A-7 Valencia by-pass upgrade: CV-32 junction to CV-35 junction (km 313 to 324)

Location
El Puig, Rafelbunyol, Massamagrell, Museros, Moncada, Bétera, Valencia, Godella and Paterna, Valencia, Valencian Community, Spain. See it on the map, in 3D
Stage
Under construction, as of November 24, 2026 (Ministerio de Transportes). The Ministry said on 24 November 2026 that the lateral carriageways between the CV-32 and CV-35 junctions are currently under construction.
Status
Reviewed record: compiled from the sources below (the owners, the procurement records and gazettes, the companies, the funders and the press), each fact checked against its source on 26 Nov 2026, the record reviewed on 27 Nov 2026.
Research as of

Who, what, how much

FieldValueSource
OwnerMinisterio de Transportes y Movilidad Sostenible, Dirección General de Carreteras
TypeHighways
Headline amountEUR 143.8 million (EUR), as of July 30, 2021Valencia News
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

FieldValueScopeSource
Length11 kmkm 313 to km 324Valencia News
Lateral carriageways2 carriagewaysone on each side of the existing by-passValencia News
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

AmountWhat it isScopeAs ofSource
€91 MContract valueselected offer (BOE), excl. VATMarch 1, 2022Boletín Oficial del Estado
€144 MBudgetestimated contract value at tender (press, 2021)July 30, 2021Valencia News
Amounts, each with its kind and scope

Companies and their roles

CompanyRoleNoteSource
Ministerio de Transportes y Movilidad Sostenible, Dirección General de CarreterasOwnerBoletín Oficial del Estado
Dragados and Pavasal (UTE)General contractorShares not stated; 11 bidsBoletín Oficial del Estado
TYPSA and MC2 (UTE)SupervisionControl and surveillance, EUR 2,414,900.00, awarded 2022-03-11Boletín Oficial del Estado
Companies and public bodies named by a source, each with its role

Milestones

DateMilestoneSource
December 3, 2020Route project approvedBoletín Oficial del Estado
March 1, 2022Works awarded to Dragados-PavasalBoletín Oficial del Estado
May 3, 2024Modification No.1 route project approvedBoletín Oficial del Estado
November 24, 2026Ministry: lateral carriageways under constructionMinisterio de Transportes
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The Ministry of Transport is adding a lateral carriageway on each side of 11 km of the A-7 Valencia by-pass, between the CV-32 junction at km 313 and the CV-35 junction at km 324, to separate local traffic from through traffic. Dragados and Pavasal won the contract in March 2022 with an offer of EUR 91.2 million excluding VAT. The lateral carriageways were still under construction in November 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.