, 2026 | Tender for the installations of the new Joaquín Sorolla rail access | BOE |
| 2028 (planned) | End of works and demolition of the Giorgeta viaduct (mid-2028) | elDiario.es |
About the project
Adif AV is putting underground every track that enters València Nord and Joaquín Sorolla stations, extending the Nudo Sur tunnels north from Avenida Fernando Abril Martorell, and remodelling Joaquín Sorolla station with ten standard-gauge tracks. The main works were awarded in December 2022 to a Dragados, Rover and Tecsa joint venture for EUR 443.3 million including VAT. Works started in May 2023 and are due to end in 2028, when the Giorgeta road viaduct comes down.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Transportes adjudica por 31,3 millones de euros la adecuación de las instalaciones de comunicación y seguridad para desarrollar el Canal de Acceso a Valencia, Ministerio de Transportes y Movilidad Sostenible (government), 11 Mar 2024. Consulted 26 Nov 2026.
- Así cambiará València: el canal de acceso prevé estar terminado en 2027, Valencia Plaza (press), 2 Jan 2023. Consulted 26 Nov 2026.
- Adif adjudica a la UTE Dragados-Rover las obras del canal de acceso de València, Valencia Plaza (press), 28 Dec 2022. Consulted 26 Nov 2026.
- Anuncio de licitación: instalaciones del nuevo acceso ferroviario a València Joaquín Sorolla, BOE (government), 27 Apr 2026. Consulted 26 Nov 2026.
- Las obras del túnel ferroviario de València finalizarán en 2028 con la demolición del 'scalextric' de Giorgeta, elDiario.es (press), 7 Jul 2026. Consulted 26 Nov 2026.